NR No. 10 Rehabilitation Nears Completion with 93% of Work Done and the Tallest Bridge Reaches 79% on Track for Operation in June 2025

By the end of October 2024, construction on Cambodia’s NR No. 10—a crucial route connecting the provinces of Koh Kong, Pursat, and Battambang—has reached an impressive 92.94% completion. Along this route, the tallest bridge, spanning 530 meters, has progressed to 79% completion and is set to be fully operational by June 2025, as reported by HE Bong Bun Hourn, Secretary of State of the Ministry of Public Works and Transport, following an official site inspection on 1 November 2024.

The road is partially open to traffic, but travellers are advised to exercise caution as certain sections remain unpaved and prone to slipping during heavy rains. Currently, the road surface varies across the route’s 198.518-kilometre stretch, with key sections comprising both rubberized surfaces and red gravel. Specifically, the road’s condition is as follows:

  • PK0 (Samlot) to PK60 (Two Crocodiles): rubber surface
  • PK60 to PK85: red gravel
  • PK85 to PK112 (Osom): rubber surface
  • PK112 to PK130: red gravel (some areas prone to slipping in rain)
  • PK130 to PK160: rubber surface
  • PK160 to PK175: red gravel
  • PK175 to PK198 (Koh Kong): rubber surface

NR No. 10 has been classified as a Grade III double-paved road (DBST) and measures 9 meters wide. The rehabilitation project, which represents a vital improvement for connectivity in the region, has been financed by the Chinese government at a total cost exceeding USD 188 million. (Read more)

- Video Advertisement -

Related Post

Brunei’s Khazanah Nasional Targets Multi-Sector Infrastructure Investment in Cambodia

Khazanah Nasional Berhad, a leading investment firm from Brunei Darussalam, has announced plans to explore infrastructure investment opportunities in Cambodia, focusing on health, water resources, transport infrastructure (including railways and airports), and banking. This initiative was discussed during a meeting between PM Hun Manet and Khazanah’s CEO, Mr. Dato Khairul Hamed, on 19 November 2024. […]

China Construction America Ordered to Pay US$1.6 Billion and Conflict of Political Interests Behind

A New York court has ordered China Construction America Inc. (CCA), a subsidiary of Chinese state-owned China State Construction Engineering, to pay US$1.6 billion to BML Properties, the original owner of the Baha Mar casino resort in the Bahamas, after the contractor was found to have committed “many acts of fraud” during its takeover of […]

Phnom Penh-SHV Expressway Offers Exclusive Discounts for 3-Day Water Festival Celebration

To celebrate the Royal Water Festival from 14 to 16 November 2024, the Ministry of Public Works and Transport (MPWT) has announced a special three-day discount on the Phnom Penh-Sihanoukville Expressway. Notification No. 052 S.K.R., dated 12 November 2024, confirmed that the Phnom Penh-Sihanoukville Expressway Company will offer a 20% discount on toll fees for […]

Groundbreaking of 500-Hectare Green Textile Industrial Park in Kampong Speu to Create Up to 60K Jobs

A groundbreaking ceremony on 8 November 2024 marked the start of a 500-hectare green textile industrial park in Chheu Neang Village, Taing Sya Commune, Phnom Sruoch District, Kampong Speu. Attended by HE Heng Sour, Minister of Labor and Vocational Training, HE Dr. Cheam Chansophoan, Governor of Kampong Speu Province, and Mr. John Yu, Chairman of […]

PM Inaugurates USD10 Million Techo Santepheap Ankoul Beach Road to Boost Tourism in Kep

The USD10 million Techo Santepheap Ankoul Road project, aimed at enhancing tourism infrastructure, was officially inaugurated in Ang Kol, Kep Village, and Angkor Village within the Ang Koul Commune of Damnak Chang Eur District, Kep Province. Led by PM Samdech Hun Manet, the ceremony on 11 November 2024 marked the completion of this pivotal project […]

NR No. 33 (Kampot-Chrak Lok) Reaches 99% Completion, Strengthening Provincial Transport Network

NR No. 33, connecting Kampot to Chrak Lok, is on the cusp of completion, with an impressive 98.89% of the project finalised as of early November 2024. This achievement was highlighted in an official inspection conducted on 6 November 2024 by HE Pal Chandara, Secretary of State of the Ministry of Public Works and Transport, […]