Drainage System Upgrade on NR No. 4 in Phnom Penh Reaches 6.7% Completion

The ambitious project to enhance the drainage system along NR No. 4 in Phnom Penh has achieved a significant progress rate of 6.7% as of 25 July 2024, surpassing the planned target of 3.92%.

This milestone was reviewed during a meeting on 7 August 2024, which assessed the progress of the emergency investment project aimed at upgrading sewer infrastructure and drainage systems to mitigate flooding along this critical roadway.

The project’s main objective is to improve rainwater harvesting systems along NR No. 4, which is expected to significantly enhance public health, sanitation, and the overall aesthetics of Phnom Penh. This infrastructure development is crucial for addressing the city’s flooding challenges and ensuring a more resilient urban environment. (Read more)

In addition to the drainage system upgrade, the rehabilitation of NR No. 4 from Bek Chan commune in Kandal province’s Ang Snoul district to Bit Trang commune in Prey Nob district, Preah Sihanouk province, has reached 54.80% completion. This project is on track for completion by the end of June 2026, further solidifying the infrastructure network essential for Phnom Penh’s growth and connectivity. (Read more)

- Video Advertisement -

Related Post

Phnom Penh Infrastructure Project Advancing Rapidly to Combat Flooding

In a significant step towards enhancing urban resilience, a major infrastructure project targeting flood prevention in the western districts of Phnom Penh is now over 66% complete. The initiative, which focuses on installing large-scale box culverts, is actively transforming National Road 4 and surrounding areas. Managed by the PPPP-TCM joint venture, this ambitious project encompasses […]

Bavet City Takes a Major Step Towards Sustainability: Landfill Project Underway

In an exciting development for Bavet City, the construction of a significant landfill project has officially commenced on a sprawling 21-hectare site in Trang Mtes village, located in the heart of Svay Rieng province. The groundbreaking ceremony, held on January 31, 2025, began a transformative initiative to enhance the city’s environmental infrastructure. This project is […]

Japan Strengthens Cambodia’s Infrastructure with New Aid Package over USD 446K

In a significant move to bolster infrastructure development in Cambodia, the Japanese government has announced a generous aid package totaling USD 446,801 for three critical projects focusing on irrigation systems and bridge construction. HE Ueno Atsushi, Japan’s Ambassador to Cambodia, officially signed the grant agreement on 30th January alongside representatives from the three beneficiary institutions […]

National Road 7 Expansion Reaches 32% Completion

As of January 30, 2025, construction on the vital National Road 7 expansion project has reached a notable milestone, achieving 32.01% of its overall progress. The initiative, aimed at enhancing connectivity and promoting economic growth, focuses on upgrading the road to four lanes over a total span of 45.5 kilometers. The work stretches from the […]

Completion Progress on National Road No. 23 Reaches 70%

The ambitious construction project for the 20-kilometer stretch of National Road No. 23, linking Koh Thom and Loek Dek districts in Kandal province, has made significant headway, with approximately 70% of the work completed. According to a report by Cambodia National Television, the project is set to conclude in April 2025. His Excellency Phay Sovicheano, […]

National Road 48 Rehabilitation Nears Completion: 82% Finish Mark Achieved

The long-awaited rehabilitation and upgrade of National Road 48, stretching 148 kilometers from Sre Ambel to Koh Kong, has completed an impressive 82.03%. His Excellency Phon Rim, spokesperson for the Ministry of Public Works and Transport, announced this on January 29, 2025. The construction project, which officially commenced on January 3, 2022, aims to significantly […]