NR No. 31 Project Connecting Bek Kus to Kampong Trach Nears Completion with Over 95% Progress

By the end of June 2024, the project to restore and upgrade NR No. 31, spanning over 53 kilometres, has achieved 95.38% completion. The Ministry of Public Works and Transport confirmed this progress on their official Facebook page on 3 July 2024.

The construction work, which began on 30 December 2022, is on track to be completed nearly a year ahead of the contracted deadline. The project includes paving two layers of AC concrete, which is now 100% complete. Remaining tasks such as installing traffic safety features—traffic signs, road signs, guardrails, and other necessary infrastructure—are scheduled for completion by the end of August 2024.

The project aims to enhance the quality of NR No. 31 with a total length of 53.53km, stretching from Bek Kus at the intersection of NR No. 3 to Kampong Trach district town, connecting to NR No. 33. The comprehensive upgrade is expected to significantly improve transportation efficiency and safety for residents along the route. (Read more)

- Video Advertisement -

Related Post

Brunei’s Khazanah Nasional Targets Multi-Sector Infrastructure Investment in Cambodia

Khazanah Nasional Berhad, a leading investment firm from Brunei Darussalam, has announced plans to explore infrastructure investment opportunities in Cambodia, focusing on health, water resources, transport infrastructure (including railways and airports), and banking. This initiative was discussed during a meeting between PM Hun Manet and Khazanah’s CEO, Mr. Dato Khairul Hamed, on 19 November 2024. […]

China Construction America Ordered to Pay US$1.6 Billion and Conflict of Political Interests Behind

A New York court has ordered China Construction America Inc. (CCA), a subsidiary of Chinese state-owned China State Construction Engineering, to pay US$1.6 billion to BML Properties, the original owner of the Baha Mar casino resort in the Bahamas, after the contractor was found to have committed “many acts of fraud” during its takeover of […]

Phnom Penh-SHV Expressway Offers Exclusive Discounts for 3-Day Water Festival Celebration

To celebrate the Royal Water Festival from 14 to 16 November 2024, the Ministry of Public Works and Transport (MPWT) has announced a special three-day discount on the Phnom Penh-Sihanoukville Expressway. Notification No. 052 S.K.R., dated 12 November 2024, confirmed that the Phnom Penh-Sihanoukville Expressway Company will offer a 20% discount on toll fees for […]

Groundbreaking of 500-Hectare Green Textile Industrial Park in Kampong Speu to Create Up to 60K Jobs

A groundbreaking ceremony on 8 November 2024 marked the start of a 500-hectare green textile industrial park in Chheu Neang Village, Taing Sya Commune, Phnom Sruoch District, Kampong Speu. Attended by HE Heng Sour, Minister of Labor and Vocational Training, HE Dr. Cheam Chansophoan, Governor of Kampong Speu Province, and Mr. John Yu, Chairman of […]

PM Inaugurates USD10 Million Techo Santepheap Ankoul Beach Road to Boost Tourism in Kep

The USD10 million Techo Santepheap Ankoul Road project, aimed at enhancing tourism infrastructure, was officially inaugurated in Ang Kol, Kep Village, and Angkor Village within the Ang Koul Commune of Damnak Chang Eur District, Kep Province. Led by PM Samdech Hun Manet, the ceremony on 11 November 2024 marked the completion of this pivotal project […]

NR No. 33 (Kampot-Chrak Lok) Reaches 99% Completion, Strengthening Provincial Transport Network

NR No. 33, connecting Kampot to Chrak Lok, is on the cusp of completion, with an impressive 98.89% of the project finalised as of early November 2024. This achievement was highlighted in an official inspection conducted on 6 November 2024 by HE Pal Chandara, Secretary of State of the Ministry of Public Works and Transport, […]