Construction of US$190 million Bakeng Water Treatment Plant 38% Complete, Operational by Late 2022

Construction of the Bakeng water treatment plant phase 1 is now over 38% complete and scheduled for full completion by late 2022, according to an announcement by the Phnom Penh Water Supply Authority on Thursday 26 August.

Construction of the main water treatment section is 10% complete, the pumping station 15%, installation of the main water pipe 53%, and the drilling work to install 2000 mm water pipe across Tonle Sap 30%.

The plant is the largest water treatment plant ever built in Cambodia and will be implemented in two phases.

The first phase is scheduled for completion by the end of 2022 or early 2023, with the capacity to produce approximately 200,000 cubic meters/day of clean water, while the second phase will be able to produce 400,000 cubic metres/day by the first quarter of 2024.

Co-funded by the French Agency for Development and the European Investment Bank with an investment value of over US$190 million, the project is being constructed by Vinci Construction Grands Projects with the technical inspection done by SAFEGE Consulting Engineers.

The project was broken ground on 1 February 2021 under the presidency of Prime Minister Hun Sen after studying for 4 years since 2017. (Read more)

 

 

- Video Advertisement -

Related Post

Electric Bus Revolution in Siem Reap: A Step Towards Sustainable Transport

In an exciting development for eco-friendly public transport, Cambodia, in partnership with the Green Development Institute (GGGI), has unveiled plans for an electric bus system in Siem Reap province. The announcement came during the final workshop of the electric bus public transport system study, where three strategic routes and 33 waiting stations were officially designated. […]

Progress Report: Siem Reap River Improvement Project Phase 2 Nears Completion

The Siem Reap River Improvement Project Phase 2 is making significant strides, with the project now completed by 97%. The Siem Reap Provincial Administration announced on August 21, 2025, via its official Facebook page that the project is on track for completion by July 1, 2025. The ongoing work focuses on restoring the river and […]

National Road 7 Expansion Project on Track for Early Completion

The ambitious project to expand and improve National Road 7, transforming it from a two-lane to a four-lane highway, is currently 43% complete and is expected to finish ahead of schedule. The 45.5-kilometre stretch of road runs from Vang Vong Moul Skun in Cheung Prey District to the base of the Kizuna Bridge in Kampong […]

India-Myanmar-Thailand Trilateral Highway Stalled Amid Conflict in Myanmar

The USD 114 billion India-Myanmar-Thailand Trilateral Highway, a crucial 1,360-kilometre infrastructure project designed to enhance ASEAN economic integration and strengthen India’s trade presence in Southeast Asia, faces major setbacks due to ongoing instability in Myanmar. Designed as a four-lane highway, the Trilateral Highway is part of India’s broader infrastructure vision, which aims to extend road […]

The Construction of Sewage System and Rainwater Pumping Station is Officially Ground Breaking in Kratie City

The construction of a vital sewerage system and rainwater pumping station, officially ground-breaking on 5th March in Kratie City, is backed by over USD 7 million in funding through the Asian Development Bank-supported Rabien 4 urban development project. H.E. Poo Manit, Deputy Director General of the Project at the Ministry of Public Works and Transport, […]

Mekong River Bridge in Kratie Province Approaching Completion

The long-awaited Mekong River Bridge, stretching 1,761 meters, is on the verge of completion, now standing at an impressive 89.84%. Local authorities anticipate the temporary opening to the public in September 2025, marking a significant milestone in the region’s infrastructure development. His Excellency Lim Sidenin, Secretary of State and Project Director, provided insights during a […]