Construction of Koh Tonsay Port, Landfill, & Seaside Road in Kep  62% Complete

Construction of the Koh Tonsay tourism port, landfill, and seaside road in Kep province is 62% complete according to the details in an official meeting on 04 August 2022.

Deputy Technical Advisor of the Asian Development Bank (ADB) Horm Nimol said that the sub-projects of the landfill, coastal road and Koh Tonsay tourism port have been 98.8%, 10.4%, and 8.5% completed respectively.

He added that the coastal road construction project is facing some technical problems and the Koh Tonsay port project went through some changes according to the request from the Koh Tonsay community.

Meanwhile, the transportation of machinery and construction materials from the mainland to the island has become expensive and difficult during the rainy season.

Kep Deputy Governor Voa Sokha stressed that provincial authorities will do their best to help solve all the issues, aiming to push the project to finish on time.

The three projects are part of the Asian Development Bank (ADB) Phase II Tourism Growth for the Greater Mekong Subregion Project, in which the Koh Tonsay Port sub-project will be built under a US$1.6-million budget.  (Read more)

- Video Advertisement -

Related Post

Cambodia Records Surge in Investment with Ten Billion Dollars in New Projects for 2025

Cambodia has reached a major economic milestone in 2025, securing 630 new investment projects with a total capital value of approximately 10 billion dollars. This performance represents a significant 45 percent increase in investment volume compared to the previous year, highlighting the Kingdom’s growing appeal as a strategic hub for international capital. The Council for […]

Kandal Province Launches Official Construction of Prek Thnot Riverbank Park to Enhance Urban Beauty

Provincial authorities and Ministry officials join forces to transform the southern riverbank into a modern recreational space for residents and tourists The landscape of Takhmao city is set for a significant aesthetic upgrade following the official groundbreaking of the Prek Thnoat riverbank park project on January 3, 2026. This ambitious development, situated along the southern […]

Battambang Completes Construction of Massive Water Treatment Facility to Meet Growing Urban Demand

New high-capacity plant set to launch in early 2026 will double the provincial capital’s clean water supply through advanced Chinese engineering The skyline of Battambang’s Kampong Seima area has been permanently transformed with the 100 percent completion of the province’s third and largest water treatment plant. This major infrastructure milestone, announced by H.E. Ut Kloeung, […]

Progress Inspection for Wastewater Treatment System Development in Takhmao City

In a significant step towards enhancing the development progress in Takhmao City, HE Ros Vanna, Secretary of State of the Ministry of Public Works and Transport, led a comprehensive inspection of the wastewater treatment system development project in Takhmao City. This project, pivotal for managing urban wastewater, is funded by the Economic Development Cooperation Fund […]

Mekong River Bridge (Dei Edth-Thma Kor) Construction Reaches 36% Completion

The Mekong River Bridge (Dei Edth-Thma Kor) Construction Project has marked a significant milestone, achieving 36% completion as of late December 2025. His Excellency So Vector, Secretary of State for the Ministry of Public Works and Transport and Managing Director of the project, led a team of officials to the construction site to evaluate advancements […]

Milestone Achievement in Kampong Cham as Mekong River Bank Protection Project Reaches Completion

The Ministry of Water Resources and Meteorology has announced the successful completion of a significant riverbank protection project along the Mekong River in Kampong Cham province. Spanning 700 meters in length, this second phase of construction has reached one hundred percent completion, marking a vital step in safeguarding local infrastructure and livelihoods against the relentless […]