Bridge Construction Over Bassac River Progresses Steadily

The construction of the bridge spanning the Bassac River between Chak Angre Krom and Prek Pra is taking shape, with the project now 36% complete, according to a recent report from the Ministry of Public Works and Transport.

As of mid-June 2025, significant strides have been made on the bridge. The overall impact resolution process is nearing completion, with 98% of the necessary arrangements finalized. Currently, construction on the eastern bridge has seen substantial progress, with the foundation completed at approximately 66.5%. This includes 156 foundation pillars, of which 137 are finished, alongside 20 piers, 9 of which have been completed, and 12 lower connecting beams, with 8 already in place.

In addition to the foundation, the structural work beneath the bridge stands at around 25.12% completion. This encompasses 12 bridge piers, where 6 are done, along with 52 additional bridge piers, with 24 completed, and 34 connecting beams, where 10 have been installed, among other critical tasks.

While the construction work is ongoing, Phnom Penh authorities are accelerating efforts to finalize the impact resolution, with 98% of cases resolved. It’s noteworthy that only 3 families have declined the total compensation package of USD 3,320,761.86 offered for the relocation process.

The bridge itself is set to stretch 1,650 meters in total, including 845.7 meters for the bridge span and 804.3 meters for the connecting roadway. The project features a road width of 27 meters on both the bridge and the connecting road. This ambitious infrastructure project is being executed by Shanghai Construction Company, with oversight from the Guangzhou Wan An Company. The total investment for the bridge is USD 60.2 million, provided through a concessional loan from the Chinese government, complemented by funding from the Royal Government of Cambodia for impact resolution, mine clearance, and associated taxes. (Read more)

As the project progresses, it is poised to enhance connectivity and promote economic development in the region, highlighting the ongoing commitment of both the Cambodian and Chinese governments to infrastructure improvements in Cambodia.

- Video Advertisement -

Related Post

Cambodia Records Surge in Investment with Ten Billion Dollars in New Projects for 2025

Cambodia has reached a major economic milestone in 2025, securing 630 new investment projects with a total capital value of approximately 10 billion dollars. This performance represents a significant 45 percent increase in investment volume compared to the previous year, highlighting the Kingdom’s growing appeal as a strategic hub for international capital. The Council for […]

Kandal Province Launches Official Construction of Prek Thnot Riverbank Park to Enhance Urban Beauty

Provincial authorities and Ministry officials join forces to transform the southern riverbank into a modern recreational space for residents and tourists The landscape of Takhmao city is set for a significant aesthetic upgrade following the official groundbreaking of the Prek Thnoat riverbank park project on January 3, 2026. This ambitious development, situated along the southern […]

Battambang Completes Construction of Massive Water Treatment Facility to Meet Growing Urban Demand

New high-capacity plant set to launch in early 2026 will double the provincial capital’s clean water supply through advanced Chinese engineering The skyline of Battambang’s Kampong Seima area has been permanently transformed with the 100 percent completion of the province’s third and largest water treatment plant. This major infrastructure milestone, announced by H.E. Ut Kloeung, […]

Progress Inspection for Wastewater Treatment System Development in Takhmao City

In a significant step towards enhancing the development progress in Takhmao City, HE Ros Vanna, Secretary of State of the Ministry of Public Works and Transport, led a comprehensive inspection of the wastewater treatment system development project in Takhmao City. This project, pivotal for managing urban wastewater, is funded by the Economic Development Cooperation Fund […]

Mekong River Bridge (Dei Edth-Thma Kor) Construction Reaches 36% Completion

The Mekong River Bridge (Dei Edth-Thma Kor) Construction Project has marked a significant milestone, achieving 36% completion as of late December 2025. His Excellency So Vector, Secretary of State for the Ministry of Public Works and Transport and Managing Director of the project, led a team of officials to the construction site to evaluate advancements […]

Milestone Achievement in Kampong Cham as Mekong River Bank Protection Project Reaches Completion

The Ministry of Water Resources and Meteorology has announced the successful completion of a significant riverbank protection project along the Mekong River in Kampong Cham province. Spanning 700 meters in length, this second phase of construction has reached one hundred percent completion, marking a vital step in safeguarding local infrastructure and livelihoods against the relentless […]