Progress Update: National Road No. 48 Rehabilitation Reaches 25% Completion

The ongoing rehabilitation and improvement project of National Road No. 48, spanning a length of 148 kilometers, has achieved a significant milestone, with completion reaching 25.57% as of April 2023. This noteworthy progress was reported following a site inspection conducted by Lok Chumteav Mithona Phuthong, the Governor, and Mrs. Inary Net, the Deputy Governor of Koh Kong Province, on May 14, 2023.

During the inspection, Lok Chumteav and her team visited four key locations along the route to assess the project’s advancements.

The first location, starting from Boeung Preav commune in Sre Ambel district, marked the beginning of the road at 0 km.

At the 60 km mark, the inspection focused on the high dam area, followed by an examination of the area to be excavated for filling the low position at the 120 km mark.

Finally, at km 142, attention was directed towards the section featuring four lanes for vehicles. It is worth noting that National Road No. 48 accommodates four lanes for five vehicles.

Based on the inspection findings, it has been determined that the road rehabilitation and improvement project will require an additional 12 months beyond the original deadline. This extension is deemed necessary to ensure the project’s successful completion and the delivery of a high-quality road infrastructure that meets the expected standards.

The National Road No. 48 construction project spans a total length of 148 km, commencing from PK 141+750 (Chamkar Luong) at the intersection of National Road No. 4 to Khemarak Phoumin City, Koh Kong Province. The project, which began on January 3, 2022, with an allocated budget of approximately $78 million, aims to enhance the road’s quality and capacity, facilitating smoother and safer transportation for the region. (Read more)

As progress continues on the rehabilitation of National Road No. 48, infrastructure development in the western part of Cambodia is set to benefit significantly. The completion of this crucial transportation route will not only improve connectivity within the region but also foster economic growth and development opportunities.

- Video Advertisement -

Related Post

The rapid progress of riverbank construction in Kampong Cham has reached 65%

In a remarkable display of swift action and engineering prowess, the construction of a vital riverbank in the Srey Santhor district has surged ahead, reaching an impressive 65% completion in under a month. The Moan Dob Leu village project, Meanchey commune, commenced on December 23, 2024, following the alarming collapse of the Mekong River bank […]

Kampong Cham Province Achieved Significant Infrastructure Development in 2024

In a remarkable stride towards improving its infrastructure, Kampong Cham Province has completed over 119 kilometers of road construction in 2024. This achievement was announced by HE Un Chanda, the Governor of Kampong Cham Province, during a press conference. During the year 2024 alone, the province welcomed 27 projects aimed at developing DBST (Dense Bituminous […]

Major Progress Made on Flood Prevention in Western Phnom Penh

In a significant step towards mitigating flooding in western Phnom Penh, the ambitious drainage and drainage system restoration project has reached a milestone, now standing at 50.50% completion as of January 5, 2025. This essential infrastructure initiative, spearheaded by the General Department of Wastewater Treatment System under the Ministry of Public Works and Transport, aims […]

National Road 7 Expansion Project Progresses, Reaches 28.76% Completion

In a significant step towards enhancing Cambodia’s infrastructure, the ambitious project to restore and expand National Road No. 7 has reached an impressive 28.76% completion as of early January 2025. This major development was confirmed during a thorough inspection led by HE Lim Sidenin, Secretary of State of the Ministry of Public Works and Transport, […]

Progress Report: National Road No. 48 Restoration Nears Completion

The restoration and upgrade of National Road No. 48, stretching 148 kilometers from Sre Ambel to Koh Kong, has reached an impressive 78% completion as of the beginning of 2025, according to a statement from HE Phorn Rim, Spokesman of the Ministry of Public Works and Transport. The ambitious project, which commenced on January 3, […]

Major Infrastructure Development Takes Shape in Kandal Province

The China Road and Bridge Corporation (CRBC) is swiftly constructing a temporary steel bridge in Kandal province to facilitate drilling for a vital clay-stone bridge. HE Phorn Rim, the Ministry of Public Works and Transport spokesman, confirmed that this project aims to improve connectivity between the eastern outskirts of Phnom Penh and Xi Jinping Boulevard. […]