National Road 48 Upgrade Hits Milestone with 38.26% Completion

The ongoing National Road No. 48 rehabilitation project has reached a significant milestone, achieving 38.26% completion as of 23 November. The project, aimed at enhancing the road’s quality and overall infrastructure, is on track for its scheduled completion by the end of April 2025. This progress was updated in a recent inspection led by HE Peng Po, Minister of Public Works and Transport.

During the site inspection, Minister Peng Po, along with technical officials and representatives from the Korean construction company ILSUNG & HANIL Joint Venture and KCI & KECC Joint Venture Technical Consulting Company, focused on ensuring strict compliance with established standards. The thorough assessment aims to eliminate any potential gaps, guaranteeing a durable and high-quality road upon completion.

In addition to scrutinising the construction progress, the delegation explored the production site for AC rubber concrete, a noteworthy component in paving the road. This highlights the project’s commitment to employing innovative and resilient materials for long-lasting infrastructure.

The rehabilitation initiative spans 148 kilometres, commencing from the junction of National Road No. 4 at PK 141 + 750 (Chamkar Luong) to Khemarak Phoumin City, Koh Kong province. With a project starting on 3 January 2022 and a budget of approximately US$78 million, the venture is a testament to Cambodia’s dedication to advancing its transportation infrastructure. (Read more)

- Video Advertisement -

Related Post

Kampong Cham Province Achieved Significant Infrastructure Development in 2024

In a remarkable stride towards improving its infrastructure, Kampong Cham Province has completed over 119 kilometers of road construction in 2024. This achievement was announced by HE Un Chanda, the Governor of Kampong Cham Province, during a press conference. During the year 2024 alone, the province welcomed 27 projects aimed at developing DBST (Dense Bituminous […]

Major Progress Made on Flood Prevention in Western Phnom Penh

In a significant step towards mitigating flooding in western Phnom Penh, the ambitious drainage and drainage system restoration project has reached a milestone, now standing at 50.50% completion as of January 5, 2025. This essential infrastructure initiative, spearheaded by the General Department of Wastewater Treatment System under the Ministry of Public Works and Transport, aims […]

National Road 7 Expansion Project Progresses, Reaches 28.76% Completion

In a significant step towards enhancing Cambodia’s infrastructure, the ambitious project to restore and expand National Road No. 7 has reached an impressive 28.76% completion as of early January 2025. This major development was confirmed during a thorough inspection led by HE Lim Sidenin, Secretary of State of the Ministry of Public Works and Transport, […]

Progress Report: National Road No. 48 Restoration Nears Completion

The restoration and upgrade of National Road No. 48, stretching 148 kilometers from Sre Ambel to Koh Kong, has reached an impressive 78% completion as of the beginning of 2025, according to a statement from HE Phorn Rim, Spokesman of the Ministry of Public Works and Transport. The ambitious project, which commenced on January 3, […]

Major Infrastructure Development Takes Shape in Kandal Province

The China Road and Bridge Corporation (CRBC) is swiftly constructing a temporary steel bridge in Kandal province to facilitate drilling for a vital clay-stone bridge. HE Phorn Rim, the Ministry of Public Works and Transport spokesman, confirmed that this project aims to improve connectivity between the eastern outskirts of Phnom Penh and Xi Jinping Boulevard. […]

What has the border ring road construction project achieved two months after the construction site opened?

The project to build the border ring road, funded by nearly $27 million from the Border Infrastructure Fund, has made significant progress since the construction site opened on November 4, 2024.  Here are some key achievements of this historic project for Cambodia: Demining Operations: The team successfully cleared 1,462,500 square meters of unexploded ordnance, with […]