Kampong Cham Province Achieved Significant Infrastructure Development in 2024
In a remarkable stride towards improving its infrastructure, Kampong Cham Province has completed over 119 kilometers of road construction in 2024. This achievement was announced by HE Un Chanda, the Governor of Kampong Cham Province, during a press conference. During the year 2024 alone, the province welcomed 27 projects aimed at developing DBST (Dense Bituminous […]
National Road 7 Expansion Project Progresses, Reaches 28.76% Completion
In a significant step towards enhancing Cambodia’s infrastructure, the ambitious project to restore and expand National Road No. 7 has reached an impressive 28.76% completion as of early January 2025. This major development was confirmed during a thorough inspection led by HE Lim Sidenin, Secretary of State of the Ministry of Public Works and Transport, […]
Progress Report: National Road No. 48 Restoration Nears Completion
The restoration and upgrade of National Road No. 48, stretching 148 kilometers from Sre Ambel to Koh Kong, has reached an impressive 78% completion as of the beginning of 2025, according to a statement from HE Phorn Rim, Spokesman of the Ministry of Public Works and Transport. The ambitious project, which commenced on January 3, […]
Major Infrastructure Development Takes Shape in Kandal Province
The China Road and Bridge Corporation (CRBC) is swiftly constructing a temporary steel bridge in Kandal province to facilitate drilling for a vital clay-stone bridge. HE Phorn Rim, the Ministry of Public Works and Transport spokesman, confirmed that this project aims to improve connectivity between the eastern outskirts of Phnom Penh and Xi Jinping Boulevard. […]
What has the border ring road construction project achieved two months after the construction site opened?
The project to build the border ring road, funded by nearly $27 million from the Border Infrastructure Fund, has made significant progress since the construction site opened on November 4, 2024. Here are some key achievements of this historic project for Cambodia: Demining Operations: The team successfully cleared 1,462,500 square meters of unexploded ordnance, with […]
Dauntri Reservoir Dam Nears Completion with 91% Progress, Set to Open by October 2025
The Dauntri Reservoir Dam project in Battambang province has reached an impressive 91% completion, marking a crucial milestone in its mission to revolutionise water supply and agricultural productivity in the province. This landmark project, designed to enhance irrigation and flood management, is expected to be fully operational by October 2025. The announcement was made during […]