Construction of NR No. 10 Reached 88.38% & Tallest Bridge Progressing Steadily, On Track for March 2025 Opening

As of the end of June 2024, the construction of NR No. 10, connecting Koh Kong, Pursat, and Battambang provinces, has reached 88.38% completion, while the tallest bridge, spanning 530 metres, has reached 43.50% completion. The road is slated for trial use by the end of March 2025, as per the latest update from the Ministry of Public Works and Transport published on 1 June 2024.

The overall progress of road construction stands at 80.26%, with the bridge work achieving 93.23%. The tallest bridge, measuring 530 metres, is also at 43.50% completion, with trial use scheduled for the end of March 2025. Additionally, drainage work across the road is 99.82% complete, while drainage work along the road and the retaining wall stands at 89.84% completion.

Despite the ongoing rainy season, travel along NR 10 remains relatively smooth, though caution is advised due to some sections being covered with red gravel and potential slipperiness during heavy rain.

NR No. 10 is a Grade III double-paved road (DBST) with a total length of 198.518km and a width of 9 metres. Funded by the Chinese government, the project has a total cost exceeding US$188 million, significantly enhancing regional connectivity and infrastructure development. (Read more)

- Video Advertisement -

Related Post

Phnom Penh Infrastructure Project Advancing Rapidly to Combat Flooding

In a significant step towards enhancing urban resilience, a major infrastructure project targeting flood prevention in the western districts of Phnom Penh is now over 66% complete. The initiative, which focuses on installing large-scale box culverts, is actively transforming National Road 4 and surrounding areas. Managed by the PPPP-TCM joint venture, this ambitious project encompasses […]

Bavet City Takes a Major Step Towards Sustainability: Landfill Project Underway

In an exciting development for Bavet City, the construction of a significant landfill project has officially commenced on a sprawling 21-hectare site in Trang Mtes village, located in the heart of Svay Rieng province. The groundbreaking ceremony, held on January 31, 2025, began a transformative initiative to enhance the city’s environmental infrastructure. This project is […]

Japan Strengthens Cambodia’s Infrastructure with New Aid Package over USD 446K

In a significant move to bolster infrastructure development in Cambodia, the Japanese government has announced a generous aid package totaling USD 446,801 for three critical projects focusing on irrigation systems and bridge construction. HE Ueno Atsushi, Japan’s Ambassador to Cambodia, officially signed the grant agreement on 30th January alongside representatives from the three beneficiary institutions […]

National Road 7 Expansion Reaches 32% Completion

As of January 30, 2025, construction on the vital National Road 7 expansion project has reached a notable milestone, achieving 32.01% of its overall progress. The initiative, aimed at enhancing connectivity and promoting economic growth, focuses on upgrading the road to four lanes over a total span of 45.5 kilometers. The work stretches from the […]

Completion Progress on National Road No. 23 Reaches 70%

The ambitious construction project for the 20-kilometer stretch of National Road No. 23, linking Koh Thom and Loek Dek districts in Kandal province, has made significant headway, with approximately 70% of the work completed. According to a report by Cambodia National Television, the project is set to conclude in April 2025. His Excellency Phay Sovicheano, […]

National Road 48 Rehabilitation Nears Completion: 82% Finish Mark Achieved

The long-awaited rehabilitation and upgrade of National Road 48, stretching 148 kilometers from Sre Ambel to Koh Kong, has completed an impressive 82.03%. His Excellency Phon Rim, spokesperson for the Ministry of Public Works and Transport, announced this on January 29, 2025. The construction project, which officially commenced on January 3, 2022, aims to significantly […]