Three Sections of NR5 Expansion 79%, 30%, and 19% Complete, Respectively

As of August, three sections of the National Road 5 (NR5) expansion project have reached 42% completion and is scheduled to be complete by 2022.

According to the Ministry of Public Works and Transport’s report on 01 September, the progress of each section of road are as follows:

1. The northern part from Battambang to Serey Sophoan (84.74 km) is 79.05% complete and scheduled for completion in July 2021
2. The central section from Thla Ma Om to Battambang (146.04 km) is 30.48% completed and scheduled for completion in April 2022
3. The southern part from Prek Kdam in Kandal province to Thla Ma Om in Pursat province (135.24 km) is 19.44% completed and scheduled for completion in August 2022

The renovation of NR5 has a total length of 366km connecting the capital to the northwest part of the country passing through Kompong Chhnang, Pursat, Battambang, and Banteay Meanchey provinces.

The road will be upgraded to Asphalt Concrete (AC) and expanded to four lanes with a width of 23m. The project is being undertaken with a loan of US$500 million from the Japanese government. (Read more)

- Video Advertisement -

Related Post

Battambang Launches Strategic Urban Infrastructure Project on Street 154

Extensive road expansion and drainage system upgrades in Wat Kor Sangkat signal the start of a city-wide modernization initiative The Battambang Provincial Administration has officially broken ground on a comprehensive infrastructure project in Battambang City, focusing on road restoration and the construction of advanced drainage systems. The ceremony, held on March 9, 2026, was led […]

Cambodia and South Korea Explore Small-Scale Hydropower Potential at Dauntri and Reaksa Reservoirs

Joint feasibility study focuses on integrating renewable energy and solar power to secure sustainable water and electricity supplies for local communities The Ministry of Water Resources and Meteorology has partnered with the Korea Water Resources Corporation, known as K-water, to conduct a comprehensive feasibility study on the installation of small-scale hydropower facilities at the Dauntri […]

Borey Peng Huoth Announces Exclusive Pre-Sale Event for New Phum Nimith Project in Chbar Ampov

Early access to prime locations within the prestigious Grand Star Platinum development starting this March Following the successful groundbreaking ceremony held on January 30, 2026, Borey Peng Huoth is pleased to announce the official pre-sale launch of its newest residential development, Phum Nimith. This highly anticipated event will take place over three days from March […]

Accelerating Connectivity: Mekong River Bridge Connecting Dei Edth-Thmor Kor Surpasses 35% Completion

Minister Peng Ponea inspects the strategic infrastructure project in Kandal province to ensure rigorous technical standards and timely delivery for the public The construction of the major bridge across the Mekong River Dei Edth-Thmor Kor connecting Dei Edth commune in Kien Svay district to Thmor Kor commune in Lvea Em district has reached a significant […]

Cambodia and Laos to Fast-Track Cross-Border Connectivity with New Ratanakiri-Attapeu Road Link

Joint inspection team to finalize construction zones this February to unlock new trade and economic opportunities Cambodia and Laos have reached a pivotal agreement to conduct a joint technical inspection aimed at defining the specific zones for a new road project connecting Ratanakiri province in Cambodia to Attapeu province in Laos. This initiative is a […]

Kratie City Drainage and Pumping Station Project Surpasses 68% Completion

Provincial authorities and ADB-funded initiative accelerate infrastructure development to eliminate seasonal flooding and boost local economic appeal Kratie City is undergoing a significant infrastructural transformation as the construction of its comprehensive drainage network and rainwater pumping station reaches 68 percent completion. This development is a key sub-project of the Fourth Greater Mekong Subregion Corridor Towns […]