Twin Flyover Construction in Phnom Penh Reaches 25% Completion, Targeting June 2025 for Full Operation

The construction of twin flyovers along Phnom Penh’s 60-metre boulevard at the intersection of National Road 2 has achieved 25% completion, a significant milestone for the project designed to enhance connectivity between Phnom Penh and Kandal province.

This progress, reported by HE Keut Chhe, Deputy Governor of Phnom Penh, was shared on 10 December 2024, marking six months since the project’s initiation on 17 June 2024.

According to HE Keut Chhe, the project’s first bridge—connecting Samdech Hun Sen Boulevard to Phnom Penh International Airport—is slated for completion by April 2025, while the entire project is scheduled to conclude by June 2025.

The twin flyovers are being constructed at a cost exceeding USD 16 million and are designed as reinforced concrete bridges with I-shaped beams. The combined structure measures 622 meters in total length, with the first flyover spanning 281 meters and the second measuring 180 meters. Each bridge is 9.5 meters wide and features three lanes configured for one-way traffic, comprising two main lanes of 3.25 meters each and an additional lane of 2 meters. (Read more)

The development aims to alleviate chronic traffic congestion at this critical junction, which serves as a vital link between Phnom Penh and neighboring provinces.

- Video Advertisement -

Related Post

Pursat Provincial Authorities Inaugurate New Bridge and Kick Off Construction of Nine Rural Roads

In a significant boost to local infrastructure, the Royal Government of Cambodia officially inaugurated a new 75-meter concrete bridge and announced the construction of nine additional rural roads in Pursat Province. The ceremony presided over by His Excellency Chhay Rithsen, Minister of Rural Development, marked a milestone for the community. The newly inaugurated bridge, connecting […]

Bassac River Bridge in Chak Angre Krom–Prek Pra Reaches 51% Completion

As of October 28, 2025, construction of the Bassac River Crossing Bridge connecting Chak Angre Krom to Prek Pra has reached 51% completion, according to the Ministry of Public Works and Transport (MPWT). A recent on-site inspection led by His Excellency Suong Heng, Secretary of State and Project Director, revealed steady progress across key construction […]

National Road 23 Fully Completed, Boosting Connectivity and Regional Growth

The Ministry of Public Works and Transport has officially announced the full completion of the National Road 23 (NR23) upgrade, marking a significant achievement in Cambodia’s ongoing infrastructure development. The announcement was made on October 24, 2025, following the completion of a 19.8-kilometer section designed to improve transportation efficiency and accessibility for local residents. The […]

Kampong Chhnang Province Celebrates Groundbreaking of Six Major Roads Enhancing Rural Development

In a significant step towards improving rural infrastructure, the Ministry of Rural Development held a groundbreaking ceremony today for the construction of six roads spanning over 40.5 kilometers. The event took place in the Teuk Phos and Kampong Tralach districts, with His Excellency Chhay Rithsen, the Minister of the Ministry of Rural Development, presiding over […]

Svay Rieng Province Celebrates New Infrastructure Development

Svay Rieng Province is making significant strides in rural infrastructure development, having successfully constructed 771 rural roads that span nearly 3,000 kilometers. Local authorities are dedicated to further enhancing infrastructure to stimulate economic growth in the region. This commitment was underscored during the recent groundbreaking ceremony for a new 60-meter-long concrete bridge over the Prek […]

Mekong River Bridge Project Nears Completion, Boosting Connectivity in Kratie

The Cambodia-China Friendship Bridge spanning the Mekong River in Kratie province is rapidly approaching completion, marking a major milestone in regional infrastructure development. According to Mr. Phon Rim, spokesperson for the Ministry of Public Works and Transport, overall construction has reached 87.25%, with the bridge itself nearly 100% complete. The project also includes a 32-kilometer […]