NR No. 48 Upgrade Achieves 64% Completion with Targeted Finish by May 2025

The rehabilitation and upgrading of NR No. 48, a crucial 148 km stretch from Sre Ambel to Koh Kong, has reached 64.05% completion, marking significant progress in the project aimed at enhancing connectivity in the province. This milestone was highlighted during the 5th Joint Monitoring Meeting by His Excellency So Vector, Secretary of State of the Ministry of Public Works and Transport, who also serves as Chairman of the project, according to the Ministry’s latest update on 21 August 2024.

The ministry is intensifying efforts on quality control, machinery, and labour supply to ensure the project’s timely completion by May 2025. The ministry discussed proposals, challenges, and detailed work directions to expedite construction, ensuring that this vital infrastructure upgrade will bolster transportation efficiency and regional development.

This ambitious project, which began on 3 January 2022, focuses on upgrading the section from the intersection of NR No. 4 PK 141 + 750 (Chamkar Luong – Sre Ambel District) to Khemarak Phoumin in Koh Kong Province. With an estimated budget of approximately USD 78 million. (Read more)

- Video Advertisement -

Related Post

Cambodia Records Surge in Investment with Ten Billion Dollars in New Projects for 2025

Cambodia has reached a major economic milestone in 2025, securing 630 new investment projects with a total capital value of approximately 10 billion dollars. This performance represents a significant 45 percent increase in investment volume compared to the previous year, highlighting the Kingdom’s growing appeal as a strategic hub for international capital. The Council for […]

Kandal Province Launches Official Construction of Prek Thnot Riverbank Park to Enhance Urban Beauty

Provincial authorities and Ministry officials join forces to transform the southern riverbank into a modern recreational space for residents and tourists The landscape of Takhmao city is set for a significant aesthetic upgrade following the official groundbreaking of the Prek Thnoat riverbank park project on January 3, 2026. This ambitious development, situated along the southern […]

Battambang Completes Construction of Massive Water Treatment Facility to Meet Growing Urban Demand

New high-capacity plant set to launch in early 2026 will double the provincial capital’s clean water supply through advanced Chinese engineering The skyline of Battambang’s Kampong Seima area has been permanently transformed with the 100 percent completion of the province’s third and largest water treatment plant. This major infrastructure milestone, announced by H.E. Ut Kloeung, […]

Progress Inspection for Wastewater Treatment System Development in Takhmao City

In a significant step towards enhancing the development progress in Takhmao City, HE Ros Vanna, Secretary of State of the Ministry of Public Works and Transport, led a comprehensive inspection of the wastewater treatment system development project in Takhmao City. This project, pivotal for managing urban wastewater, is funded by the Economic Development Cooperation Fund […]

Mekong River Bridge (Dei Edth-Thma Kor) Construction Reaches 36% Completion

The Mekong River Bridge (Dei Edth-Thma Kor) Construction Project has marked a significant milestone, achieving 36% completion as of late December 2025. His Excellency So Vector, Secretary of State for the Ministry of Public Works and Transport and Managing Director of the project, led a team of officials to the construction site to evaluate advancements […]

Milestone Achievement in Kampong Cham as Mekong River Bank Protection Project Reaches Completion

The Ministry of Water Resources and Meteorology has announced the successful completion of a significant riverbank protection project along the Mekong River in Kampong Cham province. Spanning 700 meters in length, this second phase of construction has reached one hundred percent completion, marking a vital step in safeguarding local infrastructure and livelihoods against the relentless […]