Construction of NR2 and NR22 20% Complete

The construction and restoration of National Road 2 and 22 from Takmao to Ang Ta Saom has been 20% completed and is scheduled to finish in the first quarter of 2022, according to Ministry of Public Works and Transport spokesman Heang Sotheayuth.

Mr Sotheayuth told the Ministry of Information recently that since the ground-breaking ceremony in February 2020, the construction process has proceeded smoothly despite the COVID-19 pandemic and the recent flood.

The renovation covers a total length of 72km and is being undertaken with a budget US$56 million funded by the Republic of Korea together with the government fiscal budget.

The project includes road expansion as well as upgrading both roads to asphalt concrete and will take approximately 30 months to complete. (Read more)

- Video Advertisement -

Related Post

Progress Report: National Road No. 48 Restoration Nears Completion

The restoration and upgrade of National Road No. 48, stretching 148 kilometers from Sre Ambel to Koh Kong, has reached an impressive 78% completion as of the beginning of 2025, according to a statement from HE Phorn Rim, Spokesman of the Ministry of Public Works and Transport. The ambitious project, which commenced on January 3, […]

Major Infrastructure Development Takes Shape in Kandal Province

The China Road and Bridge Corporation (CRBC) is swiftly constructing a temporary steel bridge in Kandal province to facilitate drilling for a vital clay-stone bridge. HE Phorn Rim, the Ministry of Public Works and Transport spokesman, confirmed that this project aims to improve connectivity between the eastern outskirts of Phnom Penh and Xi Jinping Boulevard. […]

What has the border ring road construction project achieved two months after the construction site opened?

The project to build the border ring road, funded by nearly $27 million from the Border Infrastructure Fund, has made significant progress since the construction site opened on November 4, 2024.  Here are some key achievements of this historic project for Cambodia: Demining Operations: The team successfully cleared 1,462,500 square meters of unexploded ordnance, with […]

Dauntri Reservoir Dam Nears Completion with 91% Progress, Set to Open by October 2025

The Dauntri Reservoir Dam project in Battambang province has reached an impressive 91% completion, marking a crucial milestone in its mission to revolutionise water supply and agricultural productivity in the province. This landmark project, designed to enhance irrigation and flood management, is expected to be fully operational by October 2025. The announcement was made during […]

Japanese Ship to Make Historic First Docking at Cambodia’s New Ream Port

Samdech Techo Hun Sen, President of the Senate of Cambodia, confirmed that a Japanese ship will be the first vessel to dock at the newly inaugurated Ream Port. This historic event underscores the growing cooperation between Cambodia and Japan, particularly in security and infrastructure development. The commitment was made during a meeting with HE Akiba […]

Cambodia Accelerates Reservoir Registration with 1562 in Total, 13% of Them Registered

Cambodia’s Ministry of Water Resources and Meteorology has disclosed that the nation is home to 1,562 irrigation reservoirs, yet only 197 of them—representing a mere 13%—are officially registered. This crucial detail was highlighted during a meeting held on 26 December 2024, where officials underscored the reservoirs’ vital role in supporting agriculture and managing water resources. […]