Construction of NR10 Connecting Battambang to Koh Kong 54% Complete

By the end of November 2021, the construction of 198km NR10 connecting Battambang to Koh Kong was 54.89% completed, according to the site inspection by the Minister of Public Works and Transport (MPWT) HE Sun Chanthol Friday 3 December.

HE Sun Chanthol also urged construction companies and technical consultants to closely monitor the construction work to ensure it follows technical standards to ensure long-term usage.

Stretching over 199km, the road links Samlot district in Battambang province to Koh Kong province passing through Veal Veng district in Pursat province. The project is being constructed with an investment of over US$188 million, which is a mixture of a Chinese loan and Cambodian government budget.

The project is being built in accordance with Chinese level 3 technical standards, paved with double-layers DBST, with a total width of 9m.

The route will also include the construction of 23 bridges with a length of 1,721m. Meanwhile, 65.89km of the road is a detour around the Cardamom mountain, as the engineering team try to avoid cutting the mountain to preserve the environment and wildlife.

With ground broken in March 2020, the road is being built by China Road and Bridge Corporation (CRBC) under the technical supervision of Guangzhou Wanan Construction Supervision Co., Ltd. and will take 48 months to complete, which will be around late 2023.

NR10 is an important artery of Cambodia’s national economy, helping connect the Khmer-Thai border to the deep seaport in Sihanoukville through Battambang and Kong Kong. With this route, cargo trucks do not have to pass through Phnom Penh, which is more cost and time effective.

- Video Advertisement -

Related Post

Progress Report on Romchek Irrigation System in Prey Veng Province

Significant strides have been made in the development of the Romchek irrigation system, which is now nearly 20% complete and poised to enhance agricultural productivity across the region. This comprehensive irrigation initiative is designed to serve a total area of nearly 2,000 hectares, ensuring both wet and dry rice fields receive the necessary water supply. […]

National Road 48 Rehabilitation Project Nears Completion

In a significant development for regional connectivity, the rehabilitation of National Road 48, which spans 148 kilometers from Sre Ambel to Koh Kong province, is now 94.30% complete. The ambitious project aims to enhance transportation, logistics, and tourism along this vital economic corridor. The progress was confirmed during a recent inspection led by His Excellency […]

Border Ring Road Construction Progress Approaches 40% Milestone

The construction progress of the highly anticipated border ring road has reached nearly 40%, marking a significant step forward for the project. Currently, approximately 39.92% of the total construction plan has been completed, as reported in a press release today. The initiative, funded by the Border Infrastructure Fund (BIF), aims to enhance connectivity along the […]

Construction Progress of Phnom Penh’s Drainage System Nears Completion

The ambitious project to build a comprehensive drainage system in western Phnom Penh is now 88% complete, with final touches expected to be finalized by July 2025. During a recent review, Ms. Koy Sodany, Permanent Secretary of State at the Ministry of Public Works and Transport and the project leader, confirmed the significant progress. The […]

Electric Bus Revolution in Siem Reap: A Step Towards Sustainable Transport

In an exciting development for eco-friendly public transport, Cambodia, in partnership with the Green Development Institute (GGGI), has unveiled plans for an electric bus system in Siem Reap province. The announcement came during the final workshop of the electric bus public transport system study, where three strategic routes and 33 waiting stations were officially designated. […]

Progress Report: Siem Reap River Improvement Project Phase 2 Nears Completion

The Siem Reap River Improvement Project Phase 2 is making significant strides, with the project now completed by 97%. The Siem Reap Provincial Administration announced on August 21, 2025, via its official Facebook page that the project is on track for completion by July 1, 2025. The ongoing work focuses on restoring the river and […]