Rehabilitation & Expansion of NR No. 4 Reaches 55% Completion

As of the end of June 2024, the ambitious project to rehabilitate and expand NR No. 4 from Bek Chan commune in Kandal province to Bit Trang commune in Prey Nob district, Preah Sihanouk province, has achieved 54.80% completion. This significant milestone was confirmed by the Ministry of Public Works and Transport on their official Facebook page on 5 July 2024.

HE Pheng Sovicheano, Secretary of State and Director of the NR No. 4 Rehabilitation and Quality Improvement Project, provided detailed insights into the project’s progress. The project encompasses six main sections and two additional packages focused on bridge repairs and new bridge construction.

Project Breakdown:

  1. Section 1: Km 19 + 700 to Km 60 + 000 (Kandal and Kampong Speu provinces) – 28.80 km of four lanes and 11.50 km of two lanes, totalling 40.30 km.
  2. Section 2: Km 60 + 000 to Km 101 + 000 (Kampong Speu province) – 2.68 km of four lanes and 38.32 km of two lanes, totalling 41.00 km.
  3. Section 3: Km 101 + 000 to Km 143 + 000 (Kampong Speu and Koh Kong provinces) – 0.30 km of four lanes and 41.70 km of two lanes, totalling 42.00 km.
  4. Section 4: Km 143 + 000 to Km 186 + 000 (Koh Kong and Preah Sihanouk provinces) – 0.93 km of four lanes and 42.07 km of two lanes, totalling 43.00 km. This section faced delays, leading to the contractor’s contract being cancelled and a deposit of $800,000 being confiscated. The ministry will re-procure this section in August.
  5. Section 5: Km 186 + 000 to Km 215 + 800 (Sihanoukville) – 7.30 km of four lanes and 22.50 km of two lanes, totalling 29.80 km.
  6. Package 6: Km 48 + 695 to Km 202 + 688 – Repairs of 24 old bridges, 8 box drains, 9 round drains, and replacement of 5 old bridge components in Kampong Speu, Koh Kong, and Sihanoukville.
  7. Package 7: Km 38 + 076 to Km 204 + 973 – Construction of 8 new bridges in Kampong Speu, Koh Kong, and Sihanoukville.

It is noteworthy that the Cambodian government has secured a US$110 million concessional loan from the World Bank to facilitate the construction, expansion, and maintenance of NR No. 4. This investment aims to enhance the safety of transportation, boost goods transport efficiency, and ensure climate resilience.

The rehabilitation and expansion project began on 3 January 2022, with an expected completion date by the end of 2026, spanning a total of 17 months of construction work. (Read more)

- Video Advertisement -

Related Post

Darasakor International Airport Opens, Ushering in a New Era for Koh Kong Province

Koh Kong Province celebrated a landmark achievement with the inauguration a $200 million Darasakor International Airport on 26 December 202. This state-of-the-art facility invested by the Chinese company Union Development Group spanning 218 hectares in the Botum Sakor district, is poised to transform the region’s connectivity and catalyse economic and tourism growth. The airport’s grand […]

61-Kilometre Road Connecting NR No. 4 to Bokor Mountain Completed 7 km of Concrete Pouring

The construction of a new 61-kilometre road linking NR No. 4 to Bokor Mountain has reached a significant milestone, with 7 kilometres of concrete pouring completed as of 19 December 2024. This update was shared by Sokha Real Estate on their official Facebook page that same afternoon, marking steady progress in this transformative infrastructure project. […]

NR 41 Completion Marks Milestone in Cambodian Transportation

NR 41, a vital addition to Cambodia’s infrastructure, has officially been completed with a total investment exceeding $67 million. Stretching over 95 kilometres, the road links NR 4 in Kandal to NR 3 in Kampot, dramatically enhancing regional connectivity and bolstering travel and trade. The announcement came following a detailed inspection led by HE Sui […]

Funan Techo Canal Completes 142 demarcation points, Sets Stage for Transformative Infrastructure Shortly

In a landmark achievement for Cambodia’s infrastructure development, the inter-ministerial technical working group has successfully completed the boundary posting process for the first 21 kilometres of the Funan Techo Canal. This initial section, stretching from Prek Takeo to Prek Po, has reached 100% completion, with 142 demarcation points now established along the route. This milestone […]

The Gov’t Temporarily Opens Morodok Techo Flyover’s First Floor Ahead of Khmer New Year 2025

To enhance urban mobility and alleviate traffic congestion in Phnom Penh, the Cambodian government has announced the temporary opening of the first floor of the highly anticipated Morodok Techo Flyover ahead of the Khmer New Year celebrations 2025. This development comes as part of efforts to facilitate smoother travel during the bustling Khmer New Year […]

Cambodia Completes 271 Rural Road Projects in 2024, Enhancing Accessibility Across Remote Areas

The Cambodian government has announced the successful completion of 271 rural road projects in 2024, significantly boosting transportation accessibility for remote communities. The Ministry of Rural Development presented these achievements during a year-end meeting on 9 December 2024, highlighting the construction and improvement of approximately 940.71 kilometres of double-paved roads and outlining strategic plans for […]