Kampong Cham’s New Landfill Project Achieves Over 80% Completion

The ambitious project to construct a large landfill in Kampong Cham has surpassed the 80% completion mark, with significant progress made over the past six months. Spanning an area of more than 8 hectares in Kampong Siem district, the facility includes standard waste processing and storage infrastructure. This milestone was confirmed during a site inspection by HE Un Chanda, Governor of Kampong Cham Provincial Board of Governors, on 4 July 2024.

During his visit, Governor Un Chanda emphasized the importance of educating local residents on proper waste disposal and packaging practices to support the efficiency of waste collection services.

The project, covering a total area of 8.15 hectares, features a landfill occupying 1.3 hectares, along with extensive infrastructure including four wastewater treatment tanks, a 2,218-meter access road, a 1,244-meter concrete road within the facility, and a perimeter fence stretching 3,010.26 meters.

Additional constructions include a 3.5×2.5-meter guard post, a two-story office building and accommodation measuring 25×12 meters, a 40-tonne weighing area sized 19×6 meters, an MRF (Materials Recovery Facility) building measuring 35×26 meters, a workshop building of 31×10 meters, a temporary hazardous waste storage building of 15×12 meters, and a car wash facility measuring 31×3.5 meters.

Commenced on 5 January 2024, the project is slated for completion on 28 May 2025, with a total construction period of 17 months. (Read more)

- Video Advertisement -

Related Post

US$10 Billion Project to Connect China-Singapore Railway Unveiled by Chinese Premier

China’s Premier Li Qiang has announced an ambitious $10 billion project to link thousands of kilometres of railways from Malaysia to China, through Thailand and Laos, culminating in a connection to Singapore. This announcement was made during his three-day official visit to Malaysia, marking the 50th anniversary of China-Malaysia diplomatic relations, according to Reuters on […]

CRBC preparing machinery and building equipment for the construction of the Mekong River Bridge soon

China Road Bridge Corporation (CRBC) is preparing drilling equipment, other machinery and construction materials to begin construction soon. HE Phan Rim, Spokesman for the Ministry of Public Works and Transport said on July 6 that CRBC is currently constructing a temporary port for transporting construction materials, which has reached 80 percent and has completed the […]

Rehabilitation and Expansion of NR No. 4 Reaches 55% Completion

As of the end of June 2024, the ambitious project to rehabilitate and expand NR No. 4 from Bek Chan commune in Kandal province to Bit Trang commune in Prey Nob district, Preah Sihanouk province, has achieved 54.80% completion. This significant milestone was confirmed by the Ministry of Public Works and Transport on their official […]

NR No. 48 from Sre Ambel to Koh Kong Construction Progresses Beyond 62%, Set for Dry Season Completion in 2025

The ambitious project to restore and upgrade the 148-kilometre stretch of NR No. 48 from Sre Ambel to Koh Kong has reached a completion milestone of 62.11%, with final completion expected in the dry season of 2025. This update was confirmed by His Excellency Phorn Rim, Spokesman of the Ministry of Public Works and Transport, […]

NR No. 31 Project Connecting Bek Kus to Kampong Trach Nears Completion with Over 95% Progress

By the end of June 2024, the project to restore and upgrade NR No. 31, spanning over 53 kilometers, has achieved 95.38% completion. The Ministry of Public Works and Transport confirmed this progress on their official Facebook page on 3 July 2024. The construction work, which began on 30 December 2022, is on track to […]

Royal Group Phnom Penh SEZ Secures Nearly US$10 Million from Green Bond Listing

Royal Group Phnom Penh SEZ Plc has successfully raised US$9.96 million from its green bond listing on the Cambodia Securities Exchange (CSX) to fund the construction of a wastewater treatment plant and its infrastructure. The official bond listing ceremony took place on 28 June 2024 at the CSX building, presided over by H.E. Dr. Hean […]