NR 33 Rehabilitation Surpasses Expectations with Over 35% Completion Ahead of Schedule

The rehabilitation and enhancement project of NR 33 has surged ahead, surpassing anticipated benchmarks by an impressive margin of 35.12%. The infrastructure initiative, executed by China Bridge and Road Corporation (CRBC), has not only defied time constraints but also underscored the potential for swift infrastructure advancements in Cambodia.

Elevating the significance of this achievement, HE Pal Chandara, Secretary of State at the Ministry of Public Works and Transport, undertook an on-site assessment accompanied by CRBC’s technical team on 18 August 2023. The verdict was resounding—the project’s pacing had outpaced initial projections, bearing testament to the efficacy of collaborative efforts and meticulous execution.

The project’s current status, per official ministry data, showcases the substantial strides undertaken to date. The clearing and preparation phase has spanned a notable distance of 52.57km, while sub-grade road construction has been accomplished over 49.87km. Further emphasizing the swift headway, sub-base construction has covered 37.66km. This resounding progress underscores that not only is the project well underway but also that its execution is racing ahead of the envisaged timeline.

Looking ahead, HE Pal Chandara underlined the meticulous scrutiny awaiting the project’s integrity. As September beckons, a dedicated technical team, armed with precision equipment, will undertake comprehensive testing. The paramount aim is to ensure that NR 33’s execution aligns with standards of durability, quality, and performance.

While heralding this achievement, HE Pal Chandara also extended a solemn reminder to the executing agency—adherence to technical specifications and stringent safety protocols are non-negotiable. The well-being of the construction team and the safety of travelers traversing the road demand meticulous vigilance, reinforcing the commitment to harmonious and secure progress.

Reflecting on the project’s significance, it’s pivotal to highlight that the endeavor to revitalize NR 33 is underpinned by a budget exceeding US$61 million, substantiated through a concessional loan from China. This financial foundation, coupled with the Royal Government of Cambodia’s contribution and resolute approach to mitigating adverse impacts and taxes, amplifies the transformative potential of this ambitious venture. (Read more)

 

 

- Video Advertisement -

Related Post

The rapid progress of riverbank construction in Kampong Cham has reached 65%

In a remarkable display of swift action and engineering prowess, the construction of a vital riverbank in the Srey Santhor district has surged ahead, reaching an impressive 65% completion in under a month. The Moan Dob Leu village project, Meanchey commune, commenced on December 23, 2024, following the alarming collapse of the Mekong River bank […]

Kampong Cham Province Achieved Significant Infrastructure Development in 2024

In a remarkable stride towards improving its infrastructure, Kampong Cham Province has completed over 119 kilometers of road construction in 2024. This achievement was announced by HE Un Chanda, the Governor of Kampong Cham Province, during a press conference. During the year 2024 alone, the province welcomed 27 projects aimed at developing DBST (Dense Bituminous […]

Major Progress Made on Flood Prevention in Western Phnom Penh

In a significant step towards mitigating flooding in western Phnom Penh, the ambitious drainage and drainage system restoration project has reached a milestone, now standing at 50.50% completion as of January 5, 2025. This essential infrastructure initiative, spearheaded by the General Department of Wastewater Treatment System under the Ministry of Public Works and Transport, aims […]

National Road 7 Expansion Project Progresses, Reaches 28.76% Completion

In a significant step towards enhancing Cambodia’s infrastructure, the ambitious project to restore and expand National Road No. 7 has reached an impressive 28.76% completion as of early January 2025. This major development was confirmed during a thorough inspection led by HE Lim Sidenin, Secretary of State of the Ministry of Public Works and Transport, […]

Progress Report: National Road No. 48 Restoration Nears Completion

The restoration and upgrade of National Road No. 48, stretching 148 kilometers from Sre Ambel to Koh Kong, has reached an impressive 78% completion as of the beginning of 2025, according to a statement from HE Phorn Rim, Spokesman of the Ministry of Public Works and Transport. The ambitious project, which commenced on January 3, […]

Major Infrastructure Development Takes Shape in Kandal Province

The China Road and Bridge Corporation (CRBC) is swiftly constructing a temporary steel bridge in Kandal province to facilitate drilling for a vital clay-stone bridge. HE Phorn Rim, the Ministry of Public Works and Transport spokesman, confirmed that this project aims to improve connectivity between the eastern outskirts of Phnom Penh and Xi Jinping Boulevard. […]