Construction of New Siem Reap Airport 42% Complete

The construction of the new Siem Reap Angkor International Airport is approximately 42% completed although some works have been disrupted by the COVID-19 pandemic.

Spokesman of the Secretariat of Civil Aviation of Cambodia HE Sin Chansereyvutha told Construction & Property Magazine on 12 May that the three main parts of the construction are on schedule.

“Although some technical works have been disrupted, the progress of the construction is still proceeding as scheduled, because the firm has added more labour to work both day and night shifts,” said HE Chansereyvutha.

According to the Angkor International Airport Investment (Cambodia) Co., Ltd. (AIAI), the construction progress is set for 67% completion by the end of 2021. (Read more)

The new airport is located in Sot Nikom district, approximately 51km from Siem Reap downtown or 40km from Angkor Wat. The construction began on 15 March 2020 and is scheduled to be completed by 2023.

The airport is being built on a 700-hectare plot with a 1,000-hectare special economic zone with an investment of over US$900 million. (Read more)

- Video Advertisement -

Related Post

ADB demonstrates support for clean water development in Cambodia through a USD 400 million large-scale financing project by 2025

The Asian Development Bank (ADB) is committed to further strengthening urban development in Cambodia through the USD400 million Large-Scale Financing (MFF) project, which is scheduled for approval by the end of 2025. The initiative comes after the success of an ongoing USD119 million project in the Battambang and Kampong Cham provinces. This was stated in […]

The 250 km Cambodia Border Ring Road is starting the construction under FBID’s Nearly USD 27 Million

The Government of Cambodia opened the construction of a 250 km border ring road under the Foundation for Border Infrastructure Development (FBID) of USD 26,967.609 million on November 1, 2024, and is scheduled to be completed by the end of April 2027.a This was confirmed by HE Kim Bunthan, Chairman of the Working Group for […]

Blyncsy Publishes Map of U.S. Interstate Highways Showing Roadway Assets to Enhance Safety, Maintenance, and Accelerate the Digital Infrastructure Movement Nationally

Blyncsy empowers state DOTs with the ability to monitor and compare—in near real-time—the status of any major highway in the continental U.S. with their existing data for more informed decision-making. PHILADELPHIA — 2024 AASHTO Annual Meeting & Expo — October 29, 2024 — Blyncsy, a Bentley Systems Inc. (Nasdaq: BSY) company, today announced it published a comprehensive public […]

NR No. 10 Rehabilitation Nears Completion with 93% of Work Done and the Tallest Bridge Reaches 79% on Track for Operation in June 2025

By the end of October 2024, construction on Cambodia’s NR No. 10—a crucial route connecting the provinces of Koh Kong, Pursat, and Battambang—has reached an impressive 92.94% completion. Along this route, the tallest bridge, spanning 530 meters, has progressed to 79% completion and is set to be fully operational by June 2025, as reported by […]

Phnom Penh-SHV Expressway to Implement Full Toll Rates from 1 November

The Phnom Penh-Sihanoukville Expressway Company has confirmed it will transition to full toll rates beginning 1 November 2024, concluding a 20% discount period that will end at 00:00 on 31 October. This was detailed in the company’s official announcement, dated 31 October 2024. In continued support of smoother travel, the expressway company will offer Electronic […]

Major Wastewater Treatment Project to Begin on 30 Hectares in Takhmao City

The Ministry of Public Works and Transport has announced an ambitious plan to construct a comprehensive wastewater treatment system over a 30-hectare site in Prek They Village, Roka Khpos Commune, Takhmao City, Kandal Province. The project, which received formal approval during a meeting on 29 October 2024, will be managed under the guidance of HE […]