Preventing Landslides: Phnom Penh-Sihanoukville Expressway Undergoes Repairs at Four Key Locations

The Expressway Management Company has announced urgent repairs on the Phnom Penh-Sihanoukville Expressway at four critical locations to prevent landslides due to flooding during the rainy season. This initiative aims to ensure road safety and prevent potential accidents. The announcement was made on the official Facebook page of the Phnom Penh-Sihanoukville Expressway on 10 June 2024.

The repair schedule is as follows:

  1. From 16:00 on 10 June to 12:00 on 11 June: Repairs will be carried out on the normal traffic lanes and emergency stop lanes from km 34 + 000 to km 34 + 800 on the Sihanoukville to Phnom Penh route. During this period, all customers can use the overtaking lane.
  2. From 12:00 to 18:00 on 11 June: The repairs will shift to the overtaking lane from km 34 + 000 to km 34 + 800 on the Sihanoukville to Phnom Penh route. Customers can travel on the normal traffic lanes and emergency stop lanes.
  3. From 18:00 on 11 June to 12:00 on 12 June: Repairs will be performed on the normal and emergency stop lanes from km 33 + 500 to km 34 + 300 on the Phnom Penh to Sihanoukville route. The overtaking lane will be available for travel.
  4. From 12:00 to 18:00 on 12 June: Repairs will continue on the overtaking lane from km 33 + 500 to km 34 + 300 on the Phnom Penh to Sihanoukville route. Customers can use the normal traffic lanes and emergency stop lanes during this time.

The company urges all travellers to reduce their driving speed and exercise increased caution while passing through these repair zones.

- Video Advertisement -

Related Post

Phnom Penh Infrastructure Project Advancing Rapidly to Combat Flooding

In a significant step towards enhancing urban resilience, a major infrastructure project targeting flood prevention in the western districts of Phnom Penh is now over 66% complete. The initiative, which focuses on installing large-scale box culverts, is actively transforming National Road 4 and surrounding areas. Managed by the PPPP-TCM joint venture, this ambitious project encompasses […]

Bavet City Takes a Major Step Towards Sustainability: Landfill Project Underway

In an exciting development for Bavet City, the construction of a significant landfill project has officially commenced on a sprawling 21-hectare site in Trang Mtes village, located in the heart of Svay Rieng province. The groundbreaking ceremony, held on January 31, 2025, began a transformative initiative to enhance the city’s environmental infrastructure. This project is […]

Japan Strengthens Cambodia’s Infrastructure with New Aid Package over USD 446K

In a significant move to bolster infrastructure development in Cambodia, the Japanese government has announced a generous aid package totaling USD 446,801 for three critical projects focusing on irrigation systems and bridge construction. HE Ueno Atsushi, Japan’s Ambassador to Cambodia, officially signed the grant agreement on 30th January alongside representatives from the three beneficiary institutions […]

National Road 7 Expansion Reaches 32% Completion

As of January 30, 2025, construction on the vital National Road 7 expansion project has reached a notable milestone, achieving 32.01% of its overall progress. The initiative, aimed at enhancing connectivity and promoting economic growth, focuses on upgrading the road to four lanes over a total span of 45.5 kilometers. The work stretches from the […]

Completion Progress on National Road No. 23 Reaches 70%

The ambitious construction project for the 20-kilometer stretch of National Road No. 23, linking Koh Thom and Loek Dek districts in Kandal province, has made significant headway, with approximately 70% of the work completed. According to a report by Cambodia National Television, the project is set to conclude in April 2025. His Excellency Phay Sovicheano, […]

National Road 48 Rehabilitation Nears Completion: 82% Finish Mark Achieved

The long-awaited rehabilitation and upgrade of National Road 48, stretching 148 kilometers from Sre Ambel to Koh Kong, has completed an impressive 82.03%. His Excellency Phon Rim, spokesperson for the Ministry of Public Works and Transport, announced this on January 29, 2025. The construction project, which officially commenced on January 3, 2022, aims to significantly […]