Construction of 400 MW power plants in Kandal province faces suspension

Two power plants with a total power capacity of 400 MW fueled by heavy fuel oil which was under construction in Lvea Em district, Kandal province may fail to come online as scheduled because contracted construction firms from China have been affected by the COVID-19 pandemic.

According to the plan, when construction started in October 2019 the power plants, were scheduled to generate power and be connected to the grid in May or June, within the first semester this year.

Unfortunately, because of construction firms contracted from China having difficulties in travelling and being required to be in quarantine for COVID-19 prevention, the process of construction work faces suspension.

Victor Jona, director-general of General Department of Energy and spokesperson of the Ministry of Mines and Energy, reported that “The suspension of commencing the power plants will be up to 6 months if the situation of COVID-19 gets better.”

Given the threat of the pandemic on the energy development sector, some people raised concerns over economic downturns especially in the power sector, as there might be some withdrawal of energy investment and delay in project implementation.

However, addressing these concerns, Mr Jona made it clear that “although the power plant commencement is suspended, it dost not negatively affect supplying power to Phnom Penh because other power sources – hydropower dams, coal-fired power plants, solar, and biomass power plants – have been put on the front lines to supply power in the dry season.”

For the 400 MW power plants, the government spent US$380 MW to import generators from Finland and Germany in mid-2019, aiming to increase power supplies to Phnom Penh.

Notably, two Chinese firms were constructing the power plants: CGGC-UN Power Co and China National Heavy Machinery Corporation. The plants are under the control of Electricite Du Cambodge (EDC). (Read more) and (Read more)

- Video Advertisement -

Related Post

Cambodia Records Surge in Investment with Ten Billion Dollars in New Projects for 2025

Cambodia has reached a major economic milestone in 2025, securing 630 new investment projects with a total capital value of approximately 10 billion dollars. This performance represents a significant 45 percent increase in investment volume compared to the previous year, highlighting the Kingdom’s growing appeal as a strategic hub for international capital. The Council for […]

Kandal Province Launches Official Construction of Prek Thnot Riverbank Park to Enhance Urban Beauty

Provincial authorities and Ministry officials join forces to transform the southern riverbank into a modern recreational space for residents and tourists The landscape of Takhmao city is set for a significant aesthetic upgrade following the official groundbreaking of the Prek Thnoat riverbank park project on January 3, 2026. This ambitious development, situated along the southern […]

Battambang Completes Construction of Massive Water Treatment Facility to Meet Growing Urban Demand

New high-capacity plant set to launch in early 2026 will double the provincial capital’s clean water supply through advanced Chinese engineering The skyline of Battambang’s Kampong Seima area has been permanently transformed with the 100 percent completion of the province’s third and largest water treatment plant. This major infrastructure milestone, announced by H.E. Ut Kloeung, […]

Progress Inspection for Wastewater Treatment System Development in Takhmao City

In a significant step towards enhancing the development progress in Takhmao City, HE Ros Vanna, Secretary of State of the Ministry of Public Works and Transport, led a comprehensive inspection of the wastewater treatment system development project in Takhmao City. This project, pivotal for managing urban wastewater, is funded by the Economic Development Cooperation Fund […]

Mekong River Bridge (Dei Edth-Thma Kor) Construction Reaches 36% Completion

The Mekong River Bridge (Dei Edth-Thma Kor) Construction Project has marked a significant milestone, achieving 36% completion as of late December 2025. His Excellency So Vector, Secretary of State for the Ministry of Public Works and Transport and Managing Director of the project, led a team of officials to the construction site to evaluate advancements […]

Milestone Achievement in Kampong Cham as Mekong River Bank Protection Project Reaches Completion

The Ministry of Water Resources and Meteorology has announced the successful completion of a significant riverbank protection project along the Mekong River in Kampong Cham province. Spanning 700 meters in length, this second phase of construction has reached one hundred percent completion, marking a vital step in safeguarding local infrastructure and livelihoods against the relentless […]