Technical Study on “Forever-Damaged” Kampot-Veal Renh Route to be Completed This Year, Expected to Cost US$60 million

A study to properly repair the so-called ‘forever damaged’ Kampot-Veal Renh road section is scheduled to be completed by the end of this year, with an estimated rehabilitation cost of about US$60 million.

This is according to an inspection by the Minister of Public Works and Transport HE Sun Chanthol on Saturday 5 June.

The NR3 section from Kampot to Veal Renh has a total length of 54.3 km, which has been repaired continuously since 2018 with a budget of US$15.85 million. The repairs were almost complete. However, due to flooding, the 20km section, which has soft-soil foundations, was completely damaged. (Read more & more)

Therefore, the Ministry asked a private firm to study an in-depth repair plan on this 20km section. The study results show that:

The first section is 15km long with foundations similar to NR146B that is under construction. Therefore, the method can be studied and adjusted from the NR146B. This section will be paved with 26cm thick concrete and be 12m wide, which is expected to cost US$30 million.

The second 5km long section has a soft soil foundation approximately 11 to 17cm deep. The experts are studying the method to remove the soil and building pillars to strengthen the foundation. The road surface will be paved with 26cm thick concrete and be 16m wide, which is expected to cost US$ 30 million.

While waiting for the study to be completed by the end of the year, the ministry is also seeking a budget of about US$60 million.

In addition to presenting this study, HE Sun Chanthol also said that the restoration of NR3 (Chom Chao-Kampot) is 98.04% complete.

- Video Advertisement -

Related Post

The Government Announces New Opening Date for Techo International Airport

In a significant new update for travelers and the aviation industry, the State Secretariat of Civil Aviation has announced a revised opening date for the much-anticipated Techo International Airport in Takhmao. Originally set to open on July 10, 2025, the grand opening is now scheduled for September 9, 2025, as indicated in a notice issued […]

National Road 10 Completed: Enhancing Regional Connectivity

The construction of National Road 10, stretching over 197.36 kilometers, has been officially completed, marking a significant milestone in the region’s infrastructure development. The road is now fully operational and has undergone a thorough inspection by a team of skilled technicians to ensure its longevity and adherence to technical standards. A detailed assessment was conducted […]

Singapore Resumes Construction of Changi Airport’s Largest Passenger Terminal After Pandemic Delay

In a significant milestone for Singapore’s aviation sector, the construction of Terminal 5 (T5) at Changi Airport has officially commenced following a two-year pause brought on by the COVID-19 pandemic. The groundbreaking ceremony, which took place on May 14, 2025, was graced by Prime Minister Lawrence Wong. Prime Minister Wong highlighted that the new terminal […]

Doun Tri Dam Construction 97% Completion

  The construction of the Doun Tri Dam in Battambang province is now 97% complete, with final completion expected by October 2025. This significant infrastructure project, located in Rukkakiri district, is being financed through concessional loans from the Republic of Korea. During a project progress review led by His Excellency Tho Jetha, Minister of Water […]

Irrigation System Project in Banteay Meanchey and Battambang is 75% Completed

  Banteay Meanchey and Battambang provinces are making strides in agricultural development as the irrigation system construction project reaches a significant milestone. As of May 7, 2025, the project is 75% complete, thanks to financing from the Korean Eximbank. During a progress review meeting led by His Excellency Minister Tho Jetha, Minister of Water Resources […]

Mekong River Bridge in Kratie Province Nearing Completion

As of early May 2025, the Mekong River Bridge in Kratie Province is making impressive strides, with construction now 94% complete. The 1,761-meter-long bridge is expected to temporarily open to traffic in September 2025, pending the completion of final touches. The update was shared on the official Facebook page of the Ministry of Public Works […]