Rehabilitation & Expansion of NR No. 4 Reaches 55% Completion

As of the end of June 2024, the ambitious project to rehabilitate and expand NR No. 4 from Bek Chan commune in Kandal province to Bit Trang commune in Prey Nob district, Preah Sihanouk province, has achieved 54.80% completion. This significant milestone was confirmed by the Ministry of Public Works and Transport on their official Facebook page on 5 July 2024.

HE Pheng Sovicheano, Secretary of State and Director of the NR No. 4 Rehabilitation and Quality Improvement Project, provided detailed insights into the project’s progress. The project encompasses six main sections and two additional packages focused on bridge repairs and new bridge construction.

Project Breakdown:

  1. Section 1: Km 19 + 700 to Km 60 + 000 (Kandal and Kampong Speu provinces) – 28.80 km of four lanes and 11.50 km of two lanes, totalling 40.30 km.
  2. Section 2: Km 60 + 000 to Km 101 + 000 (Kampong Speu province) – 2.68 km of four lanes and 38.32 km of two lanes, totalling 41.00 km.
  3. Section 3: Km 101 + 000 to Km 143 + 000 (Kampong Speu and Koh Kong provinces) – 0.30 km of four lanes and 41.70 km of two lanes, totalling 42.00 km.
  4. Section 4: Km 143 + 000 to Km 186 + 000 (Koh Kong and Preah Sihanouk provinces) – 0.93 km of four lanes and 42.07 km of two lanes, totalling 43.00 km. This section faced delays, leading to the contractor’s contract being cancelled and a deposit of $800,000 being confiscated. The ministry will re-procure this section in August.
  5. Section 5: Km 186 + 000 to Km 215 + 800 (Sihanoukville) – 7.30 km of four lanes and 22.50 km of two lanes, totalling 29.80 km.
  6. Package 6: Km 48 + 695 to Km 202 + 688 – Repairs of 24 old bridges, 8 box drains, 9 round drains, and replacement of 5 old bridge components in Kampong Speu, Koh Kong, and Sihanoukville.
  7. Package 7: Km 38 + 076 to Km 204 + 973 – Construction of 8 new bridges in Kampong Speu, Koh Kong, and Sihanoukville.

It is noteworthy that the Cambodian government has secured a US$110 million concessional loan from the World Bank to facilitate the construction, expansion, and maintenance of NR No. 4. This investment aims to enhance the safety of transportation, boost goods transport efficiency, and ensure climate resilience.

The rehabilitation and expansion project began on 3 January 2022, with an expected completion date by the end of 2026, spanning a total of 17 months of construction work. (Read more)

- Video Advertisement -

Related Post

Cambodia and Korea Sign Contract to Fast-Track $235 Million Areyaksat Bridge Construction by Mid-2025

Cambodia and Korea have sealed a comprehensive contract to expedite the construction of the Cambodia-Korea Friendship Bridge, with work slated to begin by the end of the first half of 2025. The contract, signed on 25 September 2024, details the technical collaboration between the Ministry of Public Works and Transport and Korea’s Yooshin Engineering Corporation. […]

Final 35 km Section of NR No. 5, Valued at Over USD 52 Million, Reaches 25% Completion

The final section of Cambodia’s NR No. 5, spanning 35.14 km between Serey Sophorn and Poipet, has reached 25% completion as of early September 2024, according to Ministry of Public Works and Transport, 18 September 2024. With a project cost of USD 52.56 million, funded by the Government of Cambodia and Japan’s Credit Assistance, the […]

Hong Kong International Airport Surpasses Changi to Become Asia’s Leading Hub in 2024

Hong Kong International Airport has overtaken Singapore’s Changi Airport to claim the prestigious title of “Asia’s Leading Airport” at the 2024 World Tourism Awards, according to Seasia, 9 September 2024. This marks a significant milestone, as Changi Airport had held this top position for several consecutive years before the pandemic. The win highlights Hong Kong’s […]

Large-Scale Drainage Project on Phnom Penh’s NR 4 Surpasses Schedule by 11%

The construction of a major drainage system along NR 4 in Phnom Penh has achieved an 11% faster progress rate, reaching a completed length of 624 meters. The project, which is part of a broader effort to modernize the city’s sewer infrastructure, aims to improve flood prevention and sanitation across key districts. This update was […]

SHV’s New 253-Meter Container Port Inaugurated with Japanese Aid

A new 253-meter-long container terminal at Sihanoukville Autonomous Port was officially inaugurated on 12 September 2024, marking a significant expansion for Cambodia’s primary port. Attended by PM Samdech Hun Manet, the ceremony highlighted the terminal’s modernized capabilities. The port now include advanced container lifts and loading equipment, boosting the port’s capacity from 550,000 TEU to […]

Three Key Rural Roads Near Completion in Kampong Cham & Tbong Khmum

Three rural roads spanning over 40 kilometres in Kampong Cham and Tbong Khmum provinces are nearing full completion, with construction progress close to 100% as of 4 September 2024. The Ministry of Rural Development has overseen this crucial infrastructure project, which aims to enhance regional connectivity and promote agricultural trade. The first road, measuring 17.55km, […]