Transport Minister Urges Construction Firm to Finish Kampot Tourism Port by June

Minister of Public Works and Transport HE Sun Chanthol has ordered the responsible firm to finish Kampot Tourism Port’s construction by June 2021 after several delays.

HE Sun Chanthol said during the site inspection on 04 January that the company should set a concrete plan or add more labour to accelerate the construction speed and to ensure that it proceeds as scheduled.

“It is not good to delay the construction. The Ministry of Tourism is not happy, and ADB is also not happy. Therefore, the firm must follow the contract and properly finish the construction with the promised quality by June,” said HE Sun.

The firm has accepted the request and reported that the construction is now 45% completed, with the structure scheduled for April.

HE Sun Chanthol’s order comes after the temporary halt in construction procedure due to the COVID-19 crisis, which caused construction delays several times. (Read more and more)

Located in Toek Chhu district, the ground was broken on the project in August 2018 and is being built under an US$8 million loan from the Asia Development Bank (ABD). (Read more)

Once operational, the 300-metre-long port will allow the docking of tourism vessels, which can carry up to 300 to 400 passengers.

The Kampot international tourism seaport will be the main gateway connecting tourism vessels from Thailand and Vietnam to Cambodia’s Kampot province.

- Video Advertisement -

Related Post

Techo International Airport Nears Completion: A New Gateway to Cambodia

In an exciting development for Cambodia’s aviation sector, the Techo International Airport construction project is now over 94% complete, with the total investment reaching nearly USD 1.4 billion. This ambitious project promises to transform the country’s skyways and enhance domestic and international travel connectivity. As of late December 2024, critical infrastructure components, including the Passenger […]

Chinese Company Pledges to Complete Mondulkiri Wind Power Station by 2026

In a significant commitment to renewable energy in Cambodia, HK OASIS Power Energy Development Co., Ltd. has vowed to complete the construction of a 150-megawatt wind power station in Mondulkiri province by 2026. This pledge was made by Mr. Wang Junwei, the company’s representative, during a meeting with HE Chea Vuthy, Secretary General of the […]

Serei Sophorn Welcomes the New 11 hectares of Landfill

In a significant development to enhance urban environmental management around the Tonle Sap Lake, the government officially inaugurated over 11 hectares of landfill on January 17, 2025. This project, part of the Phase 2 initiative, received support through a concessional loan from the Asian Development Bank (ADB). The landfill in Kangvea village of Sangkat Kampong […]

China Approves Highest & Largest Hydropower Dam in Tibet Worth USD 127 Billion Amid Global Concerns

China has approved the construction of the world’s largest hydropower dam on the lower Yarlung Tsangpo River in Tibet, with an estimated cost of USD 127 billion. The project, poised to generate three times more energy than the Three Gorges Dam, is expected to redefine renewable energy development globally but has raised significant concerns about […]

Cambodia Welcomes 17 New Investment Projects Worth USD 150 Million in January 2025

In an exciting start to the year, Cambodia’s investment landscape is poised for growth as the country received a notable infusion of capital with 17 new investment projects. These initiatives, collectively valued at approximately USD 150 million, were registered during the inaugural “One Window Service Office” (OWSO) meeting for 2025, held on 15 January, chaired […]

Progress Update on Kampong Thom Dam Project: 25% Completion Mark Achieved

Construction on the Kampong Kor Dam is progressing steadily, with 25% of the project now completed. HE Chan Sinath, Secretary of State, provided this update during an inspection of the project on 12 January 2025. During the inspection, HE Chan Sinath outlined the project’s current status, specifying that the dam’s construction has reached 10%, while […]