Three Sections of NR5 Expansion 46%, 38%, and 97% Complete, Respectively

To date, the renovation of NR5 is approximately 60% complete, with the southern part Prek Kdam- Pursat at 46.05%, the central part Pursat-Battambang at 38.08%, and the northern part Battambang-Banteay Meanchey at 97.30%.

This is according to a meeting between the Ministry of Public Works and Transport and the Ministry of Economy and Finance on 1 June.

Besides providing the updated progress, the meeting also officially opened the bidding for the construction of the Serei Sophorn-Poipet section (34 km) and the bidding for the construction of the vehicle weighing stations.

The renovation of NR5 has a total length of 366km connecting the capital to the northwestern part of the country passing through Kompong Chhnang, Pursat, Battambang, and Banteay Meanchey provinces.

The road will be upgraded to Asphalt Concrete (AC) and expanded to four lanes with a width of 23m. The project is being undertaken with a loan of US$500 million from the Japanese government.

In addition to the road upgrade, the Ministry of Public Works and Transport is also planning to utilise AI technology to control traffic system, especially the overweight vehicles on NR5 after the completion. (Read more)

The technology is known as the AI Camera and Weigh-in-Motion Sensor Centralised Database Solution System. The system will automatically report the data by just driving through the spot where the system is installed, which would make it easier for officers to monitor and crack down on any overweight trucks.

- Video Advertisement -

Related Post

Pursat Provincial Authorities Inaugurate New Bridge and Kick Off Construction of Nine Rural Roads

In a significant boost to local infrastructure, the Royal Government of Cambodia officially inaugurated a new 75-meter concrete bridge and announced the construction of nine additional rural roads in Pursat Province. The ceremony presided over by His Excellency Chhay Rithsen, Minister of Rural Development, marked a milestone for the community. The newly inaugurated bridge, connecting […]

Bassac River Bridge in Chak Angre Krom–Prek Pra Reaches 51% Completion

As of October 28, 2025, construction of the Bassac River Crossing Bridge connecting Chak Angre Krom to Prek Pra has reached 51% completion, according to the Ministry of Public Works and Transport (MPWT). A recent on-site inspection led by His Excellency Suong Heng, Secretary of State and Project Director, revealed steady progress across key construction […]

National Road 23 Fully Completed, Boosting Connectivity and Regional Growth

The Ministry of Public Works and Transport has officially announced the full completion of the National Road 23 (NR23) upgrade, marking a significant achievement in Cambodia’s ongoing infrastructure development. The announcement was made on October 24, 2025, following the completion of a 19.8-kilometer section designed to improve transportation efficiency and accessibility for local residents. The […]

Kampong Chhnang Province Celebrates Groundbreaking of Six Major Roads Enhancing Rural Development

In a significant step towards improving rural infrastructure, the Ministry of Rural Development held a groundbreaking ceremony today for the construction of six roads spanning over 40.5 kilometers. The event took place in the Teuk Phos and Kampong Tralach districts, with His Excellency Chhay Rithsen, the Minister of the Ministry of Rural Development, presiding over […]

Svay Rieng Province Celebrates New Infrastructure Development

Svay Rieng Province is making significant strides in rural infrastructure development, having successfully constructed 771 rural roads that span nearly 3,000 kilometers. Local authorities are dedicated to further enhancing infrastructure to stimulate economic growth in the region. This commitment was underscored during the recent groundbreaking ceremony for a new 60-meter-long concrete bridge over the Prek […]

Mekong River Bridge Project Nears Completion, Boosting Connectivity in Kratie

The Cambodia-China Friendship Bridge spanning the Mekong River in Kratie province is rapidly approaching completion, marking a major milestone in regional infrastructure development. According to Mr. Phon Rim, spokesperson for the Ministry of Public Works and Transport, overall construction has reached 87.25%, with the bridge itself nearly 100% complete. The project also includes a 32-kilometer […]