Progress Update: Rehabilitation of NR No. 48 from Sre Ambel to Koh Kong Reaches 31%

The highly anticipated rehabilitation project of NR No. 48, stretching 148 kilometers from the Sre Ambel Road intersection on NR No. 4 to Khemarak Phoumin City in Koh Kong Province, has achieved a significant milestone, with completion reaching 31% as of 22nd June 2023.

During a site inspection led by HE Sun Chanthol, Senior Minister and Minister of Public Works and Transport, alongside the construction companies ILSUNG & HANIL Joint Venture and KCI & KECC Joint Venture, it was confirmed that progress, although slightly behind schedule, has been steady. Factors contributing to the slight delay include variations in the contract scope, geographical considerations, and early onset of the rainy season.

To expedite the project, the construction company has implemented three key priority plans. Firstly, the workforce has been increased from 3 to 8 teams, ensuring simultaneous progress in multiple sections. Secondly, the focus has shifted to constructing bridge components during periods of inclement weather when road foundation works are disrupted. Lastly, stockpiling essential materials for the upcoming dry season, particularly for the rubber layer paving, which accounts for 30% of the overall project.

Spanning a total distance of 148 km, the NR No. 48 construction project, initiated on 3rd January 2022 with an allocated budget of approximately $78 million, aims to enhance the road’s quality and capacity, facilitating smoother and safer transportation throughout the province. This significant infrastructure endeavor is poised to bring about improved connectivity, fostering economic growth and prosperity for both local communities and the province as a whole. (Read more)

 

- Video Advertisement -

Related Post

Brunei’s Khazanah Nasional Targets Multi-Sector Infrastructure Investment in Cambodia

Khazanah Nasional Berhad, a leading investment firm from Brunei Darussalam, has announced plans to explore infrastructure investment opportunities in Cambodia, focusing on health, water resources, transport infrastructure (including railways and airports), and banking. This initiative was discussed during a meeting between PM Hun Manet and Khazanah’s CEO, Mr. Dato Khairul Hamed, on 19 November 2024. […]

China Construction America Ordered to Pay US$1.6 Billion and Conflict of Political Interests Behind

A New York court has ordered China Construction America Inc. (CCA), a subsidiary of Chinese state-owned China State Construction Engineering, to pay US$1.6 billion to BML Properties, the original owner of the Baha Mar casino resort in the Bahamas, after the contractor was found to have committed “many acts of fraud” during its takeover of […]

Phnom Penh-SHV Expressway Offers Exclusive Discounts for 3-Day Water Festival Celebration

To celebrate the Royal Water Festival from 14 to 16 November 2024, the Ministry of Public Works and Transport (MPWT) has announced a special three-day discount on the Phnom Penh-Sihanoukville Expressway. Notification No. 052 S.K.R., dated 12 November 2024, confirmed that the Phnom Penh-Sihanoukville Expressway Company will offer a 20% discount on toll fees for […]

Groundbreaking of 500-Hectare Green Textile Industrial Park in Kampong Speu to Create Up to 60K Jobs

A groundbreaking ceremony on 8 November 2024 marked the start of a 500-hectare green textile industrial park in Chheu Neang Village, Taing Sya Commune, Phnom Sruoch District, Kampong Speu. Attended by HE Heng Sour, Minister of Labor and Vocational Training, HE Dr. Cheam Chansophoan, Governor of Kampong Speu Province, and Mr. John Yu, Chairman of […]

PM Inaugurates USD10 Million Techo Santepheap Ankoul Beach Road to Boost Tourism in Kep

The USD10 million Techo Santepheap Ankoul Road project, aimed at enhancing tourism infrastructure, was officially inaugurated in Ang Kol, Kep Village, and Angkor Village within the Ang Koul Commune of Damnak Chang Eur District, Kep Province. Led by PM Samdech Hun Manet, the ceremony on 11 November 2024 marked the completion of this pivotal project […]

NR No. 33 (Kampot-Chrak Lok) Reaches 99% Completion, Strengthening Provincial Transport Network

NR No. 33, connecting Kampot to Chrak Lok, is on the cusp of completion, with an impressive 98.89% of the project finalised as of early November 2024. This achievement was highlighted in an official inspection conducted on 6 November 2024 by HE Pal Chandara, Secretary of State of the Ministry of Public Works and Transport, […]