NR No. 31 Project Connecting Bek Kus to Kampong Trach Nears Completion with Over 95% Progress

By the end of June 2024, the project to restore and upgrade NR No. 31, spanning over 53 kilometres, has achieved 95.38% completion. The Ministry of Public Works and Transport confirmed this progress on their official Facebook page on 3 July 2024.

The construction work, which began on 30 December 2022, is on track to be completed nearly a year ahead of the contracted deadline. The project includes paving two layers of AC concrete, which is now 100% complete. Remaining tasks such as installing traffic safety features—traffic signs, road signs, guardrails, and other necessary infrastructure—are scheduled for completion by the end of August 2024.

The project aims to enhance the quality of NR No. 31 with a total length of 53.53km, stretching from Bek Kus at the intersection of NR No. 3 to Kampong Trach district town, connecting to NR No. 33. The comprehensive upgrade is expected to significantly improve transportation efficiency and safety for residents along the route. (Read more)

- Video Advertisement -

Related Post

Singapore Resumes Construction of Changi Airport’s Largest Passenger Terminal After Pandemic Delay

In a significant milestone for Singapore’s aviation sector, the construction of Terminal 5 (T5) at Changi Airport has officially commenced following a two-year pause brought on by the COVID-19 pandemic. The groundbreaking ceremony, which took place on May 14, 2025, was graced by Prime Minister Lawrence Wong. Prime Minister Wong highlighted that the new terminal […]

Doun Tri Dam Construction 97% Completion

  The construction of the Doun Tri Dam in Battambang province is now 97% complete, with final completion expected by October 2025. This significant infrastructure project, located in Rukkakiri district, is being financed through concessional loans from the Republic of Korea. During a project progress review led by His Excellency Tho Jetha, Minister of Water […]

Irrigation System Project in Banteay Meanchey and Battambang is 75% Completed

  Banteay Meanchey and Battambang provinces are making strides in agricultural development as the irrigation system construction project reaches a significant milestone. As of May 7, 2025, the project is 75% complete, thanks to financing from the Korean Eximbank. During a progress review meeting led by His Excellency Minister Tho Jetha, Minister of Water Resources […]

Mekong River Bridge in Kratie Province Nearing Completion

As of early May 2025, the Mekong River Bridge in Kratie Province is making impressive strides, with construction now 94% complete. The 1,761-meter-long bridge is expected to temporarily open to traffic in September 2025, pending the completion of final touches. The update was shared on the official Facebook page of the Ministry of Public Works […]

Significant Infrastructure Development: Three Key National Roads Inaugurated in Cambodia

In a significant step towards enhancing connectivity in Cambodia, three major national roads totalling over 201 kilometers were officially inaugurated today. Prime Minister Hun Sen officiated the event alongside Chinese Ambassador to Cambodia, Wang Wenbin. The newly inaugurated roads—National Road 31, National Road 33, and National Road 41—are essential links connecting Phnom Penh to various […]

Progress on Cambodia’s Highest Bridge Construction

The construction team is making significant strides as they roll out asphalt to complete Bridge No. 28, currently the highest bridge in Cambodia. This vital infrastructure project is part of the National Road 10 construction initiative, which aims to enhance regional connectivity. Following a temporary closure to the public during the Khmer New Year celebration […]