New Pnnom Penh Airport Named ‘Techo International Airport’; Now 27% Complete

As of December 2021, the construction project of the new Phnom Penh Airport, which has recently been renamed as the “Techo International Airport, Takhmao City” has reached 27% completion, on track to start operation by 2023.

This is according to the site inspection by Cambodia Prime Minister Samdech Hun Sen on 9 December.

On this occasion, Cambodia Airport Investment Co., Ltd (CIAC) and OCIC, the investment companies on this project, summarised the results of the main sections of the project as follows:

1) Construction of passenger terminal with an area of over 240,000 sqm is 29% complete, scheduled for final completion in 2023.

2) Power supply centre is 55% complete, scheduled for final completion by the end of 2022.

3) The 189-hectare airport apron is 21% complete. The pavement work on the runway is scheduled to start in January 2021 and be completed in 2023.

4) 118m Air Traffic Control Tower constructed by Canasino 40% complete and will be handed over to Cambodia Air Traffic Service in July 2022 to install the equipment.

5) The new road project connecting the airport to 60m Road constructed by CHIC, which includes a 11.7km road and 2 concrete bridges across Stung Prek Tnaot, is 24% and scheduled to be completed in 2021.

6) The canal dredging work around the airport with a length of 20km is 40% complete and scheduled to be completed in 2022.

7) Construction of 19 other essential buildings including the VIP passenger terminal, wastewater station, solid waste station, vehicle repair station, fuel storage station, storage station, fire projection station, power substation, etc. is in the piling stage. To date, the work is 40% completed and scheduled to be completed in 2023.

8) Boeung Cheung Lok dredging work has achieved 18 hectares by deepening the lake from 5 to 22 metres. The firm will dredge another 100 hectares in 2022.

Chairman of OCIC Neak Oknha Pung Kheav Se said that the COVID-19 pandemic and flooding during the rainy season had caused some disruption to the construction, but the firm has overcome the obstacles and ensured that the project is going as planned.

To date, the company has invested a total of US$375 million in the project, with the plan to add another US$447 million in 2022. The total investment value of the entire project is US$1.5 billion, excluding the land price.

The project employs a total of 3,740 people, 3,125 locals and 615 foreign workers. With this project, the company is also training thousands of human resources in various fields related to the construction sector, who will become high-quality human resources in the future.

In order to seek additional capital, Cambodia Airport Investment Co., Ltd (CAIC) and OCIC has also guaranteed bonds with a total value of US $300 million. Thus far, over US$87 million have been sold to banks, insurance companies, government institutions.

- Video Advertisement -

Related Post

Cambodia Records Surge in Investment with Ten Billion Dollars in New Projects for 2025

Cambodia has reached a major economic milestone in 2025, securing 630 new investment projects with a total capital value of approximately 10 billion dollars. This performance represents a significant 45 percent increase in investment volume compared to the previous year, highlighting the Kingdom’s growing appeal as a strategic hub for international capital. The Council for […]

Kandal Province Launches Official Construction of Prek Thnot Riverbank Park to Enhance Urban Beauty

Provincial authorities and Ministry officials join forces to transform the southern riverbank into a modern recreational space for residents and tourists The landscape of Takhmao city is set for a significant aesthetic upgrade following the official groundbreaking of the Prek Thnoat riverbank park project on January 3, 2026. This ambitious development, situated along the southern […]

Battambang Completes Construction of Massive Water Treatment Facility to Meet Growing Urban Demand

New high-capacity plant set to launch in early 2026 will double the provincial capital’s clean water supply through advanced Chinese engineering The skyline of Battambang’s Kampong Seima area has been permanently transformed with the 100 percent completion of the province’s third and largest water treatment plant. This major infrastructure milestone, announced by H.E. Ut Kloeung, […]

Progress Inspection for Wastewater Treatment System Development in Takhmao City

In a significant step towards enhancing the development progress in Takhmao City, HE Ros Vanna, Secretary of State of the Ministry of Public Works and Transport, led a comprehensive inspection of the wastewater treatment system development project in Takhmao City. This project, pivotal for managing urban wastewater, is funded by the Economic Development Cooperation Fund […]

Mekong River Bridge (Dei Edth-Thma Kor) Construction Reaches 36% Completion

The Mekong River Bridge (Dei Edth-Thma Kor) Construction Project has marked a significant milestone, achieving 36% completion as of late December 2025. His Excellency So Vector, Secretary of State for the Ministry of Public Works and Transport and Managing Director of the project, led a team of officials to the construction site to evaluate advancements […]

Milestone Achievement in Kampong Cham as Mekong River Bank Protection Project Reaches Completion

The Ministry of Water Resources and Meteorology has announced the successful completion of a significant riverbank protection project along the Mekong River in Kampong Cham province. Spanning 700 meters in length, this second phase of construction has reached one hundred percent completion, marking a vital step in safeguarding local infrastructure and livelihoods against the relentless […]