NR 33 Rehabilitation Reaches 62% Completion by April 2024

The extensive effort to restore and enhance the quality of NR 33 has reached a significant milestone, with completion standing at 62% as of April 2024. This update comes following a thorough site inspection conducted by HE Bun Sophat, Deputy Director of the Project and Representative of HE Pal Chandara, Secretary of State of the Ministry of Public Works and Transport, on 2 April 2024.

The primary objective of the site inspection was to ensure strict adherence to technical standards, quality benchmarks, and durability parameters throughout the rehabilitation project, which has now achieved a commendable 62% progress.

During the inspection, the Undersecretary of State underscored the importance of prioritising key aspects such as proper watering and excavation site clearance, while emphasising the paramount importance of safety measures. Directives were issued to the construction company to enhance safety protocols, including the installation of clear signage to regulate traffic flow and the provision of adequate safety attire for on-site workers, thus ensuring smooth travel and transportation for the public.

Spanning approximately 52.57 kilometres, the NR 33 rehabilitation project links Kampot province to Lok (Cambodia-Vietnam border), traversing Teuk Chhou and Kampong Trach districts in Kampot province, as well as Kep city and Damnak Chang Eur district in Kep province. Financed through a concessional loan from the government of the People’s Republic of China, supplemented by the budget of the Royal Government of Cambodia to address associated impacts and taxes, this vital infrastructure initiative is poised to significantly enhance connectivity and transportation efficiency across the region. (Read more)

- Video Advertisement -

Related Post

Phnom Penh Infrastructure Project Advancing Rapidly to Combat Flooding

In a significant step towards enhancing urban resilience, a major infrastructure project targeting flood prevention in the western districts of Phnom Penh is now over 66% complete. The initiative, which focuses on installing large-scale box culverts, is actively transforming National Road 4 and surrounding areas. Managed by the PPPP-TCM joint venture, this ambitious project encompasses […]

Bavet City Takes a Major Step Towards Sustainability: Landfill Project Underway

In an exciting development for Bavet City, the construction of a significant landfill project has officially commenced on a sprawling 21-hectare site in Trang Mtes village, located in the heart of Svay Rieng province. The groundbreaking ceremony, held on January 31, 2025, began a transformative initiative to enhance the city’s environmental infrastructure. This project is […]

Japan Strengthens Cambodia’s Infrastructure with New Aid Package over USD 446K

In a significant move to bolster infrastructure development in Cambodia, the Japanese government has announced a generous aid package totaling USD 446,801 for three critical projects focusing on irrigation systems and bridge construction. HE Ueno Atsushi, Japan’s Ambassador to Cambodia, officially signed the grant agreement on 30th January alongside representatives from the three beneficiary institutions […]

National Road 7 Expansion Reaches 32% Completion

As of January 30, 2025, construction on the vital National Road 7 expansion project has reached a notable milestone, achieving 32.01% of its overall progress. The initiative, aimed at enhancing connectivity and promoting economic growth, focuses on upgrading the road to four lanes over a total span of 45.5 kilometers. The work stretches from the […]

Completion Progress on National Road No. 23 Reaches 70%

The ambitious construction project for the 20-kilometer stretch of National Road No. 23, linking Koh Thom and Loek Dek districts in Kandal province, has made significant headway, with approximately 70% of the work completed. According to a report by Cambodia National Television, the project is set to conclude in April 2025. His Excellency Phay Sovicheano, […]

National Road 48 Rehabilitation Nears Completion: 82% Finish Mark Achieved

The long-awaited rehabilitation and upgrade of National Road 48, stretching 148 kilometers from Sre Ambel to Koh Kong, has completed an impressive 82.03%. His Excellency Phon Rim, spokesperson for the Ministry of Public Works and Transport, announced this on January 29, 2025. The construction project, which officially commenced on January 3, 2022, aims to significantly […]