New NR4-Monivong Bokor National Park Road Reaches 30% Completion Milestone

The NR4-Monivong Bokor National Park Road, a major infrastructure project connecting the National Road No. 4 to the Bokor mountain, has reached a significant milestone. As of 8 April 2023, the project has reached 30 percent completion, according to Mr Svay Vuthy, a representative of Sokha Hotel Company, which is responsible for the construction of the road. This comes after the completion of site clearance on 1 April 2023. (Read more)

The construction progress was confirmed by Mr Vuthy during the inspection of the project by HE Chea Sophara, Deputy Prime Minister and Minister of Land Management, Urban Planning and Construction.

He added that “the road will be built in steps, with the first step being the construction of a Macadam Road. Once completed, the road will be accessible to high-end cars and motorcycles at a speed of 15 to 20 kilometres per hour.”

The new road, which is approximately 61 kilometers long, will be built with a width of 20 meters, divided into two 3.5-meter-wide car lanes and 3-meter-wide motorbike lanes, with 3.5-meter-wide sidewalks on each side. The plan studied by the Ministry of Public Works and Transport calls for the road to be built with an Asphalt concrete paved road (AC) and the addition of a 200-millimetre-thick concrete floor and rubber for long-term stability.

The new road, built by Sokha Real Estate Co., Ltd, connects National Road No. 4 at km 158+200 in Kampong Seila commune, Prey Nob district, Preah Sihanouk province, towards Bokor mountain, connected with 500 rice fields road. The project, which was approved by the Royal Government in February 2022, will provide better accessibility to the Bokor mountain and boost economic growth in the region.

The NR4-Monivong Bokor National Park Road project is a significant development that will bring numerous benefits to the region. With the completion of site clearance and 30 percent of the construction already complete, it is on track to provide better connectivity and accessibility to the area.

Photo Credit to CCT

- Video Advertisement -

Related Post

Cambodia Records Surge in Investment with Ten Billion Dollars in New Projects for 2025

Cambodia has reached a major economic milestone in 2025, securing 630 new investment projects with a total capital value of approximately 10 billion dollars. This performance represents a significant 45 percent increase in investment volume compared to the previous year, highlighting the Kingdom’s growing appeal as a strategic hub for international capital. The Council for […]

Kandal Province Launches Official Construction of Prek Thnot Riverbank Park to Enhance Urban Beauty

Provincial authorities and Ministry officials join forces to transform the southern riverbank into a modern recreational space for residents and tourists The landscape of Takhmao city is set for a significant aesthetic upgrade following the official groundbreaking of the Prek Thnoat riverbank park project on January 3, 2026. This ambitious development, situated along the southern […]

Battambang Completes Construction of Massive Water Treatment Facility to Meet Growing Urban Demand

New high-capacity plant set to launch in early 2026 will double the provincial capital’s clean water supply through advanced Chinese engineering The skyline of Battambang’s Kampong Seima area has been permanently transformed with the 100 percent completion of the province’s third and largest water treatment plant. This major infrastructure milestone, announced by H.E. Ut Kloeung, […]

Progress Inspection for Wastewater Treatment System Development in Takhmao City

In a significant step towards enhancing the development progress in Takhmao City, HE Ros Vanna, Secretary of State of the Ministry of Public Works and Transport, led a comprehensive inspection of the wastewater treatment system development project in Takhmao City. This project, pivotal for managing urban wastewater, is funded by the Economic Development Cooperation Fund […]

Mekong River Bridge (Dei Edth-Thma Kor) Construction Reaches 36% Completion

The Mekong River Bridge (Dei Edth-Thma Kor) Construction Project has marked a significant milestone, achieving 36% completion as of late December 2025. His Excellency So Vector, Secretary of State for the Ministry of Public Works and Transport and Managing Director of the project, led a team of officials to the construction site to evaluate advancements […]

Milestone Achievement in Kampong Cham as Mekong River Bank Protection Project Reaches Completion

The Ministry of Water Resources and Meteorology has announced the successful completion of a significant riverbank protection project along the Mekong River in Kampong Cham province. Spanning 700 meters in length, this second phase of construction has reached one hundred percent completion, marking a vital step in safeguarding local infrastructure and livelihoods against the relentless […]