Techo Int’l Airport construction progress reaches 44% completion

The construction of Phnom Penh’s Techo International Airport has reached over 44% completion, according to HE Nou Peng Chandara, Deputy Governor of Kandal Province. Speaking at a press conference on “Five Years of Success of Kandal Provincial Administration” on 30 March 2023.

HE Chandara provided an update on the settlement of land disputes, saying that the authorities are currently working to resolve any issues affecting the project. He added that 63.1% of the total area, equivalent to 1,640 hectares, had been settled.

According to him, the settlement of land disputes with residents covered more than 302 hectares, equivalent to 11%, while the land owned by the company was more than 657 hectares, equivalent to 25.26%.

Furthermore, HE Chandara highlighted that the construction of the road connecting NR 2 and Samdech Techo Blvd. to the airport, which is 13.5 km long, has reached more than 35% completion.

The Techo International Airport, which is invested by Cambodia Airport Investment Co Ltd (CAIC) under a total investment capital of approximately US$1.5 billion, is being constructed by China Construction Third Engineering Bureau Group Co., Ltd. The project covers an area of 2,600 hectares. (read more )

Investors and stakeholders interested in the project are encouraged to stay updated on the progress of the construction of Techo International Airport, as it is set to play a vital role in Cambodia’s continued development as a key player in the region.

- Video Advertisement -

Related Post

Toyota Unveils US$36 Million Assembly Plant in Phnom Penh SEZ

In a significant boost to Cambodia’s automotive industry, a new Toyota assembly plant, valued at over US$36 million, was officially inaugurated in the Phnom Penh Special Economic Zone on 2 May 2024. This landmark event was presided over by Samdech Hun Manet, Prime Minister, marking a new era in the country’s manufacturing capabilities. The Toyota […]

Cambodia Forges Ahead with International Standard Community Nurseries for Workers

Cambodia is accelerating its initiatives to establish community nurseries built to international standards. In a concerted effort to elevate working conditions and support the welfare of labourers, the Ministry of Labor and Vocational Training (MLVT) convened a pivotal meeting on 18 April 2024, in collaboration with the World Child and Development Organisation and the World […]

Cobber Packing Company Commits Over US$3 Million to Establish Cardboard Factory in SHV

The Preah Sihanouk Provincial Sub-Committee on Investment (ECCC) has greenlit an ambitious venture by Cooper Packing (Cambodia) Co., Ltd., investing upwards of US$3 million to erect a state-of-the-art cardboard factory in Sihanoukville. The decision came to light during a meeting presided over by Mr. Kouch Chamroeun, Governor of Preah Sihanouk Province, on 17 April 2024. […]

Construction Sector Thrives: Ministry Approves 3,207 Projects Worth US$5.4bn in 2023

In 2023, Cambodia’s construction landscape witnessed a remarkable surge, with the Ministry of Economy and Finance (MEF) greenlighting a total of 3,207 construction projects, collectively valued at US$5.4 billion. This data, unveiled in a ministry report, highlights a significant stride in the nation’s development trajectory. The report indicates a notable shift in construction dynamics compared […]

Hong Kong Firm, Sunwah Group, Expands Investment Horizons in Cambodia, Eyes Five Key Sectors

Hong Kong-based Sunwah Group is set to broaden its investment portfolio in Cambodia, signalling its intent to venture into five pivotal sectors beyond its existing seafood processing operations, which have been operational since 1994. This development emerged from a high-level meeting between Prime Minister Samdech Hun Manet and Mr. Jonathan K.S. Choi, President of Sunwah […]

Construction Begins on Quảng Trị’s US$580m Deep-water Port After 4-Year Delay

Construction of the long-awaited Mỹ Thủy deep-water port project in Quảng Trị Southeast Economic Zone finally commenced on Monday, following a four-year delay, according to Vietnamnews on 26 March 2024. Approved by the Prime Minister on 4 January 2019, with a total investment of VNĐ14.2 trillion (US$580 million), this project is of paramount importance to […]