What has the Border Ring Road Construction Project Achieved Two Months after Construction Started?

The project to build the border ring road, funded by nearly USD 27 million from the Border Infrastructure Fund, has made significant progress since the construction site opened on 4 November 2024.  Here are some key achievements of this historic project for Cambodia:

Demining Operations:

The team successfully cleared 1,462,500 square meters of unexploded ordnance, with 1,225,000 square meters in Mondulkiri province and 237,500 square meters in Ratanakkiri province. During the search for mines, the team discovered 23 rounds of ammunition, including six bombs or cluster munitions. The Engineering Command of the Royal Cambodian Armed Forces (RCAF) works diligently to ensure the area’s safety.

Clearance Work:

  • A road with a width of 5 meters has been cleared, reaching a total length of 58.5 kilometers (49 kilometers in Mondulkiri and 9.5 kilometers in Ratanakkiri).
  • A 20-meter-wide road has been cleared for 36 kilometers (27.9 kilometers in Mondulkiri and 8.7 kilometers in Ratanakkiri) to identify the road axis by clearing valleys and lowlands.
  • Canal construction has reached 30.20 kilometers (20.60 kilometers in Mondulkiri and 7.6 kilometers in Ratanakkiri).
  • The construction of the road and mountain walls has totaled 25 kilometers (22 kilometers in Mondulkiri and 3 kilometers in Ratanakkiri).
  • Paving work has been completed over a length of 10.20 kilometers in Mondulkiri province.

The team and engineering unit at the border ring road construction site are committed to working responsibly to achieve this historic project according to plan. Their relentless efforts are paving the way for a bright future for Cambodia.

Cambodia has officially constructed a 250-kilometre border ring road, funded by nearly USD 27 million raised through donations to the Foundation for Border Infrastructure Development (FBID). The ground-breaking ceremony for this vital infrastructure project took place on 1 November 2024. (Read more)

- Video Advertisement -

Related Post

Progress Report on National Road 5: Final Section Construction Updates

As of early February 2025, significant progress has been made on the final section of National Road 5, stretching from Seri Sophon to Poipet. With a total length of 35.14 kilometers, this crucial infrastructure project is currently 29% complete and is on track for completion in 2026. The update was shared by His Excellency Phon […]

Phnom Penh Infrastructure Project Advancing Rapidly to Combat Flooding

In a significant step towards enhancing urban resilience, a major infrastructure project targeting flood prevention in the western districts of Phnom Penh is now over 66% complete. The initiative, which focuses on installing large-scale box culverts, is actively transforming National Road 4 and surrounding areas. Managed by the PPPP-TCM joint venture, this ambitious project encompasses […]

Bavet City Takes a Major Step Towards Sustainability: Landfill Project Underway

In an exciting development for Bavet City, the construction of a significant landfill project has officially commenced on a sprawling 21-hectare site in Trang Mtes village, located in the heart of Svay Rieng province. The groundbreaking ceremony, held on January 31, 2025, began a transformative initiative to enhance the city’s environmental infrastructure. This project is […]

Japan Strengthens Cambodia’s Infrastructure with New Aid Package over USD 446K

In a significant move to bolster infrastructure development in Cambodia, the Japanese government has announced a generous aid package totaling USD 446,801 for three critical projects focusing on irrigation systems and bridge construction. HE Ueno Atsushi, Japan’s Ambassador to Cambodia, officially signed the grant agreement on 30th January alongside representatives from the three beneficiary institutions […]

National Road 7 Expansion Reaches 32% Completion

As of January 30, 2025, construction on the vital National Road 7 expansion project has reached a notable milestone, achieving 32.01% of its overall progress. The initiative, aimed at enhancing connectivity and promoting economic growth, focuses on upgrading the road to four lanes over a total span of 45.5 kilometers. The work stretches from the […]

Completion Progress on National Road No. 23 Reaches 70%

The ambitious construction project for the 20-kilometer stretch of National Road No. 23, linking Koh Thom and Loek Dek districts in Kandal province, has made significant headway, with approximately 70% of the work completed. According to a report by Cambodia National Television, the project is set to conclude in April 2025. His Excellency Phay Sovicheano, […]