ESIA Ongoing for New 72km Battambang-Siem Reap Road; 10 Major Decisions Made

Plans to construct a new road connecting Siem Reap and Battambang have seen progression, as the inter-ministerial committee has officially begun the Environmental and Social Impact Assessment (ESIA) for the project.

Held on Tuesday 8 February and led by Secretary of State of the Ministry of Environment HE Sabo Ojano, the meeting has given 10 orders to construction firms as follows:

1. The committee gives the greenlight to the project, but it must be done precisely.

2. The firm must have a clear work plan and must cooperate with local authorities and local communities regarding the impact resettlements and compensation for damages.

3. The project owner must put up signs to inform the public of the construction to avoid accidents.

4. The project owner must take into account the health and safety of workers in the project.

5. The project owner must properly manage the waste soil and rocks. Canals surrounding the construction site must be built to prevent wastewater from leaking into public spaces. If possible, a filtration system should be installed to reuse the wastewater.

6. The project owner must carefully manage solid and liquid waste, air pollution, noise, and vibration according to the ministry guidelines.

7. The project owner must plant trees around the project area and cooperate with officers in restoring and preserving nearby forest.

8. Project owners must help maintain surrounding roads nearby the project and educate their workers to obey the law.

9. The project owner must spray water regularly at least 3 times/day to avoid dust.

10. The project owner and the consulting company shall revise the report based on the inter-ministerial meeting decision and include it in the full ESIA report.

Up completion, this new national road will pass through three provinces including Battambang, Banteay Meanchey and Siem Reap, and help shorten the travelling distance between the two provinces by up to 69 kilometres.

The project was studied at the request of Prime Minister Hun Sen in early 2020. (Read more)

 

- Video Advertisement -

Related Post

Techo International Airport Nears Completion: A New Gateway to Cambodia

In an exciting development for Cambodia’s aviation sector, the Techo International Airport construction project is now over 94% complete, with the total investment reaching nearly USD 1.4 billion. This ambitious project promises to transform the country’s skyways and enhance domestic and international travel connectivity. As of late December 2024, critical infrastructure components, including the Passenger […]

Chinese Company Pledges to Complete Mondulkiri Wind Power Station by 2026

In a significant commitment to renewable energy in Cambodia, HK OASIS Power Energy Development Co., Ltd. has vowed to complete the construction of a 150-megawatt wind power station in Mondulkiri province by 2026. This pledge was made by Mr. Wang Junwei, the company’s representative, during a meeting with HE Chea Vuthy, Secretary General of the […]

Serei Sophorn Welcomes the New 11 hectares of Landfill

In a significant development to enhance urban environmental management around the Tonle Sap Lake, the government officially inaugurated over 11 hectares of landfill on January 17, 2025. This project, part of the Phase 2 initiative, received support through a concessional loan from the Asian Development Bank (ADB). The landfill in Kangvea village of Sangkat Kampong […]

China Approves Highest & Largest Hydropower Dam in Tibet Worth USD 127 Billion Amid Global Concerns

China has approved the construction of the world’s largest hydropower dam on the lower Yarlung Tsangpo River in Tibet, with an estimated cost of USD 127 billion. The project, poised to generate three times more energy than the Three Gorges Dam, is expected to redefine renewable energy development globally but has raised significant concerns about […]

Cambodia Welcomes 17 New Investment Projects Worth USD 150 Million in January 2025

In an exciting start to the year, Cambodia’s investment landscape is poised for growth as the country received a notable infusion of capital with 17 new investment projects. These initiatives, collectively valued at approximately USD 150 million, were registered during the inaugural “One Window Service Office” (OWSO) meeting for 2025, held on 15 January, chaired […]

Progress Update on Kampong Thom Dam Project: 25% Completion Mark Achieved

Construction on the Kampong Kor Dam is progressing steadily, with 25% of the project now completed. HE Chan Sinath, Secretary of State, provided this update during an inspection of the project on 12 January 2025. During the inspection, HE Chan Sinath outlined the project’s current status, specifying that the dam’s construction has reached 10%, while […]