Construction of First Phase of Bak Kheng Water Treatment Plant 60% Complete

The construction of the Bak Kheng Water Treatment Plant, Phase 1, is now 60% complete and is scheduled to be completed as planned, according to an announcement by the Phnom Penh Water Supply Authority on 2 May.

The Phnom Penh Water Supply Authority said that by the first quarter of 2022, the first phase of the project with a production capacity of nearly 200,000 cubic meters per day is 60% complete.

The project is divided into three parts which include:

Part 1: Construction of water treatment plant 50% complete.

Part 2: Construction of Water Pumping Station 45% complete.

Part 3: Construction work on laying main pipelines is 50% complete.

Meanwhile, the construction of the second phase of the Bak Kheng water treatment plant, which has a production capacity of nearly 400,000 cubic meters per day, is now about 37% complete.

The project is a large investment project in the water supply sector in Phnom Penh and Takhmao by the Phnom Penh Water Supply Authority. The project uses a total investment of US$190 million, which is co-financed by the French Development Agency, European Investment Bank, and Phnom Penh Water Supply Authority.

The project officially started construction on 5 May 2020.

According to the Phnom Penh Water Supply Authority, the construction of the plant will be accelerated according to the planned schedule, as well as the study of the master plan until 2030 to meet the demand for clean water in Phnom Penh and Takhmao town.

- Video Advertisement -

Related Post

Progress Update on the Stung Khliech Water Resources Development Project in Kampong Speu

Strategic irrigation infrastructure reaches fifteen percent completion milestone to support forty thousand hectares of farmland The Stung Khliech Water Resources Development Project in Kampong Speu province has reached a fifteen percent completion rate in its construction phase. Once finished, this significant infrastructure project will have the capacity to provide irrigation for approximately 40,000 hectares of […]

Borey Peng Huoth Announces Exclusive Pre-Sale Event for New Phum Nimith Project in Chbar Ampov

Early access to prime locations within the prestigious Grand Star Platinum development starting this March Following the successful groundbreaking ceremony held on January 30, 2026, Borey Peng Huoth is pleased to announce the official pre-sale launch of its newest residential development, Phum Nimith. This highly anticipated event will take place over three days from March […]

Accelerating Connectivity: Mekong River Bridge Connecting Dei Edth-Thmor Kor Surpasses 35% Completion

Minister Peng Ponea inspects the strategic infrastructure project in Kandal province to ensure rigorous technical standards and timely delivery for the public The construction of the major bridge across the Mekong River Dei Edth-Thmor Kor connecting Dei Edth commune in Kien Svay district to Thmor Kor commune in Lvea Em district has reached a significant […]

Cambodia and Laos to Fast-Track Cross-Border Connectivity with New Ratanakiri-Attapeu Road Link

Joint inspection team to finalize construction zones this February to unlock new trade and economic opportunities Cambodia and Laos have reached a pivotal agreement to conduct a joint technical inspection aimed at defining the specific zones for a new road project connecting Ratanakiri province in Cambodia to Attapeu province in Laos. This initiative is a […]

Kratie City Drainage and Pumping Station Project Surpasses 68% Completion

Provincial authorities and ADB-funded initiative accelerate infrastructure development to eliminate seasonal flooding and boost local economic appeal Kratie City is undergoing a significant infrastructural transformation as the construction of its comprehensive drainage network and rainwater pumping station reaches 68 percent completion. This development is a key sub-project of the Fourth Greater Mekong Subregion Corridor Towns […]

Border Ring Road Project in Mondulkiri and Ratanakiri Surpasses 72% Completion in 13 Months

Cambodia’s historic border ring road project has reached a significant milestone, achieving an overall completion rate of 72.29% as of January 11, 2026. This monumental initiative is being realized through the “Border Infrastructure Fund,” fueled by enthusiastic contributions from citizens across the country to strengthen national security and enhance the livelihoods of those living in […]