Construction of NR10 Connecting Battambang to Koh Kong 54% Complete

By the end of November 2021, the construction of 198km NR10 connecting Battambang to Koh Kong was 54.89% completed, according to the site inspection by the Minister of Public Works and Transport (MPWT) HE Sun Chanthol Friday 3 December.

HE Sun Chanthol also urged construction companies and technical consultants to closely monitor the construction work to ensure it follows technical standards to ensure long-term usage.

Stretching over 199km, the road links Samlot district in Battambang province to Koh Kong province passing through Veal Veng district in Pursat province. The project is being constructed with an investment of over US$188 million, which is a mixture of a Chinese loan and Cambodian government budget.

The project is being built in accordance with Chinese level 3 technical standards, paved with double-layers DBST, with a total width of 9m.

The route will also include the construction of 23 bridges with a length of 1,721m. Meanwhile, 65.89km of the road is a detour around the Cardamom mountain, as the engineering team try to avoid cutting the mountain to preserve the environment and wildlife.

With ground broken in March 2020, the road is being built by China Road and Bridge Corporation (CRBC) under the technical supervision of Guangzhou Wanan Construction Supervision Co., Ltd. and will take 48 months to complete, which will be around late 2023.

NR10 is an important artery of Cambodia’s national economy, helping connect the Khmer-Thai border to the deep seaport in Sihanoukville through Battambang and Kong Kong. With this route, cargo trucks do not have to pass through Phnom Penh, which is more cost and time effective.

- Video Advertisement -

Related Post

Kampong Speu Irrigation Projects Nearing Completion: Roleang Chrey Canal at 60%, Tasal Reservoir at 90%

Significant progress has been made on critical irrigation projects in Kampong Speu province, according to an inspection visit by H.E. Bun Hean, Secretary of State and Chairman of the Project Inspection Unit of the Ministry of Water Resources and Meteorology, on 15 May 2024. The rehabilitation of the Tasal Reservoir and the North Roleang Chrey […]

Australia Pours US$6.6 Million into Cambodia’s Water Development Fund

In a significant move to bolster Cambodia’s water infrastructure and management capabilities, Australia has pledged AUD10 million (US$6.6 million) to establish a dedicated water development fund, according to a meeting held on 13 May 2024 between Mr. Hem Vandy, Cambodia’s Minister of Industry, Science, Technology and Innovation, and Mr. Pablo Kang, Chargé d’Affaires of the […]

A New Frontier for Conservation: US$520K Canal Project to Shield Techo Sen Russey Trep National Park

In a significant conservation effort, the Royal Academy of Cambodia unveiled plans on 5 May 2024 for the construction of a 52-kilometre-long canal to safeguard the expansive Techo Sen Russey Trep National Park. Spanning 6 meters in width and 2.5 meters in depth, this ambitious US$520,000 project aims to encircle and protect over 10,000 hectares […]

49km of Kratie Province Roads Revitalization Hits Midway Mark: A 53% Completion in Infrastructure Enhancement

As of 8 May 2024, the Kratie Provincial Administration has reported a significant milestone in the enhancement of its transportation infrastructure, with the rehabilitation project of two main provincial roads reaching approximately 53% completion. Spanning nearly 49 km, Provincial Road No. 377 and Road 377A are undergoing extensive improvements to bolster the quality and maintenance […]

Revitalizing Kampot: AZ Group to Invest Up to US$10M in International Tourist Port

AZ Builder, a subsidiary of the prominent Cambodian AZ GROUP, is set to invest between US$ 5 million and US$ 10 million in the rehabilitation of the Kampot International Tourist Port, a project that has faced delays since its inception in 2022. This strategic investment aims to rejuvenate the port, enhancing its accessibility for ships […]

Kratie’s Mekong River Bridges Approach Halfway Mark in $111 Million Project

The ambitious project to construct bridges across the Mekong River in Kratie province, valued at US$111 million,  has surged ahead, with completion surpassing 49% as of early May 2024 while the road connection component stands at an impressive 36.24%. This milestone was confirmed by the Ministry of Public Works and Transport’s official Facebook page on […]