NR No. 31 Project Connecting Bek Kus to Kampong Trach Nears Completion with Over 95% Progress

By the end of June 2024, the project to restore and upgrade NR No. 31, spanning over 53 kilometers, has achieved 95.38% completion. The Ministry of Public Works and Transport confirmed this progress on their official Facebook page on 3 July 2024.

The construction work, which began on 30 December 2022, is on track to be completed nearly a year ahead of the contracted deadline. The project includes paving two layers of AC concrete, which is now 100% complete. Remaining tasks such as installing traffic safety features—traffic signs, road signs, guardrails, and other necessary infrastructure—are scheduled for completion by the end of August 2024.

The project aims to enhance the quality of NR No. 31 with a total length of 53.53 km, stretching from Bek Kus at the intersection of NR No. 3 to Kampong Trach district town, connecting to NR No. 33. The comprehensive upgrade is expected to significantly improve transportation efficiency and safety for residents along the route. (Read more)

- Video Advertisement -

Related Post

CRBC preparing machinery and building equipment for the construction of the Mekong River Bridge soon

China Road Bridge Corporation (CRBC) is preparing drilling equipment, other machinery and construction materials to begin construction soon. HE Phan Rim, Spokesman for the Ministry of Public Works and Transport said on July 6 that CRBC is currently constructing a temporary port for transporting construction materials, which has reached 80 percent and has completed the […]

Rehabilitation and Expansion of NR No. 4 Reaches 55% Completion

As of the end of June 2024, the ambitious project to rehabilitate and expand NR No. 4 from Bek Chan commune in Kandal province to Bit Trang commune in Prey Nob district, Preah Sihanouk province, has achieved 54.80% completion. This significant milestone was confirmed by the Ministry of Public Works and Transport on their official […]

Kampong Cham’s New Landfill Project Achieves Over 80% Completion

The ambitious project to construct a large landfill in Kampong Cham has surpassed the 80% completion mark, with significant progress made over the past six months. Spanning an area of more than 8 hectares in Kampong Siem district, the facility includes standard waste processing and storage infrastructure. This milestone was confirmed during a site inspection […]

NR No. 48 from Sre Ambel to Koh Kong Construction Progresses Beyond 62%, Set for Dry Season Completion in 2025

The ambitious project to restore and upgrade the 148-kilometre stretch of NR No. 48 from Sre Ambel to Koh Kong has reached a completion milestone of 62.11%, with final completion expected in the dry season of 2025. This update was confirmed by His Excellency Phorn Rim, Spokesman of the Ministry of Public Works and Transport, […]

Royal Group Phnom Penh SEZ Secures Nearly US$10 Million from Green Bond Listing

Royal Group Phnom Penh SEZ Plc has successfully raised US$9.96 million from its green bond listing on the Cambodia Securities Exchange (CSX) to fund the construction of a wastewater treatment plant and its infrastructure. The official bond listing ceremony took place on 28 June 2024 at the CSX building, presided over by H.E. Dr. Hean […]

Darasakor International Airport Set for Temporary Opening in August

The Darasakor International Airport in Khemarak Phoumin City, Koh Kong Province, is scheduled to open temporarily at the end of August, initially operating domestic flights. This information was confirmed by Mr Sin Chanserivutha, Secretary of State and spokesperson for civil aviation, during a recent announcement to Fresh News in late June 2024. Mr. Chanserivutha stated […]