Construction of Phnom Penh-Sihanoukville Expressway 64% Complete

Construction of the 190km Phnom Penh-Sihanoukville expressway was 64% complete by July 2021, according to the Ministry of Public Works and Transport (MPWT)’s spokesperson Heang Sotheayuth.

He added that despite the fact that Cambodia is facing the COVID-19 pandemic crisis, the expressway construction process is not being affected.

The project, on the other hand, might be completed ahead of schedule, changing from the initial date of March 2023 to September 2022, with a free ride trial during the first week or month.

Minister of Public Works and Transport HE Sun Chanthol said in June that the ministry is also currently negotiating for the firm to charge as low a fee as possible, aiming for lower than 10cent/km. (Read more)

The Phnom Penh-Sihanoukville Expressway has a total length of 190 kilometres connecting Sangkat Samrong Krom, Khan Por Senchey in Phnom Penh to Sangkat 3 in Sihanoukville.

The project is expected to cost a total of US$2 billion and is being built by China Bridge and Road Corporation (CRBC) through the Cambodian PPSHV Expressway Co., Ltd.

- Video Advertisement -

Related Post

Border Ring Road Construction Progress Approaches 40% Milestone

The construction progress of the highly anticipated border ring road has reached nearly 40%, marking a significant step forward for the project. Currently, approximately 39.92% of the total construction plan has been completed, as reported in a press release today. The initiative, funded by the Border Infrastructure Fund (BIF), aims to enhance connectivity along the […]

Construction Progress of Phnom Penh’s Drainage System Nears Completion

The ambitious project to build a comprehensive drainage system in western Phnom Penh is now 88% complete, with final touches expected to be finalized by July 2025. During a recent review, Ms. Koy Sodany, Permanent Secretary of State at the Ministry of Public Works and Transport and the project leader, confirmed the significant progress. The […]

Electric Bus Revolution in Siem Reap: A Step Towards Sustainable Transport

In an exciting development for eco-friendly public transport, Cambodia, in partnership with the Green Development Institute (GGGI), has unveiled plans for an electric bus system in Siem Reap province. The announcement came during the final workshop of the electric bus public transport system study, where three strategic routes and 33 waiting stations were officially designated. […]

Progress Report: Siem Reap River Improvement Project Phase 2 Nears Completion

The Siem Reap River Improvement Project Phase 2 is making significant strides, with the project now completed by 97%. The Siem Reap Provincial Administration announced on August 21, 2025, via its official Facebook page that the project is on track for completion by July 1, 2025. The ongoing work focuses on restoring the river and […]

National Road 7 Expansion Project on Track for Early Completion

The ambitious project to expand and improve National Road 7, transforming it from a two-lane to a four-lane highway, is currently 43% complete and is expected to finish ahead of schedule. The 45.5-kilometre stretch of road runs from Vang Vong Moul Skun in Cheung Prey District to the base of the Kizuna Bridge in Kampong […]

India-Myanmar-Thailand Trilateral Highway Stalled Amid Conflict in Myanmar

The USD 114 billion India-Myanmar-Thailand Trilateral Highway, a crucial 1,360-kilometre infrastructure project designed to enhance ASEAN economic integration and strengthen India’s trade presence in Southeast Asia, faces major setbacks due to ongoing instability in Myanmar. Designed as a four-lane highway, the Trilateral Highway is part of India’s broader infrastructure vision, which aims to extend road […]