Comin Khmere installs 30,000 floating and curved roof solar panels in Kampot province

Comin Khmere, a subsidiary of Comin Asia Group and one of the country’s leading engineering solutions provider, has successfully executed Cambodia’s first floating solar system and curved rooftop solar installation in Kampot province.

In an email response to Construction & Property Magazine on 29 August, Mr Phanith Hak, group marketing and communication coordinator of Comin Khmere said that in April 2019 the company had finished installing 30,000 floating and curved roof solar panels.

Executed for the Chip Mong Insee cement factory in Kampot, the company is the first to implement a floating solar system in Cambodia along with a unique curved rooftop installation.

The newly installed solar panels, on which work began in September 2018, are capable of producing up to 13,000,000-kilowatt hours of energy per year, about 7% of the total energy needed.

Despite facing challenges, as this is the first time that Comin Khmere has executed a floating solar system, the company has implemented safety practices to achieve zero incidents on-site.

As solar power is to account for about 15% of total Cambodia’s power consumption in 2020, this clean energy sources will provide many benefits for consumers as well.

According to Mr Phanith Hak, by using solar panels customer can reduce their carbon footprint, and save costs as well.

Comin Khmere is an engineering solution provider of design, engineering, procurement installation and testing and commissioning as well as service and maintenance for all mechanical, electrical and people movement solutions.

 

 

- Video Advertisement -

Related Post

National Road No. 33 (Kampot-Chrak Lok) is almost 99% completed

National Road No. 33 (Kampot-Chrak Lok) is nearly complete, with 98.89% of the project achieved as of early November 2024. This progress was reported during an inspection led by HE Pal Chandara, Secretary of State of the Ministry of Public Works and Transport. On November 6, 2024, the technical team from China Bridge and Road […]

China’s Sailun Group Plans Expansion of Rubber Processing Investment in Cambodia

In a significant move to enhance its presence in Southeast Asia, Chinese tyre manufacturer Sailun Group has announced plans to increase its investment in rubber processing in Cambodia, where it currently operates a tyre factory in Svay Rieng province. The announcement occurred during a recent meeting between Yuan Zhongxue, Honorary Chairman of Sailun Group, and […]

The Gov’t decided to establish a new village called “Bun Rany Sen Chey Damnak Troyeung” in Phnom Kravanh district, Pursat province

The Ministry of Interior has decided to establish a new village called “Bun Rany Sen Chey Damnak Troyeung Village” in Prongel Commune, Phnom Kravanh District, Pursat Province. This is according to Prakas No. 6762, dated November 08, 2024. This new village is separated from Say village, Prongel commune, Phnom Kravanh district, Pursat province. It should […]

Chinese Company to Establish Cashew Processing Plant in Cambodia

Shandong (Cambodia) Economic and Technological Development Zone, a Chinese company specializing in cassava and cashew cultivation, has announced plans to increase its capital to establish a cashew processing plant in Cambodia. This initiative was discussed during a recent meeting held on November 6, 2024, between His Excellency Hun Manet, the Prime Minister of Cambodia, and […]

Techo International Airport completed more than 90%, cost of USD1.3 billion

As of the first week of November 2024, the construction of Techo International Airport has achieved more than 90% with a cost of more than USD 1.3 billion. HE Sinn Chansery Vutha, Secretary of State and Spokesman for the Secretariat of State for Civil Aviation of Cambodia said on November 6 that the major construction […]

The rehabilitation of National Road No. 48 from Sre Ambel to Koh Kong is currently 67.45% complete

As of November 6, 2024, the project to restore and upgrade the quality of National Road No. 48, which stretches 148 km, has reached a completion rate of 67.45%. This update was provided by the Ministry of Public Works and Transport. The working group for the National Rehabilitation and Upgrading of National Road No. 48 […]