Five Water Stations in PP Worth Over US$247m, Can Produce Over 1 million m3 /day

Phnom Penh Water Supply Authority will have a total production capacity of 1,100,000 m3/day and a total length of water network (water mains and water distribution network) of 5,189 km through five water supply projects worth more than US$247m after construction.

According to a press release issued by the Ministry of Industry, Science, Technology, and Innovation on 4 November, the five projects include:

1- Bak Kheng Water Supply Project, Phase 1, capacity 195,000 m3/ day, and total water network length of 750 km, which is scheduled to be completed in the second quarter of 2023.

2_ Bak Kheng Water Supply Project, Phase 2, capacity 195,000 m3/ day and total water network length of 188 km, which is scheduled to be completed in the first quarter of 2024. It should be noted that the two-phase Bak Kheng water supply project has a total investment of US$190m, which is co-financed by the French Development Agency, the European Investment Bank, and the Phnom Penh Water Supply Authority. (Read more)

3_ Projects to expand the water supply system of Takhmao city with a capacity of 30,000m3/ day, which is scheduled to be completed in December 2024. The project uses a total budget of about US$32m, a grant from the Japanese government. (Read more)

4_ Projects to expand the water supply system of the Prek Phum village factory from 150,000 m3 / day to 195,000 m3 / day, which is scheduled to start construction in 2026. The Japanese government has decided to provide more than US$23 million in grants for a project to expand the Prek Phum water supply system to Cambodia.  (Read more)

5_ Projects to build a Boeung Thom water supply system with a capacity of 5,000 m3/ day and a total water supply system with a total length of 12 km. Construction of the project began in August 2022 and is scheduled to be completed in February 2023, with a grant from the Government of Japan of US$1,494,624 and a contribution of the Phnom Penh Autonomous Authority of US$931,900.  (Read more)

The five-year project will be able to supply clean, safe, sustainable, and affordable water to more than 610,800 households in Phnom Penh and Takhmao.

Meanwhile, the Phnom Penh Water Supply Authority is continuing to cooperate with development partners to study the Bak Kheng Water Supply Project, Phase 3, Niroth Water Supply Project, Phase 3, Water Supply Project, Techo Takhmao International Airport and Water Supply Project. The middle sand, too.

Currently, the demand for clean water in Phnom Penh as a whole is about 746,000m3/ day, while the capacity of the four water treatment plants is only 630,000m3/ day.

- Video Advertisement -

Related Post

Building at a Whole New Scale: This Engineer is Taking Construction into the Fourth Dimension With ‘Godzilla Mode’

By Sean O’Neill James Bowles has always loved building things. As a child, he spent hours with Lego, piecing together miniature cities brick by brick. As a teenager, he became fascinated by skyscrapers—their design, engineering, and sheer scale. It wasn’t just their height that intrigued him, but the challenge of making something so ambitious stand. […]

Cambodian Parliament Approves Landmark Law for 24 Electricity Investment Projects

In a significant move to bolster the nation’s energy infrastructure, the Cambodian Parliament has officially approved a draft law facilitating payment guarantees to 24 electricity investment companies. This landmark decision was made during the fourth session of the seventh National Assembly held on May 22, 2025. The new law comes in response to the surging […]

The Government Announces New Opening Date for Techo International Airport

In a significant new update for travelers and the aviation industry, the State Secretariat of Civil Aviation has announced a revised opening date for the much-anticipated Techo International Airport in Takhmao. Originally set to open on July 10, 2025, the grand opening is now scheduled for September 9, 2025, as indicated in a notice issued […]

Unlock Your Dream Condo at the Star Polaris 23: Exclusive Weekend Event!

  Are you ready to elevate your living experience? Discover the magnificent Star Polaris 23 Condo, presented by Borey Peng Huoth Company, where exceptional opportunities await! Join us for an Exclusive Weekend Program on May 24-25, 2025, right in the heart of our stunning condo lobby. This is your chance to turn your homeownership dreams […]

National Road 10 Completed: Enhancing Regional Connectivity

The construction of National Road 10, stretching over 197.36 kilometers, has been officially completed, marking a significant milestone in the region’s infrastructure development. The road is now fully operational and has undergone a thorough inspection by a team of skilled technicians to ensure its longevity and adherence to technical standards. A detailed assessment was conducted […]

Successful Completion of Land Survey in Oddar Meanchey Province

The Ministry of Land Management has proudly announced the successful completion of a systematic land survey in Oddar Meanchey Province, marking a significant milestone in the region’s land management efforts. The closing ceremony was chaired by His Excellency Say Samal, Deputy Prime Minister and Minister of the Ministry of Land Management, Urban Planning, and Construction. […]