NRNo. 31 (Bek Kus – Kampot) Rehabilitation with 53km in Length Nears Completion, Achieving Almost 99% Progress

The extensive rehabilitation of Cambodia’s NR No. 31, covering a 53.54-km stretch from Bek Kus to Kampong Trach, is almost complete, reaching a 98.68% progress milestone as of 21 October 2024.

This update was shared during a review meeting led by His Excellency Khan Ma Ne, Secretary of State and Director of the Rehabilitation and Upgrading Project, who praised the project’s steady advancement and confirmed its early completion, meeting high technical standards, as reported on 21 October 2024.

NR No. 31 spans 53.54km from the Bek Kus intersection with NR No. 3 through Kampong Trach district town, where it links to NR No. 33, forming a vital infrastructure corridor for the coastal region.

Since construction commenced on 30 December 2022, notable progress includes the full installation of two layers of AC rubber and the near completion of essential traffic safety installations, including traffic signs, road markings, and guide rails.

HE Khan Ma Me highlighted that completing the project ahead of schedule demonstrates the effectiveness of planning and execution efforts, reflecting a strong commitment to maintaining national infrastructure to the highest standards. With only final safety equipment installations remaining, NR No. 31 is on track to open and significantly improve connectivity within the region.

- Video Advertisement -

Related Post

Pursat Provincial Authorities Inaugurate New Bridge and Kick Off Construction of Nine Rural Roads

In a significant boost to local infrastructure, the Royal Government of Cambodia officially inaugurated a new 75-meter concrete bridge and announced the construction of nine additional rural roads in Pursat Province. The ceremony presided over by His Excellency Chhay Rithsen, Minister of Rural Development, marked a milestone for the community. The newly inaugurated bridge, connecting […]

Bassac River Bridge in Chak Angre Krom–Prek Pra Reaches 51% Completion

As of October 28, 2025, construction of the Bassac River Crossing Bridge connecting Chak Angre Krom to Prek Pra has reached 51% completion, according to the Ministry of Public Works and Transport (MPWT). A recent on-site inspection led by His Excellency Suong Heng, Secretary of State and Project Director, revealed steady progress across key construction […]

National Road 23 Fully Completed, Boosting Connectivity and Regional Growth

The Ministry of Public Works and Transport has officially announced the full completion of the National Road 23 (NR23) upgrade, marking a significant achievement in Cambodia’s ongoing infrastructure development. The announcement was made on October 24, 2025, following the completion of a 19.8-kilometer section designed to improve transportation efficiency and accessibility for local residents. The […]

Kampong Chhnang Province Celebrates Groundbreaking of Six Major Roads Enhancing Rural Development

In a significant step towards improving rural infrastructure, the Ministry of Rural Development held a groundbreaking ceremony today for the construction of six roads spanning over 40.5 kilometers. The event took place in the Teuk Phos and Kampong Tralach districts, with His Excellency Chhay Rithsen, the Minister of the Ministry of Rural Development, presiding over […]

Svay Rieng Province Celebrates New Infrastructure Development

Svay Rieng Province is making significant strides in rural infrastructure development, having successfully constructed 771 rural roads that span nearly 3,000 kilometers. Local authorities are dedicated to further enhancing infrastructure to stimulate economic growth in the region. This commitment was underscored during the recent groundbreaking ceremony for a new 60-meter-long concrete bridge over the Prek […]

Mekong River Bridge Project Nears Completion, Boosting Connectivity in Kratie

The Cambodia-China Friendship Bridge spanning the Mekong River in Kratie province is rapidly approaching completion, marking a major milestone in regional infrastructure development. According to Mr. Phon Rim, spokesperson for the Ministry of Public Works and Transport, overall construction has reached 87.25%, with the bridge itself nearly 100% complete. The project also includes a 32-kilometer […]