Construction of 400 MW power plants in Kandal province faces suspension

Two power plants with a total power capacity of 400 MW fueled by heavy fuel oil which was under construction in Lvea Em district, Kandal province may fail to come online as scheduled because contracted construction firms from China have been affected by the COVID-19 pandemic.

According to the plan, when construction started in October 2019 the power plants, were scheduled to generate power and be connected to the grid in May or June, within the first semester this year.

Unfortunately, because of construction firms contracted from China having difficulties in travelling and being required to be in quarantine for COVID-19 prevention, the process of construction work faces suspension.

Victor Jona, director-general of General Department of Energy and spokesperson of the Ministry of Mines and Energy, reported that “The suspension of commencing the power plants will be up to 6 months if the situation of COVID-19 gets better.”

Given the threat of the pandemic on the energy development sector, some people raised concerns over economic downturns especially in the power sector, as there might be some withdrawal of energy investment and delay in project implementation.

However, addressing these concerns, Mr Jona made it clear that “although the power plant commencement is suspended, it dost not negatively affect supplying power to Phnom Penh because other power sources – hydropower dams, coal-fired power plants, solar, and biomass power plants – have been put on the front lines to supply power in the dry season.”

For the 400 MW power plants, the government spent US$380 MW to import generators from Finland and Germany in mid-2019, aiming to increase power supplies to Phnom Penh.

Notably, two Chinese firms were constructing the power plants: CGGC-UN Power Co and China National Heavy Machinery Corporation. The plants are under the control of Electricite Du Cambodge (EDC). (Read more) and (Read more)

- Video Advertisement -

Related Post

Borey Peng Huoth Announces Exclusive Pre-Sale Event for New Phum Nimith Project in Chbar Ampov

Early access to prime locations within the prestigious Grand Star Platinum development starting this March Following the successful groundbreaking ceremony held on January 30, 2026, Borey Peng Huoth is pleased to announce the official pre-sale launch of its newest residential development, Phum Nimith. This highly anticipated event will take place over three days from March […]

Accelerating Connectivity: Mekong River Bridge Connecting Dei Edth-Thmor Kor Surpasses 35% Completion

Minister Peng Ponea inspects the strategic infrastructure project in Kandal province to ensure rigorous technical standards and timely delivery for the public The construction of the major bridge across the Mekong River Dei Edth-Thmor Kor connecting Dei Edth commune in Kien Svay district to Thmor Kor commune in Lvea Em district has reached a significant […]

Cambodia and Laos to Fast-Track Cross-Border Connectivity with New Ratanakiri-Attapeu Road Link

Joint inspection team to finalize construction zones this February to unlock new trade and economic opportunities Cambodia and Laos have reached a pivotal agreement to conduct a joint technical inspection aimed at defining the specific zones for a new road project connecting Ratanakiri province in Cambodia to Attapeu province in Laos. This initiative is a […]

Kratie City Drainage and Pumping Station Project Surpasses 68% Completion

Provincial authorities and ADB-funded initiative accelerate infrastructure development to eliminate seasonal flooding and boost local economic appeal Kratie City is undergoing a significant infrastructural transformation as the construction of its comprehensive drainage network and rainwater pumping station reaches 68 percent completion. This development is a key sub-project of the Fourth Greater Mekong Subregion Corridor Towns […]

Border Ring Road Project in Mondulkiri and Ratanakiri Surpasses 72% Completion in 13 Months

Cambodia’s historic border ring road project has reached a significant milestone, achieving an overall completion rate of 72.29% as of January 11, 2026. This monumental initiative is being realized through the “Border Infrastructure Fund,” fueled by enthusiastic contributions from citizens across the country to strengthen national security and enhance the livelihoods of those living in […]

Advancing Cambodia’s Maritime Ambition: Sihanoukville Deep-Sea Terminal Reaches Significant Construction Milestone

Phase one of the new container terminal achieves nearly 60 percent completion as the government accelerates its vision for a regional logistics hub The construction of the first phase of the Sihanoukville new deep-sea container terminal has made substantial progress, reaching 57.40 percent completion as of early 2026. During a review of the construction site’s […]