Airports Capacity Grows with Traffic

The double-digit growth of air passengers through Cambodia’s airports has led to the launch of a huge airport development master plan which offers a transport infrastructure vision for the next 30-40 years.

The kingdom’s three international airports; Phnom Penh (PNH), Siem Reap (REP), and Sihanoukville are currently undergoing construction, extension, and renovation projects to increase their respective capacities.

Cambodia Airports— a joint venture between France’s VINCI Airports (70%) and Malaysia’s Muhibbah Group (30%) has the concession to develop and operate the three international airports for 45 years starting from 1995. It decided to launch the extension and renovation projects for Phnom Penh and Siem Reap airports after seeing the steep rise in traffic at the airports.

“We at the airports of Phnom Penh and Siem Reap have observed double-digit growth annually of passengers since 2010 from 18% to 20% in Siem Reap and 12% to 15% in Phnom Penh although the increases have been softer in 2014,” said Emmanuel Menanteau, CEO of Cambodia Airports.

While construction projects for both airports are jointly built by Vinci Construction Grands Projets (VCGP) and Muhibbah, Hamiltons International were selected as an architectural consultant for Phnom Penh and Archetype won the bid for Siem Reap.

Since there was already an expansion plan in place during construction in 2004, upgrading Siem Reap airport is relatively straightforward with some new facilities already open between check-in and boarding. As the airport’s brand new international arrival terminal opened on 13 June, work will also start this year to extend the apron to accommodate three more additional aircraft. No aircraft-terminal walkways have yet been installed in Siem Reap to conserve its unique architecture.

In Phnom Penh, construction is more complicated because the terminal building is quite old, although it was partly planned for an extension. After the new design was approved, construction started in June 2014 with completion expected by March 2016. The design involves an extension wing which increases the current terminal size as well as renovating the existing facilities including car parks, etc. The new wing is expected to be open and connected to the existing terminal by December and fully operational in 2016.

“This is why it is a complicated project because rather than building a brand new terminal, we build a wing that connects to an existing terminal and then we refurbish the old facilities, all of that without stopping operations,” Menanteau explained.

Thanks to these projects, both airports will be equipped with larger spaces for premium lounges and duty-free areas, more food and beverage outlets, check-in counters and boarding gates, and luggage delivery carousels, as well as increased aircraft parking capacity.

Responding to environmental conditions, brand-new wastewater treatment plants have been installed at both airports. Wastewater and garbage from the airports will be composited and transformed into agriculture fertiliser that will be offered to external users.

So far, Cambodia Airports has spent over $100 million on various projects at both airports under its own financing as the airport concessionaire.

Expansion and renovation works have also been launched at Sihanoukville airport this year. Besides extending its facilities to ensure this coastal airport can accommodate medium-sized regional commercial planes, have enough passenger facilities, and also be connected to the EDC electrical grid.

By the end of 2015, PNH and REP are expected to handle combined traffic of around 6.1 million passengers, while the Sihanoukville airport, which handled 40,000 passengers last year, is expected to receive 80,000 passengers this year.

For 2020, PNH and REP are expected to receive around 7.3 million passengers, roughly 3.5 million for each airport with 200,000 passengers through Sihanoukville.

To help ease the burden on the three international airports, the government and Cambodia Airports, via cooperation with the International Air Transport Association (IATA), have been studying the feasibility of reopening some domestic airports.

The study aimed to create a long-term vision of Cambodia’s airport infrastructure that will link to other transport infrastructure developments in the country, and also connect Cambodia to the rest of the world.

IATA recommended Ratanakiri, Kong Kong, and Preah Vihear provinces as prospective areas for either reopening or developing airports’ due to tourism potential.

Cambodia doesn’t need to build another new international airport near the capital according to IATA, asserting that the size of the current Phnom Penh airport will be able to handle traffic until almost 2035 or 2040.

- Video Advertisement -

Related Post

Techo International Airport Nears Completion: A New Gateway to Cambodia

In an exciting development for Cambodia’s aviation sector, the Techo International Airport construction project is now over 94% complete, with the total investment reaching nearly USD 1.4 billion. This ambitious project promises to transform the country’s skyways and enhance domestic and international travel connectivity. As of late December 2024, critical infrastructure components, including the Passenger […]

Chinese Company Pledges to Complete Mondulkiri Wind Power Station by 2026

In a significant commitment to renewable energy in Cambodia, HK OASIS Power Energy Development Co., Ltd. has vowed to complete the construction of a 150-megawatt wind power station in Mondulkiri province by 2026. This pledge was made by Mr. Wang Junwei, the company’s representative, during a meeting with HE Chea Vuthy, Secretary General of the […]

Serei Sophorn Welcomes the New 11 hectares of Landfill

In a significant development to enhance urban environmental management around the Tonle Sap Lake, the government officially inaugurated over 11 hectares of landfill on January 17, 2025. This project, part of the Phase 2 initiative, received support through a concessional loan from the Asian Development Bank (ADB). The landfill in Kangvea village of Sangkat Kampong […]

China Approves Highest & Largest Hydropower Dam in Tibet Worth USD 127 Billion Amid Global Concerns

China has approved the construction of the world’s largest hydropower dam on the lower Yarlung Tsangpo River in Tibet, with an estimated cost of USD 127 billion. The project, poised to generate three times more energy than the Three Gorges Dam, is expected to redefine renewable energy development globally but has raised significant concerns about […]

Cambodia Welcomes 17 New Investment Projects Worth USD 150 Million in January 2025

In an exciting start to the year, Cambodia’s investment landscape is poised for growth as the country received a notable infusion of capital with 17 new investment projects. These initiatives, collectively valued at approximately USD 150 million, were registered during the inaugural “One Window Service Office” (OWSO) meeting for 2025, held on 15 January, chaired […]

Progress Update on Kampong Thom Dam Project: 25% Completion Mark Achieved

Construction on the Kampong Kor Dam is progressing steadily, with 25% of the project now completed. HE Chan Sinath, Secretary of State, provided this update during an inspection of the project on 12 January 2025. During the inspection, HE Chan Sinath outlined the project’s current status, specifying that the dam’s construction has reached 10%, while […]