Rehabilitation & Expansion of NR No. 4 Reaches 55% Completion

As of the end of June 2024, the ambitious project to rehabilitate and expand NR No. 4 from Bek Chan commune in Kandal province to Bit Trang commune in Prey Nob district, Preah Sihanouk province, has achieved 54.80% completion. This significant milestone was confirmed by the Ministry of Public Works and Transport on their official Facebook page on 5 July 2024.

HE Pheng Sovicheano, Secretary of State and Director of the NR No. 4 Rehabilitation and Quality Improvement Project, provided detailed insights into the project’s progress. The project encompasses six main sections and two additional packages focused on bridge repairs and new bridge construction.

Project Breakdown:

  1. Section 1: Km 19 + 700 to Km 60 + 000 (Kandal and Kampong Speu provinces) – 28.80 km of four lanes and 11.50 km of two lanes, totalling 40.30 km.
  2. Section 2: Km 60 + 000 to Km 101 + 000 (Kampong Speu province) – 2.68 km of four lanes and 38.32 km of two lanes, totalling 41.00 km.
  3. Section 3: Km 101 + 000 to Km 143 + 000 (Kampong Speu and Koh Kong provinces) – 0.30 km of four lanes and 41.70 km of two lanes, totalling 42.00 km.
  4. Section 4: Km 143 + 000 to Km 186 + 000 (Koh Kong and Preah Sihanouk provinces) – 0.93 km of four lanes and 42.07 km of two lanes, totalling 43.00 km. This section faced delays, leading to the contractor’s contract being cancelled and a deposit of $800,000 being confiscated. The ministry will re-procure this section in August.
  5. Section 5: Km 186 + 000 to Km 215 + 800 (Sihanoukville) – 7.30 km of four lanes and 22.50 km of two lanes, totalling 29.80 km.
  6. Package 6: Km 48 + 695 to Km 202 + 688 – Repairs of 24 old bridges, 8 box drains, 9 round drains, and replacement of 5 old bridge components in Kampong Speu, Koh Kong, and Sihanoukville.
  7. Package 7: Km 38 + 076 to Km 204 + 973 – Construction of 8 new bridges in Kampong Speu, Koh Kong, and Sihanoukville.

It is noteworthy that the Cambodian government has secured a US$110 million concessional loan from the World Bank to facilitate the construction, expansion, and maintenance of NR No. 4. This investment aims to enhance the safety of transportation, boost goods transport efficiency, and ensure climate resilience.

The rehabilitation and expansion project began on 3 January 2022, with an expected completion date by the end of 2026, spanning a total of 17 months of construction work. (Read more)

- Video Advertisement -

Related Post

Phnom Penh Infrastructure Project Advancing Rapidly to Combat Flooding

In a significant step towards enhancing urban resilience, a major infrastructure project targeting flood prevention in the western districts of Phnom Penh is now over 66% complete. The initiative, which focuses on installing large-scale box culverts, is actively transforming National Road 4 and surrounding areas. Managed by the PPPP-TCM joint venture, this ambitious project encompasses […]

Bavet City Takes a Major Step Towards Sustainability: Landfill Project Underway

In an exciting development for Bavet City, the construction of a significant landfill project has officially commenced on a sprawling 21-hectare site in Trang Mtes village, located in the heart of Svay Rieng province. The groundbreaking ceremony, held on January 31, 2025, began a transformative initiative to enhance the city’s environmental infrastructure. This project is […]

Japan Strengthens Cambodia’s Infrastructure with New Aid Package over USD 446K

In a significant move to bolster infrastructure development in Cambodia, the Japanese government has announced a generous aid package totaling USD 446,801 for three critical projects focusing on irrigation systems and bridge construction. HE Ueno Atsushi, Japan’s Ambassador to Cambodia, officially signed the grant agreement on 30th January alongside representatives from the three beneficiary institutions […]

National Road 7 Expansion Reaches 32% Completion

As of January 30, 2025, construction on the vital National Road 7 expansion project has reached a notable milestone, achieving 32.01% of its overall progress. The initiative, aimed at enhancing connectivity and promoting economic growth, focuses on upgrading the road to four lanes over a total span of 45.5 kilometers. The work stretches from the […]

Completion Progress on National Road No. 23 Reaches 70%

The ambitious construction project for the 20-kilometer stretch of National Road No. 23, linking Koh Thom and Loek Dek districts in Kandal province, has made significant headway, with approximately 70% of the work completed. According to a report by Cambodia National Television, the project is set to conclude in April 2025. His Excellency Phay Sovicheano, […]

National Road 48 Rehabilitation Nears Completion: 82% Finish Mark Achieved

The long-awaited rehabilitation and upgrade of National Road 48, stretching 148 kilometers from Sre Ambel to Koh Kong, has completed an impressive 82.03%. His Excellency Phon Rim, spokesperson for the Ministry of Public Works and Transport, announced this on January 29, 2025. The construction project, which officially commenced on January 3, 2022, aims to significantly […]