Three Sections of NR5 Expansion 79%, 30%, and 19% Complete, Respectively

As of August, three sections of the National Road 5 (NR5) expansion project have reached 42% completion and is scheduled to be complete by 2022.

According to the Ministry of Public Works and Transport’s report on 01 September, the progress of each section of road are as follows:

1. The northern part from Battambang to Serey Sophoan (84.74 km) is 79.05% complete and scheduled for completion in July 2021
2. The central section from Thla Ma Om to Battambang (146.04 km) is 30.48% completed and scheduled for completion in April 2022
3. The southern part from Prek Kdam in Kandal province to Thla Ma Om in Pursat province (135.24 km) is 19.44% completed and scheduled for completion in August 2022

The renovation of NR5 has a total length of 366km connecting the capital to the northwest part of the country passing through Kompong Chhnang, Pursat, Battambang, and Banteay Meanchey provinces.

The road will be upgraded to Asphalt Concrete (AC) and expanded to four lanes with a width of 23m. The project is being undertaken with a loan of US$500 million from the Japanese government. (Read more)

- Video Advertisement -

Related Post

A $117 Million Economic Lifeline: Prime Minister Hun Manet Inaugurates Newly Expanded National Road 7

The newly upgraded 4-lane highway connecting Skun and Kampong Cham town is projected to deliver a 15.27% economic return, slashing travel times and boosting agricultural trade… In a major boost to Cambodia’s internal logistics network, a vital 45.489-kilometer section of National Road 7 connecting the Skun roundabout to the Kizuna Bridge roundabout in Kampong Cham […]

Maritime Geopolitical Rivalry Intensifies as Vietnam Accelerates $4 Billion Deep Sea Port Project in the Far South

The massive infrastructure development on Hon Khoai Island serves as both an economic gateway for the Mekong Delta and a strategic maritime shield amid shifting regional dynamics Ho Chi Minh City: The geopolitical and trade landscape of Southeast Asia is entering a highly competitive phase as nations across the region race to build strategic advantages. […]

Field Assessments Underway for Kandal Province New Strategic Bridge

A joint delegation evaluates four potential sites for the Koh Khsach Tonlea crossing to enhance rural connectivity and market access In a significant step forward for Cambodia’s infrastructure development, a multi-institutional technical team has launched a comprehensive field survey to determine the optimal location for the upcoming Koh Khsach Tonlea Bridge project in Kandal Province. […]

Cambodia Completes Major Expansion of National Road 7 Connecting Skun and Kampong Cham

The $117 million infrastructure upgrade backed by China is set for an official inauguration by Prime Minister Hun Manet in July… The extensive upgrade of National Road 7, stretching over 45 kilometers to connect the hub of Skun with Kampong Cham town, has officially reached 100% completion. To mark this infrastructural milestone, a formal handover […]

Cambodia to Upgrade National Road 4 Section in Chbar Mon to Drive Regional Economic Growth

The Kampong Speu Provincial Administration recently announced a comprehensive infrastructure initiative aimed at upgrading the aesthetics and functionality of a key section of National Road 4 within Chbar Mon City. The project is strategically designed to transform the province into a vital economic and commercial center for the region. This development plan was detailed in […]

Bassac Riverbank Stabilization Project in Kandal Reaches 60% Completion

The ongoing infrastructure initiative to reinforce the Bassac riverbank in Sampov Poun City, Kandal Province, has achieved a significant milestone, with construction teams completing approximately 60% of the designated works. Local authorities and engineering crews remain heavily committed to accelerating the remaining phases to ensure the project concludes entirely on schedule. During a recent field […]