MPWT writes warning letter to company constructing National Road 2 and Road 22

The Ministry of Public Works and Transport (MPWT) has issued a warning letter to Korean Company Hanshin contracted to build National Road 2 and National Road 22 following the discovery of delays in construction works, inadequate machinery equipment on sites, and lack of technical expertise in the implementation.
The warning was made by MPWT Minister, H.E Sun Chanthol, during his inspection visit on the construction of National Road 11 on 04 May 2020.

The minister decided to take such action following unannounced site visits two weeks ago with the Secretary of State for Road Technique, Director General of Technique, and a photographer visited the site of National Road 2 and 22.

“…on the road construction from Phnom Penh to Takeo, there are only two machines. No one was working on the National Road 2 project site, and there is one group working on National Road 22 site. When I asked, they said the machinery is in Vietnam. I got it now, but when will it be brought here? Why don’t they hire machinery in Cambodia instead? If it is later than scheduled, the company will be fined…,” rebuked Chanthol publicly.

“Tomorrow [05 May], Hanshin Engineering & Construction Co., Ltd will receive the warning letter from MPWT giving some time for the company to deal with the existing problems or the company will definitely face the MPWT,” added Chanthol.

The warning letters were to be sent to the company and also to the Embassy of South Korea and to the Economic Development Cooperation Fund (EDCF) to inform them of the current situation.

In the past, the Minister has taken similar strong measures on other projects including the company building the road from Skun to Siem Reap which required reconstruction and adding 3cm of rubber. Another case was the removal of 8 foreign technicians on the project from Kampot to Veal Rinh due to non-compliance with technical standards.

For other road construction projects, HE emphasized that the construction of all roads in Cambodia such as National Road 5, National Road 11, National Road 13 and some other roads are in progress, unlike construction on National Road 2 and National Road 22 construction, even though Cambodia is currently facing the COVID-19 pandemic.

National Road 2 and Road 22 have a total length of 72km. The restoration section of National Road 2 covers a total length of 62.56km s, from Takmao roundabout to Chambak and from Chambak to Doun Kaev roundabout in Takeo province. The restoration section of National Road 22 covers a total length of 9.61km, from Doun Kaew roundabout to the Angk Ta Saom area. The project is expected to cost approximately US$56 million in total, which is financed by the South Korean government and Cambodian government budget. (Read more)

- Video Advertisement -

Related Post

Construction Progress of Phnom Penh’s Drainage System Nears Completion

The ambitious project to build a comprehensive drainage system in western Phnom Penh is now 88% complete, with final touches expected to be finalized by July 2025. During a recent review, Ms. Koy Sodany, Permanent Secretary of State at the Ministry of Public Works and Transport and the project leader, confirmed the significant progress. The […]

Electric Bus Revolution in Siem Reap: A Step Towards Sustainable Transport

In an exciting development for eco-friendly public transport, Cambodia, in partnership with the Green Development Institute (GGGI), has unveiled plans for an electric bus system in Siem Reap province. The announcement came during the final workshop of the electric bus public transport system study, where three strategic routes and 33 waiting stations were officially designated. […]

Progress Report: Siem Reap River Improvement Project Phase 2 Nears Completion

The Siem Reap River Improvement Project Phase 2 is making significant strides, with the project now completed by 97%. The Siem Reap Provincial Administration announced on August 21, 2025, via its official Facebook page that the project is on track for completion by July 1, 2025. The ongoing work focuses on restoring the river and […]

National Road 7 Expansion Project on Track for Early Completion

The ambitious project to expand and improve National Road 7, transforming it from a two-lane to a four-lane highway, is currently 43% complete and is expected to finish ahead of schedule. The 45.5-kilometre stretch of road runs from Vang Vong Moul Skun in Cheung Prey District to the base of the Kizuna Bridge in Kampong […]

India-Myanmar-Thailand Trilateral Highway Stalled Amid Conflict in Myanmar

The USD 114 billion India-Myanmar-Thailand Trilateral Highway, a crucial 1,360-kilometre infrastructure project designed to enhance ASEAN economic integration and strengthen India’s trade presence in Southeast Asia, faces major setbacks due to ongoing instability in Myanmar. Designed as a four-lane highway, the Trilateral Highway is part of India’s broader infrastructure vision, which aims to extend road […]

The Construction of Sewage System and Rainwater Pumping Station is Officially Ground Breaking in Kratie City

The construction of a vital sewerage system and rainwater pumping station, officially ground-breaking on 5th March in Kratie City, is backed by over USD 7 million in funding through the Asian Development Bank-supported Rabien 4 urban development project. H.E. Poo Manit, Deputy Director General of the Project at the Ministry of Public Works and Transport, […]