Rehabilitation & Expansion of NR No. 4 Reaches 55% Completion

As of the end of June 2024, the ambitious project to rehabilitate and expand NR No. 4 from Bek Chan commune in Kandal province to Bit Trang commune in Prey Nob district, Preah Sihanouk province, has achieved 54.80% completion. This significant milestone was confirmed by the Ministry of Public Works and Transport on their official Facebook page on 5 July 2024.

HE Pheng Sovicheano, Secretary of State and Director of the NR No. 4 Rehabilitation and Quality Improvement Project, provided detailed insights into the project’s progress. The project encompasses six main sections and two additional packages focused on bridge repairs and new bridge construction.

Project Breakdown:

  1. Section 1: Km 19 + 700 to Km 60 + 000 (Kandal and Kampong Speu provinces) – 28.80 km of four lanes and 11.50 km of two lanes, totalling 40.30 km.
  2. Section 2: Km 60 + 000 to Km 101 + 000 (Kampong Speu province) – 2.68 km of four lanes and 38.32 km of two lanes, totalling 41.00 km.
  3. Section 3: Km 101 + 000 to Km 143 + 000 (Kampong Speu and Koh Kong provinces) – 0.30 km of four lanes and 41.70 km of two lanes, totalling 42.00 km.
  4. Section 4: Km 143 + 000 to Km 186 + 000 (Koh Kong and Preah Sihanouk provinces) – 0.93 km of four lanes and 42.07 km of two lanes, totalling 43.00 km. This section faced delays, leading to the contractor’s contract being cancelled and a deposit of $800,000 being confiscated. The ministry will re-procure this section in August.
  5. Section 5: Km 186 + 000 to Km 215 + 800 (Sihanoukville) – 7.30 km of four lanes and 22.50 km of two lanes, totalling 29.80 km.
  6. Package 6: Km 48 + 695 to Km 202 + 688 – Repairs of 24 old bridges, 8 box drains, 9 round drains, and replacement of 5 old bridge components in Kampong Speu, Koh Kong, and Sihanoukville.
  7. Package 7: Km 38 + 076 to Km 204 + 973 – Construction of 8 new bridges in Kampong Speu, Koh Kong, and Sihanoukville.

It is noteworthy that the Cambodian government has secured a US$110 million concessional loan from the World Bank to facilitate the construction, expansion, and maintenance of NR No. 4. This investment aims to enhance the safety of transportation, boost goods transport efficiency, and ensure climate resilience.

The rehabilitation and expansion project began on 3 January 2022, with an expected completion date by the end of 2026, spanning a total of 17 months of construction work. (Read more)

- Video Advertisement -

Related Post

Brunei’s Khazanah Nasional Targets Multi-Sector Infrastructure Investment in Cambodia

Khazanah Nasional Berhad, a leading investment firm from Brunei Darussalam, has announced plans to explore infrastructure investment opportunities in Cambodia, focusing on health, water resources, transport infrastructure (including railways and airports), and banking. This initiative was discussed during a meeting between PM Hun Manet and Khazanah’s CEO, Mr. Dato Khairul Hamed, on 19 November 2024. […]

China Construction America Ordered to Pay US$1.6 Billion and Conflict of Political Interests Behind

A New York court has ordered China Construction America Inc. (CCA), a subsidiary of Chinese state-owned China State Construction Engineering, to pay US$1.6 billion to BML Properties, the original owner of the Baha Mar casino resort in the Bahamas, after the contractor was found to have committed “many acts of fraud” during its takeover of […]

Phnom Penh-SHV Expressway Offers Exclusive Discounts for 3-Day Water Festival Celebration

To celebrate the Royal Water Festival from 14 to 16 November 2024, the Ministry of Public Works and Transport (MPWT) has announced a special three-day discount on the Phnom Penh-Sihanoukville Expressway. Notification No. 052 S.K.R., dated 12 November 2024, confirmed that the Phnom Penh-Sihanoukville Expressway Company will offer a 20% discount on toll fees for […]

Groundbreaking of 500-Hectare Green Textile Industrial Park in Kampong Speu to Create Up to 60K Jobs

A groundbreaking ceremony on 8 November 2024 marked the start of a 500-hectare green textile industrial park in Chheu Neang Village, Taing Sya Commune, Phnom Sruoch District, Kampong Speu. Attended by HE Heng Sour, Minister of Labor and Vocational Training, HE Dr. Cheam Chansophoan, Governor of Kampong Speu Province, and Mr. John Yu, Chairman of […]

PM Inaugurates USD10 Million Techo Santepheap Ankoul Beach Road to Boost Tourism in Kep

The USD10 million Techo Santepheap Ankoul Road project, aimed at enhancing tourism infrastructure, was officially inaugurated in Ang Kol, Kep Village, and Angkor Village within the Ang Koul Commune of Damnak Chang Eur District, Kep Province. Led by PM Samdech Hun Manet, the ceremony on 11 November 2024 marked the completion of this pivotal project […]

NR No. 33 (Kampot-Chrak Lok) Reaches 99% Completion, Strengthening Provincial Transport Network

NR No. 33, connecting Kampot to Chrak Lok, is on the cusp of completion, with an impressive 98.89% of the project finalised as of early November 2024. This achievement was highlighted in an official inspection conducted on 6 November 2024 by HE Pal Chandara, Secretary of State of the Ministry of Public Works and Transport, […]