MoWRAM Initiates Swift Upgrades on Irrigation Systems Across Five Provinces to Beat Rainy Season

In a significant move to enhance agricultural productivity ahead of the impending rainy season, the Ministry of Water Resources and Meteorology (MoWRAM) is fast-tracking the repair and improvement of critical irrigation systems in five provinces. This ambitious initiative, targeting key infrastructures including the North Melang Chrey Canal in Kampong Speu province and the Spean Sreng Irrigation System in Banteay Meanchey province among others, was detailed in a recent update from the Ministry on 24 April 2024.

The ministry’s latest report unveils substantial progress in the refurbishment efforts across the designated areas. Notably, the North Meling Chrey Canal project in Sangkat Rokar Thom, Kampong Speu province has reached a 50% completion milestone, with extensive repairs conducted over a 14,500-metre stretch. This project alone encompasses 27 construction sites, with a 10% completion rate, alongside three new constructions at 35% completion.

Secondly, in Banteay Meanchey province, the Spean Sreng Irrigation System which is located in Spean Sreng commune, Phnom Srok district has seen 45 construction sites achieving a 20% completion rate, with an additional new construction project reaching 30%.

Thirdly, the Chhnuk Trou Irrigation System in Prey Sniet and Reap communes, Pearang district, Prey Veng province reports a 42% completion rate across 27 construction sites and five new projects.

Fourth, the Spean Sreng Trapeang Ambel Irrigation System in Siem Reap province has 34 buildings under rehabilitation at 10% completion and a new building at 20%.

Fifth, the Tumnob Lok Irrigation System in Oddar Meanchey province is also under significant renovation. The project has initiated work on two new sites.

By enhancing water management and supply, MoWRAM aims to mitigate potential adverse effects of the rainy season, ensuring sustainability and resilience in the face of climate variability.

- Video Advertisement -

Related Post

The Government Announces New Opening Date for Techo International Airport

In a significant new update for travelers and the aviation industry, the State Secretariat of Civil Aviation has announced a revised opening date for the much-anticipated Techo International Airport in Takhmao. Originally set to open on July 10, 2025, the grand opening is now scheduled for September 9, 2025, as indicated in a notice issued […]

National Road 10 Completed: Enhancing Regional Connectivity

The construction of National Road 10, stretching over 197.36 kilometers, has been officially completed, marking a significant milestone in the region’s infrastructure development. The road is now fully operational and has undergone a thorough inspection by a team of skilled technicians to ensure its longevity and adherence to technical standards. A detailed assessment was conducted […]

Singapore Resumes Construction of Changi Airport’s Largest Passenger Terminal After Pandemic Delay

In a significant milestone for Singapore’s aviation sector, the construction of Terminal 5 (T5) at Changi Airport has officially commenced following a two-year pause brought on by the COVID-19 pandemic. The groundbreaking ceremony, which took place on May 14, 2025, was graced by Prime Minister Lawrence Wong. Prime Minister Wong highlighted that the new terminal […]

Doun Tri Dam Construction 97% Completion

  The construction of the Doun Tri Dam in Battambang province is now 97% complete, with final completion expected by October 2025. This significant infrastructure project, located in Rukkakiri district, is being financed through concessional loans from the Republic of Korea. During a project progress review led by His Excellency Tho Jetha, Minister of Water […]

Irrigation System Project in Banteay Meanchey and Battambang is 75% Completed

  Banteay Meanchey and Battambang provinces are making strides in agricultural development as the irrigation system construction project reaches a significant milestone. As of May 7, 2025, the project is 75% complete, thanks to financing from the Korean Eximbank. During a progress review meeting led by His Excellency Minister Tho Jetha, Minister of Water Resources […]

Mekong River Bridge in Kratie Province Nearing Completion

As of early May 2025, the Mekong River Bridge in Kratie Province is making impressive strides, with construction now 94% complete. The 1,761-meter-long bridge is expected to temporarily open to traffic in September 2025, pending the completion of final touches. The update was shared on the official Facebook page of the Ministry of Public Works […]