Construction of NR10 Connecting Battambang to Koh Kong 54% Complete

By the end of November 2021, the construction of 198km NR10 connecting Battambang to Koh Kong was 54.89% completed, according to the site inspection by the Minister of Public Works and Transport (MPWT) HE Sun Chanthol Friday 3 December.

HE Sun Chanthol also urged construction companies and technical consultants to closely monitor the construction work to ensure it follows technical standards to ensure long-term usage.

Stretching over 199km, the road links Samlot district in Battambang province to Koh Kong province passing through Veal Veng district in Pursat province. The project is being constructed with an investment of over US$188 million, which is a mixture of a Chinese loan and Cambodian government budget.

The project is being built in accordance with Chinese level 3 technical standards, paved with double-layers DBST, with a total width of 9m.

The route will also include the construction of 23 bridges with a length of 1,721m. Meanwhile, 65.89km of the road is a detour around the Cardamom mountain, as the engineering team try to avoid cutting the mountain to preserve the environment and wildlife.

With ground broken in March 2020, the road is being built by China Road and Bridge Corporation (CRBC) under the technical supervision of Guangzhou Wanan Construction Supervision Co., Ltd. and will take 48 months to complete, which will be around late 2023.

NR10 is an important artery of Cambodia’s national economy, helping connect the Khmer-Thai border to the deep seaport in Sihanoukville through Battambang and Kong Kong. With this route, cargo trucks do not have to pass through Phnom Penh, which is more cost and time effective.

- Video Advertisement -

Related Post

Phnom Penh and Battambang Set for Expansion of Pedestrian Streets Following Successful Trial

In a significant move to enhance urban mobility and promote pedestrian-friendly environments, the Cambodian government is gearing up to construct additional pedestrian streets in both Phnom Penh and Battambang. This initiative follows the successful trial of pedestrian streets in Phnom Penh, which has garnered widespread public support. During a recent meeting held on February 11, […]

Progress on Clay-Thoma Kor Bridge Construction

The construction of the temporary steel bridge across the Mekong River at Clay-Thoma Kor is progressing steadily, with 5.40% of the work completed, as reported by His Excellency Phan Rim, Spokesperson for the Ministry of Public Works and Transport. Currently, the China Road and Bridge Corporation (CRBC) is actively working on the western side of […]

Progress Update on the Bassac River Bridge Project: 19% Completion Marked

The ambitious project to construct a bridge across the Bassac River has achieved a significant milestone, with 19% of the work now completed after 11 months of construction. The project, which connects Chak Angre Krom and Prek Pra, remains on schedule, with no delays reported, according to a Ministry of Public Works and Transport statement. […]

Progress Report on National Road 5: Final Section Construction Updates

As of early February 2025, significant progress has been made on the final section of National Road 5, stretching from Seri Sophon to Poipet. With a total length of 35.14 kilometers, this crucial infrastructure project is currently 29% complete and is on track for completion in 2026. The update was shared by His Excellency Phon […]

Phnom Penh Infrastructure Project Advancing Rapidly to Combat Flooding

In a significant step towards enhancing urban resilience, a major infrastructure project targeting flood prevention in the western districts of Phnom Penh is now over 66% complete. The initiative, which focuses on installing large-scale box culverts, is actively transforming National Road 4 and surrounding areas. Managed by the PPPP-TCM joint venture, this ambitious project encompasses […]

Bavet City Takes a Major Step Towards Sustainability: Landfill Project Underway

In an exciting development for Bavet City, the construction of a significant landfill project has officially commenced on a sprawling 21-hectare site in Trang Mtes village, located in the heart of Svay Rieng province. The groundbreaking ceremony, held on January 31, 2025, began a transformative initiative to enhance the city’s environmental infrastructure. This project is […]