What has the Border Ring Road Construction Project Achieved Two Months after Construction Started?

The project to build the border ring road, funded by nearly USD 27 million from the Border Infrastructure Fund, has made significant progress since the construction site opened on 4 November 2024.  Here are some key achievements of this historic project for Cambodia:

Demining Operations:

The team successfully cleared 1,462,500 square meters of unexploded ordnance, with 1,225,000 square meters in Mondulkiri province and 237,500 square meters in Ratanakkiri province. During the search for mines, the team discovered 23 rounds of ammunition, including six bombs or cluster munitions. The Engineering Command of the Royal Cambodian Armed Forces (RCAF) works diligently to ensure the area’s safety.

Clearance Work:

  • A road with a width of 5 meters has been cleared, reaching a total length of 58.5 kilometers (49 kilometers in Mondulkiri and 9.5 kilometers in Ratanakkiri).
  • A 20-meter-wide road has been cleared for 36 kilometers (27.9 kilometers in Mondulkiri and 8.7 kilometers in Ratanakkiri) to identify the road axis by clearing valleys and lowlands.
  • Canal construction has reached 30.20 kilometers (20.60 kilometers in Mondulkiri and 7.6 kilometers in Ratanakkiri).
  • The construction of the road and mountain walls has totaled 25 kilometers (22 kilometers in Mondulkiri and 3 kilometers in Ratanakkiri).
  • Paving work has been completed over a length of 10.20 kilometers in Mondulkiri province.

The team and engineering unit at the border ring road construction site are committed to working responsibly to achieve this historic project according to plan. Their relentless efforts are paving the way for a bright future for Cambodia.

Cambodia has officially constructed a 250-kilometre border ring road, funded by nearly USD 27 million raised through donations to the Foundation for Border Infrastructure Development (FBID). The ground-breaking ceremony for this vital infrastructure project took place on 1 November 2024. (Read more)

- Video Advertisement -

Related Post

Singapore Resumes Construction of Changi Airport’s Largest Passenger Terminal After Pandemic Delay

In a significant milestone for Singapore’s aviation sector, the construction of Terminal 5 (T5) at Changi Airport has officially commenced following a two-year pause brought on by the COVID-19 pandemic. The groundbreaking ceremony, which took place on May 14, 2025, was graced by Prime Minister Lawrence Wong. Prime Minister Wong highlighted that the new terminal […]

Doun Tri Dam Construction 97% Completion

  The construction of the Doun Tri Dam in Battambang province is now 97% complete, with final completion expected by October 2025. This significant infrastructure project, located in Rukkakiri district, is being financed through concessional loans from the Republic of Korea. During a project progress review led by His Excellency Tho Jetha, Minister of Water […]

Irrigation System Project in Banteay Meanchey and Battambang is 75% Completed

  Banteay Meanchey and Battambang provinces are making strides in agricultural development as the irrigation system construction project reaches a significant milestone. As of May 7, 2025, the project is 75% complete, thanks to financing from the Korean Eximbank. During a progress review meeting led by His Excellency Minister Tho Jetha, Minister of Water Resources […]

Mekong River Bridge in Kratie Province Nearing Completion

As of early May 2025, the Mekong River Bridge in Kratie Province is making impressive strides, with construction now 94% complete. The 1,761-meter-long bridge is expected to temporarily open to traffic in September 2025, pending the completion of final touches. The update was shared on the official Facebook page of the Ministry of Public Works […]

Significant Infrastructure Development: Three Key National Roads Inaugurated in Cambodia

In a significant step towards enhancing connectivity in Cambodia, three major national roads totalling over 201 kilometers were officially inaugurated today. Prime Minister Hun Sen officiated the event alongside Chinese Ambassador to Cambodia, Wang Wenbin. The newly inaugurated roads—National Road 31, National Road 33, and National Road 41—are essential links connecting Phnom Penh to various […]

Progress on Cambodia’s Highest Bridge Construction

The construction team is making significant strides as they roll out asphalt to complete Bridge No. 28, currently the highest bridge in Cambodia. This vital infrastructure project is part of the National Road 10 construction initiative, which aims to enhance regional connectivity. Following a temporary closure to the public during the Khmer New Year celebration […]