NR 31 Rehabilitation Project Nears Completion at Over 96%, Ahead of Schedule

The rehabilitation and upgrade of NR No. 31, covering a distance of over 53 kilometres, has achieved an impressive 96.10% completion as of early August 2024. With this pace, the project is expected to be completed a full year ahead of schedule, while maintaining the highest technical standards, according to the Ministry of Public Works and Transport on 9 August 2024.

The ministry confirmed that the application of two layers of AC rubber has been fully completed. Additionally, the installation of traffic safety equipment, including traffic signs, road signs, and safety bars, is slated for completion by the end of August 2024.

During a recent site inspection, HE Khan Maner, Secretary of State and Project Director, urged the construction company to strictly adhere to the technical standards and construction contracts to ensure the long-term durability and strength of the road.

The project is focused on restoring and upgrading NR No. 31, which spans 53.53 kilometres from Bek Kus, at the intersection of NR 3, to Kampong Trach district town, connecting with NR No. 33. The construction site was officially opened on 30 December 2022. (Read more)

- Video Advertisement -

Related Post

Large-Scale Drainage Project on Phnom Penh’s NR 4 Surpasses Schedule by 11%

The construction of a major drainage system along NR 4 in Phnom Penh has achieved an 11% faster progress rate, reaching a completed length of 624 meters. The project, which is part of a broader effort to modernize the city’s sewer infrastructure, aims to improve flood prevention and sanitation across key districts. This update was […]

SHV’s New 253-Meter Container Port Inaugurated with Japanese Aid

A new 253-meter-long container terminal at Sihanoukville Autonomous Port was officially inaugurated on 12 September 2024, marking a significant expansion for Cambodia’s primary port. Attended by PM Samdech Hun Manet, the ceremony highlighted the terminal’s modernized capabilities. The port now include advanced container lifts and loading equipment, boosting the port’s capacity from 550,000 TEU to […]

Three Key Rural Roads Near Completion in Kampong Cham & Tbong Khmum

Three rural roads spanning over 40 kilometres in Kampong Cham and Tbong Khmum provinces are nearing full completion, with construction progress close to 100% as of 4 September 2024. The Ministry of Rural Development has overseen this crucial infrastructure project, which aims to enhance regional connectivity and promote agricultural trade. The first road, measuring 17.55km, […]

Techo International Airport to Undergo Five Days Final Flight Inspections Ahead of 2025 Launch

Techo International Airport, Cambodia’s largest and only 4F-class airport, will conduct a five-day flight inspection from 8 to 12 September 2024, as it gears up for its scheduled opening in the first half of next year. HE Sin Chanserivutha, Under-Secretary of State and Spokesman for the State Secretariat of Civil Aviation, confirmed that this critical […]

Siem Reap-Angkor International Airport Received 900k Passengers, Expected to Hit 1.5 Million by Year-End

After nearly a year of operation, the Siem Reap-Angkor International Airport has welcomed approximately 900,000 passengers, with projections to reach 1.3 million by October and 1.5 million by the end of 2024. This milestone was announced during a working session between the Chairman of Angkor International Airport Investment (Cambodia) Co., Ltd. (AIAI), Lu Wei, and […]

Stung Toch Drainage Rehabilitation Project in Kampong Speu Reaches 89% Completion

The rehabilitation of the Stung Toch drainage system in Kampong Speu province has achieved approximately 89% completion, as reported by the Ministry of Water Resources and Meteorology (MoWRM)  on 1 September 2024. This significant project includes rehabilitating a 51-kilometre-long small river, with a mouth width of 100 metres and a 40-metre-high dam. The river stretches […]