Banteay Meanchey Irrigation Development Project Exceeds 64% Completion

The Irrigation Development Project for Flood Reduction (IDFMP) in Banteay Meanchey province has made significant progress, achieving a completion rate of over 64%. The project is on track for completion by mid-2026, as reported by a working group from the Ministry of Water Resources and Meteorology on 15 January 2025.

Progress highlights include:

  1. Restoration of Pools:

– Pong Pool: 100% complete

– Veang Heng Pool: 100% complete

– Kanseng Pool: 99% complete

  1. Canal System Development:

– MC1-1 Main Canal: 98% complete

– MC1-2 Main Canal: 85% complete

– MC2 Main Canal: 95.04% complete

– MC3-1 Main Canal: 36% complete

– MC3-2 Main Canal: 98.50% complete

  1. Art Structures:

– A total of 127 out of 216 planned art buildings have been constructed.

Funded by a concession from the Republic of Korea, this project is designed to manage water received from streams along the Cambodian Thai border effectively. Key infrastructures erected include:

– Irrigation canals spanning a total length of 87.6 kilometres

– Three pools: Pong, Veang Heng, and Kanseng

– The repair of the O Khai Don Pool

The project is expected to provide irrigation for 28,354 hectares of arable land during the rainy season and 13,827 hectares during the dry season, benefiting agricultural activities in Serey Sophorn City and beyond.

- Video Advertisement -

Related Post

Pursat Provincial Authorities Inaugurate New Bridge and Kick Off Construction of Nine Rural Roads

In a significant boost to local infrastructure, the Royal Government of Cambodia officially inaugurated a new 75-meter concrete bridge and announced the construction of nine additional rural roads in Pursat Province. The ceremony presided over by His Excellency Chhay Rithsen, Minister of Rural Development, marked a milestone for the community. The newly inaugurated bridge, connecting […]

Bassac River Bridge in Chak Angre Krom–Prek Pra Reaches 51% Completion

As of October 28, 2025, construction of the Bassac River Crossing Bridge connecting Chak Angre Krom to Prek Pra has reached 51% completion, according to the Ministry of Public Works and Transport (MPWT). A recent on-site inspection led by His Excellency Suong Heng, Secretary of State and Project Director, revealed steady progress across key construction […]

National Road 23 Fully Completed, Boosting Connectivity and Regional Growth

The Ministry of Public Works and Transport has officially announced the full completion of the National Road 23 (NR23) upgrade, marking a significant achievement in Cambodia’s ongoing infrastructure development. The announcement was made on October 24, 2025, following the completion of a 19.8-kilometer section designed to improve transportation efficiency and accessibility for local residents. The […]

Kampong Chhnang Province Celebrates Groundbreaking of Six Major Roads Enhancing Rural Development

In a significant step towards improving rural infrastructure, the Ministry of Rural Development held a groundbreaking ceremony today for the construction of six roads spanning over 40.5 kilometers. The event took place in the Teuk Phos and Kampong Tralach districts, with His Excellency Chhay Rithsen, the Minister of the Ministry of Rural Development, presiding over […]

Svay Rieng Province Celebrates New Infrastructure Development

Svay Rieng Province is making significant strides in rural infrastructure development, having successfully constructed 771 rural roads that span nearly 3,000 kilometers. Local authorities are dedicated to further enhancing infrastructure to stimulate economic growth in the region. This commitment was underscored during the recent groundbreaking ceremony for a new 60-meter-long concrete bridge over the Prek […]

Mekong River Bridge Project Nears Completion, Boosting Connectivity in Kratie

The Cambodia-China Friendship Bridge spanning the Mekong River in Kratie province is rapidly approaching completion, marking a major milestone in regional infrastructure development. According to Mr. Phon Rim, spokesperson for the Ministry of Public Works and Transport, overall construction has reached 87.25%, with the bridge itself nearly 100% complete. The project also includes a 32-kilometer […]