Construction of Monivong Flyover Pillars 11% Complete

The construction of the Preah Monivong flyover, the first circular flyover in Cambodia, has been 11% completed as the technical team is currently drilling 219 pillars on Samdech Techo Hun Sen Blvd and Preah Monivong Blvd. 

Mr Sam Piseth, Director of the Department of Public Works and Transport of Phnom Penh, told BTV on 7 February that the construction company is currently drilling the foundation of the Preah Monivong flyover. To date, 25 pillars have been drilled, which is 11.41% of the total. 

The NR1 zone of the project, which is the area around Hun Sen Blvd, is going smoothly. However, the NR2 zone faces difficulties due to some protests. 

In the N3 zone along Preah Monivong Blvd, three foundations have been drilled, while the rest will be done after the impact resettlement. However, the work on St. 271 has yet to start. 

The Preah Monivong flyover is being built by OCIC at a cost of more than US$36 million and will take 36 months to be completed. It is located at the intersection of Samdech Techo Hun Sen Blvd., Monivong Blvd. and St. 217 in Khan Chamkarmon and Khan Meanchey. (Read more)

 

 

- Video Advertisement -

Related Post

BYD to Establish Vehicle Assembly Plant in Sihanoukville Economic Zone

In a significant boost to Cambodia’s automotive industry, BYD, China’s leading electric car manufacturer, has announced plans to establish a vehicle assembly plant within the Sihanoukville Special Economic Zone. The project, which involves an investment of USD 32 million, is expected to create over 200 jobs and contribute to the local economy. The assembly plant […]

Cambodia Welcomes 12 New Investment Proposals Worth USD 135 Million

In a promising development for the nation’s economy, Cambodia received 12 new investment proposals in early February, collectively valued at USD 135 million. These proposals were submitted to the Cambodia Investment Committee, part of the Council for the Development of Cambodia, and will be examined at the upcoming second “Single Gateway Meeting” in 2025. The […]

As of 2024, Phnom Penh has 1877 high-rise buildings with 5 floors or more

As of 2024, Phnom Penh has a total of 453 apartment buildings and 1,877 high-rise buildings with five or more floors. This information was presented by His Excellency Keut Chhe, Deputy Governor of Phnom Penh, on February 1, 2023. Phnom Penh, the largest capital city of Cambodia, is currently experiencing rapid urbanization and industrial growth. […]

Indonesia is set to invest nearly USD 3 billion to complete the second phase of its new capital development

The Indonesian government will allocate an additional 48.8 trillion IDR (approximately USD 2.99 billion) to continue its new capital (IKN) development during the second phase, which spans from 2025 to 2029. Vietnam Plus reported this information on January 23, 2025. In the first phase (from 2022 to 2024), the Indonesian government has already invested 89 […]

Techo International Airport Nears Completion: A New Gateway to Cambodia

In an exciting development for Cambodia’s aviation sector, the Techo International Airport construction project is now over 94% complete, with the total investment reaching nearly USD 1.4 billion. This ambitious project promises to transform the country’s skyways and enhance domestic and international travel connectivity. As of late December 2024, critical infrastructure components, including the Passenger […]

Chinese Company Pledges to Complete Mondulkiri Wind Power Station by 2026

In a significant commitment to renewable energy in Cambodia, HK OASIS Power Energy Development Co., Ltd. has vowed to complete the construction of a 150-megawatt wind power station in Mondulkiri province by 2026. This pledge was made by Mr. Wang Junwei, the company’s representative, during a meeting with HE Chea Vuthy, Secretary General of the […]