SR 38-road Renovation Project 63% Complete, On Track for Final Completion in December

Construction of the 38-road renovations in Siem Reap will be completed by December this year as scheduled, while progress to date has reached over 63%, according to Minister of Public Works and Transport HE Sun Chanthol during his site inspection on 28 June.

As of 25 June, the overall construction is 63.87% complete, of which the drainage system is at 90%, the drainage system for the 38 roads at 87%, and the lighting and gardening work at 40%.

HE Sun Chanthol also rejected criticism on social media that the ministry used thin steel reinforcements and does not comply with technical standards but clarified that there are different sizes of steel for different placements and all the works are following the technical standards.

On this occasion, the minister also urged the construction team to spray water regularly on the construction site to prevent dust, quickly close the sewers in front of shophouses, and ensure that the construction does not cause traffic jams.

With a total length of 108km and estimated to consume a total budget of US$140 million, this project stretches across 12 districts of Siem Reap city and a part of Prasat Bakong and the 38 roads will be well-connected with other main road systems to ease traffic congestion and reduce accidents. (Read more)

The government also decided to reallocate the remaining budget from Sihanoukville’s 34-road renovation project to upgrade the sidewalks along the Siem Reap River. Another separate US$9-million budget has also been reallocated to restore rainwater and sewage systems.

- Video Advertisement -

Related Post

Brunei’s Khazanah Nasional Targets Multi-Sector Infrastructure Investment in Cambodia

Khazanah Nasional Berhad, a leading investment firm from Brunei Darussalam, has announced plans to explore infrastructure investment opportunities in Cambodia, focusing on health, water resources, transport infrastructure (including railways and airports), and banking. This initiative was discussed during a meeting between PM Hun Manet and Khazanah’s CEO, Mr. Dato Khairul Hamed, on 19 November 2024. […]

China Construction America Ordered to Pay US$1.6 Billion and Conflict of Political Interests Behind

A New York court has ordered China Construction America Inc. (CCA), a subsidiary of Chinese state-owned China State Construction Engineering, to pay US$1.6 billion to BML Properties, the original owner of the Baha Mar casino resort in the Bahamas, after the contractor was found to have committed “many acts of fraud” during its takeover of […]

Phnom Penh-SHV Expressway Offers Exclusive Discounts for 3-Day Water Festival Celebration

To celebrate the Royal Water Festival from 14 to 16 November 2024, the Ministry of Public Works and Transport (MPWT) has announced a special three-day discount on the Phnom Penh-Sihanoukville Expressway. Notification No. 052 S.K.R., dated 12 November 2024, confirmed that the Phnom Penh-Sihanoukville Expressway Company will offer a 20% discount on toll fees for […]

Groundbreaking of 500-Hectare Green Textile Industrial Park in Kampong Speu to Create Up to 60K Jobs

A groundbreaking ceremony on 8 November 2024 marked the start of a 500-hectare green textile industrial park in Chheu Neang Village, Taing Sya Commune, Phnom Sruoch District, Kampong Speu. Attended by HE Heng Sour, Minister of Labor and Vocational Training, HE Dr. Cheam Chansophoan, Governor of Kampong Speu Province, and Mr. John Yu, Chairman of […]

PM Inaugurates USD10 Million Techo Santepheap Ankoul Beach Road to Boost Tourism in Kep

The USD10 million Techo Santepheap Ankoul Road project, aimed at enhancing tourism infrastructure, was officially inaugurated in Ang Kol, Kep Village, and Angkor Village within the Ang Koul Commune of Damnak Chang Eur District, Kep Province. Led by PM Samdech Hun Manet, the ceremony on 11 November 2024 marked the completion of this pivotal project […]

NR No. 33 (Kampot-Chrak Lok) Reaches 99% Completion, Strengthening Provincial Transport Network

NR No. 33, connecting Kampot to Chrak Lok, is on the cusp of completion, with an impressive 98.89% of the project finalised as of early November 2024. This achievement was highlighted in an official inspection conducted on 6 November 2024 by HE Pal Chandara, Secretary of State of the Ministry of Public Works and Transport, […]