Construction of Major Bridges Along Ring Road 3 Almost 100% Complete

Construction of the two bridges crossing the Bassac River along ring road 3 is on average 97.25% complete, while the overall ring road 3 construction progress is also running smoothly, according to the Ministry of Public Works and Transport on 4 July.

The two bridges include the 366-metre-long bridge west side that is approximately 99% complete and the 630-metre-long eastern bridge that is over 95.10% complete. The two bridges are scheduled for final completion by September and October this year respectively.

The ring road 3 project is a 52km concrete road that will be 22 metres wide with four lanes. The route runs through Phnom Penh for 15.42 km and Kandal province for 37.56 km, and will be a major ring road serving transportation connecting NR6, 5, 4, 3, 2, 21.

The project is expected to cost approximately US$273 million, which is a loan from China. (Read more)

Construction began in January 2019, while the construction work is being implemented by the Shanghai Construction Group Co., Ltd. with technical inspection by Guangzhou Wanan Construction Supervision Co., Ltd.

- Video Advertisement -

Related Post

Saudi Arabia’s Mukaab: the World’s Largest Building​ Breaks Ground

Construction is now officially underway on the Mukaab, a monumental 400-metre-high supertall skyscraper in Riyadh set to become the world’s largest building. Located at the heart of the 19-square-kilometer New Murabba development, the Mukaab will rise with cube-shaped dimensions, featuring 400-meter-long edges, and stand as a centerpiece of Saudi Arabia’s capital. The New Murabba Development […]

Beijing Unveils Smart Rail Project Using Data Analytics System for Reducing Carbon Emission While Optimizing Efficiency in City

Leveraging Data Analytics and Model-Based Approaches to Optimize Station Placement and Multimodal Connectivity Reducing Carbon through Public Transportation Effective public transportation is essential for vibrant, sustainable cities. It not only enhances the quality of life for residents but also significantly reduces the reliance on carbon-emitting private vehicles and cuts down on other atmospheric pollutants that […]

Bentley Digital Technology Saves China Nearly a Year & Saves More Than US$8 million on 6.5m/m2 Reservoir Project

Nestled along the scenic Woken River in Heilongjiang, China, the Taoshan Reservoir, fondly known as the “Little West Lake” of Qitaihe City, stands as a testament to modern water management excellence. Serving as a linchpin for flood control, urban water supply, and the holistic utilization of farmland irrigation and aquaculture in Heilongjiang province, this reservoir […]

Eternal Splendour Revived: APSARA Authority’s Restoration of Preah Khan Temple

The APSARA Authority has embarked on the second phase of the meticulous restoration of Preah Khan temple while preserving the ancient architectural style. Building upon the triumphant completion of the initial phase in October 2022, this endeavor reflects Cambodia’s enduring commitment to preserving its cultural heritage. The Ministry of Culture and Fine Arts unveiled their […]

PM Orders to Move Two District Halls to Newly-Developed Areas

Prime Minister Samdech Hun Sen has asked authorities to relocate two district halls in the Apsara area, where construction was banned, to the new development areas in Preak Snaeng and Run Ta Ek. Speaking at a get-together with almost 2,000 families in the Run Ta Ek development area of Banteay Srei district, PM Hun Sen […]

115ha on Ta Prom Island to be Transformed to Mixed-Use Development

The Council of Ministers has given a permit to Ta Prohm Investment Co., Ltd. to develop 116 hectares of land on Ta Prohm Island in Sangkat Prek Eang, Khan Chbar Ampov into a new development zone. According to letter No. 821 of the National Assembly dated 23 September 2022, the company will develop Ta Prom […]